Due to a lapse in appropriations, the NRC has ceased normal operations. However, excepted and exempted activities necessary to maintain critical health and safety functions—as well as essential progress on designated critical activities, including those specified in Executive Order 14300—will continue, consistent with the OMB-Approved NRC Lapse Plan.

Search Results

Displaying 421 - 430 of 455

Power Reactor Status Report for May 6, 2002

…     BROWNS FERRY 2 100     *   BROWNS FERRY 3 100         BRUNSWICK 1 100         BRUNSWICK 2 100         CATAWBA 1 0 … OUTAGE     BYRON 1 100         BYRON 2 100   MEASURED STEAM GENERATOR TUBE LEAKAGE = 35 GPD *   CLINTON 1 15   … 2 96     *   DRESDEN 3 100         DUANE ARNOLD 1 94   100% ELECTRICAL CAPABILITY     FERMI 2 100         KEWAUNEE 1 0 …

Power Reactor Status Report for November 2, 2001

…     BROWNS FERRY 2 100         BROWNS FERRY 3 100         BRUNSWICK 1 100         BRUNSWICK 2 100         CATAWBA 1 … TURBINE GENERATOR VIBRATION *   BYRON 1 99   100% OF RATED ELECTRICAL CAPABILITY     BYRON 2 100         CLINTON 1 100 …   PRAIRIE ISLAND 2 0 10/31/2001 MANUAL REACTOR TRIP DUE TO STEAM LEAK - SEE EVENT #38448     QUAD CITIES 1 100         …

Power Reactor Status Report for August 13, 2015

…       Browns Ferry 2 100         Browns Ferry 3 100         Brunswick 1 100         Brunswick 2 100         Catawba 1 …   Byron 1 100         Byron 2 100         Clinton 99   100% ELECTRICAL CAPABILITY     D.C. Cook 1 100         D.C. Cook …         Diablo Canyon 1 98   MOISTURE SEPARATOR REHEATER STEAM REDUCTION DUE TO BREAKER TRIP     Diablo Canyon 2 100 …

Power Reactor Status Report for August 4, 2014

…     Ginna 2   TURBINE TAKEN OFFLINE FOR REPAIR TO MAIN STEAM VALVE INSTRUMENT AIR LINE *   Hope Creek 1 100         … PUMP LEAK INSIDE DRYWELL *   Browns Ferry 3 100         Brunswick 1 100         Brunswick 2 100         Catawba 1 …   Byron 1 100         Byron 2 100         Clinton 98   100% ELECTRICAL CAPABILITY     D.C. Cook 1 100         D.C. Cook …

Power Reactor Status Report for July 14, 2014

…       Browns Ferry 2 100         Browns Ferry 3 100         Brunswick 1 100         Brunswick 2 100         Catawba 1 …   Byron 1 100         Byron 2 100         Clinton 98   100% ELECTRICAL CAPABILITY     D.C. Cook 1 100         D.C. Cook 2 48   STEAM LEAK REPAIR COMPLETE - PLANT ON CHEMISTRY HOLD PRIOR …

Power Reactor Status Report for August 11, 2013

… 0 08/09/2013 FORCED OUTAGE - AUTOMATIC REACTOR TRIP ON LOW STEAM GENERATOR WATER LEVEL - SEE EN# 49260 - CURRENTLY …       Browns Ferry 2 100         Browns Ferry 3 100         Brunswick 1 100         Brunswick 2 22   HOLDING POWER WITH …   Byron 1 100         Byron 2 100         Clinton 97   100% ELECTRICAL CAPABILITY     D.C. Cook 1 100   MINIMUM …

Power Reactor Status Report for December 4, 2013

… Bottom 3 100         Pilgrim 1 10   TURBINE OFFLINE DUE TO STEAM LEAK IN CONDENSER BAY *   Salem 1 100         Salem 2 …       Browns Ferry 2 100         Browns Ferry 3 100         Brunswick 1 100         Brunswick 2 100         Catawba 1 …   Byron 1 100         Byron 2 100         Clinton 97   100% ELECTRICAL CAPABILITY     D.C. Cook 1 100         D.C. Cook …

Power Reactor Status Report for April 27, 2014

…       Browns Ferry 2 100         Browns Ferry 3 100         Brunswick 1 100         Brunswick 2 81   INCREASING POWER TO …   Byron 1 100         Byron 2 100         Clinton 98   100% ELECTRICAL CAPABILITY     D.C. Cook 1 100         D.C. Cook … 0 01/31/2014 REFUELING OUTAGE     Dresden 2 17   STEAM CHEST WARMING *   Dresden 3 100         Duane Arnold …

Power Reactor Status Report for April 25, 2015

… REFUELING OUTAGE     Salem 1 55   TROUBLE SHOOTING STEAM GENERATOR FEEDPUMP *   Salem 2 100         Seabrook 1 …       Browns Ferry 2 100         Browns Ferry 3 100         Brunswick 1 100         Brunswick 2 100         Catawba 1 … *   Clinton 92   COASTDOWN TO REFUELING OUTAGE 100% ELECTRICAL CAPABILITY *   D.C. Cook 1 100         D.C. Cook …

Power Reactor Status Report for March 8, 2017

… 02/24/2017 REFUELING OUTAGE     Browns Ferry 3 100         Brunswick 1 92   INCREASING POWER FOLLOWING ROD PATTERN …       Turkey Point 4 100         Vogtle 1 99   TESTING MAIN STEAM VALVES *   Vogtle 2 100         Watts Bar 1 100       … REFUELING OUTAGE     Byron 2 100         Clinton 99   100% ELECTRICAL CAPABILITY *   D.C. Cook 1 100         D.C. Cook …