Due to a lapse in appropriations, the NRC has ceased normal operations. However, excepted and exempted activities necessary to maintain critical health and safety functions—as well as essential progress on designated critical activities, including those specified in Executive Order 14300—will continue, consistent with the OMB-Approved NRC Lapse Plan.

Search Results

Displaying 1261 - 1270 of 8197

Power Reactor Status Report for July 3, 2001

…         GINNA 1 100         HOPE CREEK 1 100         INDIAN POINT 2 100         INDIAN POINT 3 100         LIMERICK 1 100         LIMERICK 2 100   … 06/20/2001 MAINTENANCE OUTAGE     PERRY 1 100         POINT BEACH 1 100         POINT BEACH 2 100     *   PRAIRIE ISLAND …

Power Reactor Status Report for July 2, 2001

…         GINNA 1 100         HOPE CREEK 1 100         INDIAN POINT 2 100         INDIAN POINT 3 100         LIMERICK 1 100         LIMERICK 2 100   … 06/20/2001 MAINTENANCE OUTAGE     PERRY 1 100         POINT BEACH 1 100         POINT BEACH 2 75   LOAD FOLLOWING *   …

Power Reactor Status Report for July 1, 2001

…         GINNA 1 100         HOPE CREEK 1 100     *   INDIAN POINT 2 100         INDIAN POINT 3 100         LIMERICK 1 100         LIMERICK 2 100   … 06/20/2001 MAINTENANCE OUTAGE     PERRY 1 100         POINT BEACH 1 100         POINT BEACH 2 97     *   PRAIRIE ISLAND …

Power Reactor Status Report for June 30, 2001

…         GINNA 1 100         HOPE CREEK 1 93     *   INDIAN POINT 2 100         INDIAN POINT 3 100         LIMERICK 1 100         LIMERICK 2 100   … 06/20/2001 MAINTENANCE OUTAGE     PERRY 1 100         POINT BEACH 1 100     *   POINT BEACH 2 15   TURBINE LATCHED BUT …

Power Reactor Status Report for June 29, 2001

…         GINNA 1 100         HOPE CREEK 1 100         INDIAN POINT 2 100         INDIAN POINT 3 100         LIMERICK 1 100         LIMERICK 2 95   … 06/20/2001 MAINTENANCE OUTAGE     PERRY 1 100         POINT BEACH 1 95   HOLDING POWER DUE TO CIRC WATER PROBLEM *   …

Power Reactor Status Report for June 28, 2001

…         GINNA 1 100         HOPE CREEK 1 100         INDIAN POINT 2 100         INDIAN POINT 3 100         LIMERICK 1 100         LIMERICK 2 0 … 06/20/2001 MAINTENANCE OUTAGE     PERRY 1 100         POINT BEACH 1 80   REDUCED POWER DUE TO CIRC WATER PROBLEMS CAUSED …

Power Reactor Status Report for June 27, 2001

…         GINNA 1 100         HOPE CREEK 1 100         INDIAN POINT 2 100         INDIAN POINT 3 100         LIMERICK 1 100         LIMERICK 2 0 … 06/20/2001 MAINTENANCE OUTAGE     PERRY 1 100         POINT BEACH 1 100         POINT BEACH 2 100         PRAIRIE ISLAND …

Power Reactor Status Report for June 26, 2001

…         GINNA 1 100         HOPE CREEK 1 100         INDIAN POINT 2 100         INDIAN POINT 3 100         LIMERICK 1 100         LIMERICK 2 100   … 06/20/2001 MAINTENANCE OUTAGE     PERRY 1 100         POINT BEACH 1 100         POINT BEACH 2 100         PRAIRIE ISLAND …

Power Reactor Status Report for June 25, 2001

…         GINNA 1 100     *   HOPE CREEK 1 100     *   INDIAN POINT 2 100         INDIAN POINT 3 100         LIMERICK 1 100         LIMERICK 2 100   … 06/20/2001 MAINTENANCE OUTAGE     PERRY 1 100     *   POINT BEACH 1 100         POINT BEACH 2 100         PRAIRIE ISLAND …

Power Reactor Status Report for June 24, 2001

… POWER FOR TURBINE VALVE TEST AND ROD SHUFFLE *   INDIAN POINT 2 100         INDIAN POINT 3 100         LIMERICK 1 100         LIMERICK 2 100   … OUTAGE     PERRY 1 94   INCREASING POWER *   POINT BEACH 1 100         POINT BEACH 2 100         PRAIRIE ISLAND …