Information Notice No. 84-67: Recent Snubber Inservice Testing with High Failure Rates
SSINS No.: 6835 IN 84-67 UNITED STATES NUCLEAR REGULATORY COMMISSION OFFICE OF INSPECTION AND ENFORCEMENT WASHINGTON, D.C. 20555 August 17, 1984 Information Notice No. 84-67: RECENT SNUBBER INSERVICE TESTING WITH HIGH FAILURE RATES Addressees: All nuclear power facilities holding an operating license (OL) or a construction permit (CP). Purpose: This information notice is provided as a notification of a potentially significant problem pertaining to recent snubber inservice testing that resulted in high failure rates. It is expected that recipients will review the information for applicability to their facilities and consider actions, if appropriate, to preclude a similar problem occurring at their facilities. However, suggestions contained in this information notice do not constitute NRC requirements and, therefore, no specific action or written response is required. Description of Circumstance: The following recent events involving snubber inservice testing with high failure rates have been reported: 1. On October 17, 1983, the Consumers Power Company reported [Licensee Event Report (LER) 83-063] the failure of both of the tested steam generator hydraulic snubbers to lock up during their inservice test at the Palisades Plant. The cause was attributed to insufficient counter boring of the valve block end-cap for the hydraulic snubber, which inhibited the shuttle valve from properly closing the appropriate block port. Inspection of the remaining 14 hydraulic snubbers revealed the same defect in 3 additional snubbers (31% over all failure rate). All defective snubbers were reworked to ensure proper operation. The hydraulic snubbers were ITT Grinnel Figure 200 (8 in. bore by 5 in. stroke). 8408140208 . IN 84-67 August 17, 1984 Page 2 of 4 ITT Grinnel indicated in a conversation that they felt the cause of the problem was the use of a nonstandard spring that gave the snubbers a higher lockup velocity. It was the longer compressed length of this spring that prevented proper shuttle valve positioning. ITT Grinnel also indicated that they were not aware of any other facilities with this non standard spring. 2. On April 16, 1984, the Virginia Electric and Power Company reported (LER 84-006) the failure of a number of hydraulic and mechanical snubbers at Surry Power Station Unit 1 to pass the inservice testing required by their Technical Specifications. These tests, conducted in March 1984, were a continuation of tests initially performed in March 1983. All numbers presented below and in the tables are totals of the 1983 and 1984 tests. Of the 160 hydraulic snubbers tested, failures were found in 48 (30%). The modes of failure are shown in Table 1. Twenty-one of the hydraulic snubbers were reset to design conditions and reinstalled. Of the remaining 27 hydraulic snubbers, 23 had been disassembled as of the date of the report to determine the cause of failure. The causes of failure are shown in Table 2. To preclude any generic concerns with the ITT Grinnel Lynair-type snubbers (67% of the failures were with this type), the utility plans on replacing as many as possible with ITT Grinnel Miller-type snubbers. Of the 66 mechanical snubbers tested, failures were found in 21 (44%). The modes of failure are shown in Table 3. Five of the mechanical snubbers were disassembled to determine the cause of failure. Of these, three had no observable defect and two had broken metallic parts in the mechanism. All of the mechanical snubbers are Pacific Scientific snubbers. 3. On April 25, 1984, the Florida Power and Light Company notified the NRC resident inspector of their intention to shut down Turkey Point Plant Unit 3 to test the mechanical snubbers in the unit. They indicated that they were taking this action because of the high number of failures observed when the mechanical snubbers in Turkey Point Plant Unit 4 were tested. Of the approximately 100 mechanical snubbers in each unit, 31 failures had been observed in Unit 4 and 46 failures were found in Unit 3. This did not include 17 snubbers in Unit 4 that were found with the telescoping cylinder not staked at the ball nut thread joint. The modes of failure are shown in Table 4. All of the mechanical snubbers are Pacific Scientific snubbers. 4. On June 25, 1984, the Commonwealth Edison Company verbally reported the failure of the steam generator hydraulic snubbers at Braidwood Station to pass their qualification tests. All three of the tested snubbers failed to meet the specified requirements in that the mechanical seals in the snubbers failed to hold hydraulic fluid at test loads of only 10 to 33 percent of the rated capacity of 2,400 kips. The snubbers were manufactured by Boeing Company prior to their discontinuing business in that field. It is currently not known if the same mechanical seal design is used on other snubber models manufactured by Boeing Company. . IN 84-67 August 17, 1984 Page 3 of 4 Discussion: As a part of a multifaceted program to improve overall snubber reliability, a November 