The U.S. Nuclear Regulatory Commission is in the process of rescinding or revising guidance and policies posted on this webpage in accordance with Executive Order 14151 Ending Radical and Wasteful Government DEI Programs and Preferencing, and Executive Order 14168 Defending Women From Gender Ideology Extremism and Restoring Biological Truth to the Federal Government. In the interim, any previously issued diversity, equity, inclusion, or gender-related guidance on this webpage should be considered rescinded that is inconsistent with these Executive Orders.

Application Review Schedule for Willow Creek

The following table summarizes the key milestones in the schedule that the U.S. Nuclear Regulatory Commission (NRC) has established for its review of the application that Uranium One USA, Inc. submitted to renew its license for the Willow Creek in situ recovery facility.

Key Milestones Completion Date
Actual - A
Target - T
Application Tendered 5/30/08 – A
Acceptance Review
Docketing Decision Letter Issued/Acceptance Review Complete
12/24/08 – A
Safety Review
Requests for Additional Information (RAIs) Issued to Applicant
3/24/09 – A
Final Safety Evaluation Report (SER) completed
10/2011 – T
Environmental Review
RAIs Issued to Applicant
3/24/09 – A
Draft EA issued
5/25/10 – A
Public comment period
6/9/10 – A
Final EA issued
7/7/11 – A
License
Licensing Action Completed
10/2011 – T