Application Review Schedule for Northwest Medical Isotopes, LLC

The following table summarizes the key milestones in the schedule that the U.S. Nuclear Regulatory Commission (NRC) has established for its review of the application that Northwest Medical Isotopes, LLC submitted to obtain a construction permit for a medical radioisotope production facility.

Key Milestones Completion Date
Actual—A
Target—T
Application Tendered  
Receipt of Environmental Report (Part One of Two-Part Construction Permit Application)
02/2015—A
Receipt of Preliminary Safety Analysis Report (Part Two of Two-Part Construction Permit Application)
07/2015—A
Acceptance Review
Acceptance of Part One of Application for Docketing
06/2015—A
Acceptance of Part Two of Application for Docketing
12/2015—A
Environmental Review Schedule
Environmental Site Audit
09/2015—A
Issuance of Request for Additional Information on Environmental Report
11/2015—A
Environmental Scoping Meeting in Columbia, MO
12/2015—A
Issuance of Supplemental Request for Additional Information on Environmental Report
01/2016—A
NUREG Publication of Draft Environmental Impact Statement
12/2016—T
10/2016—A
Draft Environmental Impact Statement public meeting
12/06/2016—T
12/06/2016—A
NUREG Publication of Final Environmental Impact Statement
 
05/2017—T

05/2017—A
Safety Review Schedule
Issuance of Request for Additional Information on Preliminary Safety Analysis Report
08/2016—T
09/2016—A
Issuance of Supplemental Request for Additional Information on Preliminary Safety Analysis Report
09/2016—A
Completion of Draft Safety Evaluation Report
06/2017—T
Advisory Committee on Reactor Safeguards Subcommittee Meeting
06/2017—A
07/2017—A
08/2017—A
09/2017—A
Advisory Committee on Reactor Safeguards Full Committee Meeting
11/2017—A
Completion of Safety Evaluation Report
11/2017—A
NUREG Publication of Safety Evaluation Report
TBD
Hearing
Mandatory Hearing on Construction Permit Application
01/23/2018 – A
License
Decision on Construction Permit
05/03/2018 – A