Application Review Schedule for SHINE Medical Technologies LLC
SHINE Medical Technologies, LLC submitted an application for a construction permit to build a medical radioisotope production facility. The following table summarizes the U.S. Nuclear Regulatory Commission’s key milestones for reviewing this application.
Key Milestones |
Completion Date
Actual—A
Target—T |
Application Tendered |
|
Receipt of Environmental Report (Part One of Two-Part Construction Permit Application)
|
03/2013—A |
Receipt of Preliminary Safety Analysis Report (Part Two of Two-Part Construction Permit Application)
|
05/2013—A |
Acceptance Review |
Acceptance of Part One of Application for Docketing
|
07/2013—A |
Acceptance of Part Two of Application for Docketing
|
12/2013—A |
Environmental Review Schedule |
Environmental Scoping Meeting
|
07/2013—A |
Environmental Site Audit
|
08/2013—A |
Issuance of Request for Additional Information on Environmental Report
|
08/2013—A |
Issuance of Supplemental Requests for Additional Information on Environmental Report
|
09/2014–01/2015—A |
NUREG Publication of Draft Environmental Impact Statement
|
05/2015—A |
NUREG Publication of Final Environmental Impact Statement
|
10/2015—A |
Safety Review Schedule |
Issuance of Request for Additional Information on Preliminary Safety Analysis Report
|
09/2014—A |
Issuance of Supplemental Requests for Additional Information on Preliminary Safety Analysis Report
|
01/2015—A
03/2015—A
04/2015—A
09/2015—A |
Advisory Committee on Reactor Safeguards Subcommittee Meetings
|
06/2015—A
08/2015—A
09/2015—A |
Completion of Draft Safety Evaluation Report
|
09/2015—A |
Advisory Committee on Reactor Safeguards Full Committee Meeting
|
10/2015—A |
Completion of Safety Evaluation Report
|
10/2015—A |
NUREG Publication of Safety Evaluation Report
|
08/2016—A |
Hearing |
Mandatory Hearing on Construction Permit Application
|
12/2015—A |
License |
Decision on Construction Permit
|
02/2016—A |