Life cycle timeline showing current status, consisting of 6 various stages of status (Pre-Licensing, Licensing, Construction, Operating, Operating with Intent to Decommission, Decommissioning) with the current status (Licensing) shown with color background and white text, and the other available statuses are greyed out

Photo of Orano Enrichment USA building 

Location: Oak Ridge, TN
Licensee: Orano Enrichment USA, LLC
License Number: TBD
License Expires: TBD
Docket Number: 07007038

Facility Type: Uranium Enrichment
Facility Status: Licensing Application

Press Releases
Upcoming Meetings
Past Meetings

Orano Dashboards (Pending)


Facility Information

Documentation

License Application

Announcements

Automatic Email Distributions (GovDelivery)

NRC Contacts

  • Safety Project Manager
    Osiris Siurano-Perez (301-415-7827) and Katie Barnes (610-337-5323)
  • Environmental Project Manager
    Stacey Imboden (301-415-2462) and Patrick Donohue (301-415-5237)
  • Public Affairs:
    800-368-5642 or 301-415-8200

Related Information​

Review Process

Safety and Safeguards ReviewEnvironmental Review

Application (Completed)

  • Safety and safeguards report was received on March 27, 2026

Acceptance (Completed)

  • NRC accepted the application for docketing on May 21, 2026.
  • Acceptance Letter: (ML26134A324

Develop Safety and Safeguards Evaluation Report (In Process)

  • Develop Requests for Additional Information
  • Develop Draft Safety Evaluation Repot

Application (Completed)

  • Environmental report was received January 30, 2026

Acceptance (Completed)

  • NRC accepted the application for docketing on May 21, 2026.
  • Acceptance Letter: (ML26134A324

Develop Environmental Impact Statement (In Process)

  • Scoping
  • Develop Request for Additional Information

To top of page

Page Last Reviewed/Updated Tuesday, June 16, 2026

Page Last Reviewed/Updated Tuesday, June 16, 2026