20, 1980 letter from NRC requested all licensees to revise their Technical Specifications with respect to inservice testing of snubbers that were previously exempted from testing because of inaccessibility and to include mechanical snubbers in the testing program. Thus, the first three failures discussed above resulted from the first inservice testing for the steam generator hydraulic snubbers at the Palisades Plant and also for the mechanical snubbers at Surry Power Station Unit 1 and Turkey Point Plant Units 3 and 4. Because it was the result of a manufacturing defect, it can be reasonably assumed that the inoperability of the steam generator hydraulic snubbers at the Palisades Plant existed since they were installed. However, the length of inoperability cannot be readily determined for the mechanical snubbers at Surry Power Station Unit 1 and Turkey Point Plant Units 3 and 4. What is known, though, is that IE Bulletin 81-01, "Surveillance of Mechanical Snubbers," required all licensees to ensure that their mechanical snubbers were not locked up and that: 1. Virginia Electric and Power Company responded on July 30, 1981, saying that only 1 of the 68 mechanical snubbers at Surry Power Station Unit 1 could not be stroked in accordance with the bulletin. 2. Florida Power, and Light Company responded on July 6, 1981, to say that only 3 of 64 mechanical snubbers at Turkey Point Plant Unit 3 were frozen. Their February 19, 1982 response indicated that only 2 of the 60 mechanical snubbers at Turkey Point Plant Unit 4 had been frozen. From the above it becomes readily apparent that it is important to implement the revised Technical Specifications for snubbers as soon as practical and that a higher failure rate than previously expected can be anticipated. The mechanical snubber test procedures contained two conditions (summarized below) that some felt accentuated the failure rates observed. However, the NRC staff does not consider these conditions to be unduly conservative; they simply represent the conditions under which the snubber would be expected to function, either in its passive or its active role. The conditions in question are as follows: 1. The procedure required performing the drag/breakaway test on the mechanical snubber in the as-found condition before performing the acceleration tests. This test sequence provides an excellent indication of the ability of the snubber to perform its passive role of not impeding thermal growth of the attached piping system after the snubber has remained in one position for a period of time. 2. The procedure required performing the acceleration test at rated load. Testing at rated load provides assurance that the full design capability of the snubber remains available after the snubber has been in service for a period of time. Because not all snubbers are tested during each testing period (unless significant failure rates are detected), testing at rated load should not place an undue strain on the snubbers that could shorten their expected life. . IN 84-67 August 17, 1984 Page 4 of 4 No written response to this information notice is required. If you have any questions about this matter, please contact the Regional Administrator of the appropriate NRC Regional Office, or this office. Edward L. Jordan, Director Division of Emergency Preparedness and Engineering Response Office of Inspection and Enforcement Technical Contact: R. J. Kiessel, IE (301) 492-8119 Attachments: 1. Tables 1-4 2. List of Recently Issued IE Information Notices . Attachment 1 IN 84-67 August 17, 1984 Page 1 of 2 Table 1 Surry Power Station Unit 1 HYDRAULIC SNUBBER FAILURE MODES* % of Snubbers % of Snubbers Mode Number Tested that Failed Low lockup in tension 13 8 27 Low lockup in compression 3 2 6 Low bleed in tension 11 7 23 Low bleed in compression 10 6 21 High lockup in tension 17 11 35 High lockup in compression 10 6 21 High bleed in tension 6 4 13 High bleed in compression 3 2 6 Table 2 Surry Power Station Unit 1 HYDRAULIC SNUBBER FAILURE CAUSES* % of Snubbers % of Snubbers Cause Number Tested that Failed No observable defect 6 4 26 Degraded EP seals 3 2 13 Polyurethane piston seals 7 4 30 Poppet upside down 3 2 13 Debris in fluid 1 1 4 Poppet stuck 1 1 4 Lockup adjustment screw broken1 1 4 Piston/cylinder scoring 2 1 9 Table 3 Surry Power Station Unit 1 MECHANICAL SNUBBER FAILURE MODES % of Snubbers % of Snubbers Mode Number Tested that Failed High drag 14 21 66 Locked up 5 8 24 High acceleration 1 2 5 Locks up in compression 1 2 5 * Failures total more than 100 percent because some snubbers exhibited more than one failure mode or cause. . Attachment 2 IN 84-67 August 17, 1984 Page 2 of 2 Table 4 Turkey Point Plant Units 3 and 4 MECHANICAL SNUBBER FAILURE MODES Unit 3 Unit 4 Mode Failures Failures Free moving 1 1 Found locked up 1 4 Locked up during test 12 6 Failed drag/breakaway test 16 13 Exceeded 0.02g acceleration limit 1 7 Erratic acceleration response 0 8 Acceleration reduced to zero 0 7
Page Last Reviewed/Updated Tuesday, March 09, 2021
Page Last Reviewed/Updated Tuesday, March 09, 2021