Bulletin 86-02: Static "O" Ring Differential Pressure Switches
SSINS No.: 6820 OMB No.: 3150-0012 IEB 86-02 UNITED STATES NUCLEAR REGULATORY COMMISSION OFFICE OF INSPECTION AND ENFORCEMENT WASHINGTON, DC 20555 July 18, 1986 IE BULLETIN NO. 86-02: STATIC "O" RING DIFFERENTIAL PRESSURE SWITCHES Addresses: All power reactor facilities holding an operating license (OL) or a construction permit (CP). Purpose: The purpose of this bulletin is to request that boiling water reactor (BWR) and pressurized water reactor (PWR) licensees determine whether or not they have Series 102 or 103 differential pressure switches supplied by SOR, Incorporated (formerly Static "O" Ring Pressure Switch Company), installed as electrical equipment important to safety. Those licensees that have SOR Series 102 or 103 differential pressure switches installed in systems subject to Technical Specifications are requested to take certain actions to assure that system operation is reliable. Description of Circumstances: SOR Series 103 differential pressure switches were installed in LaSalle 2 in mid 1985 as part of an environmental qualification modification which was performed after initial operation of the unit. Identical switches were also installed in LaSalle 1. LaSalle 1 and 2 each have about 60 of these switches in various systems, including the reactor protection system and the emergency core cooling system. On June 1, 1986, LaSalle 2 experienced a feedwater transient that resulted in low water level in the reactor vessel. One of four low level trip channels actuated, resulting in a half scram. The operator recovered level and power operation was continued. However, subsequent reviews by the Licensee's personnel raised concerns that the level apparently had gone below the scram setpoint and that a malfunction of the reactor scram system may have occurred. Based on this concern, the Licensee declared an "Alert," shut the plant down, notified the NRC, and subsequently informed SOR of possible switch malfunctions. (This incident is described in greater detail in IE Information Notice 86-47). NRC dispatched an augmented inspection team to the site on June 2 to investigate the root cause and significance of the feedwater transient, the performance of the differential pressure switches in the low level trip channels, the response of the reactor protection system, and related matters. 8607180302 . IEB 86-02 July 18, 1986 Page 2 of 9 After recalibrating the level switches on June 1, the Licensee tested the performance of the level switches by lowering water level (drop test) in the reactor and reading the levels indicated on level transmitters when each of the four level switches tripped. The results were erratic with the switches tripping at levels between 2.4 inches and 12.2 (plus or minus about 1.5 inches, depending on the transmitter read). These measurements are relative to instrument zero which is at 161.5 inches above the top of active fuel. The technical specifications require that level channels be declared inoperable if the actual trippoint is below 11.0 inches. As of June 9, 1986, the Licensee had tested differential pressure switches in the residual heat removal systems and the high pressure core spray system. These switches open valves in minimum flow recirculation lines so that adequate cooling to pump seals and bearings is provided when system flow is low. One of the switches actuated within the range permitted by technical specifications; the others did not. The switch for the high pressure core spray system was calibrated to actuate at 1300 gpm but did not actuate until flow decreased to 530 gpm. The switches for the two residual heat removal systems should have actuated at 1000 gpm but did not actuate until flow decreased to the 480 to 800 gpm range. On the basis of these results, the Licensee declared all emergency core cooling systems for Units l and 2 to be inoperable. Both units remain in cold shutdown. Information Notice 86-47 was issued by the Office of Inspection and Enforcement on June 10, 1986 to inform licensees of the erratic behavior of SOR differential pressure switches during the incident at LaSalle 2 on June 1 and during subsequent testing. An attachment to the information notice listed licensees to which SOR had supplied Series 103 differential pressure switches. That list has been revised (Attachment 1) to include Series 102 differential pressure switches which have important similarities to Series 103 switches. It should be noted that the list of affected licensees is not believed to be fully accurate. The information notice also announced a public meeting of representatives from NRC, General Electric Company, SOR, and interested licensees to discuss the application and performance of Series 102 and 103 switches in safety related systems, which was held on June 12, 1986. Testing at LaSalle of other Model 103 SOR differential pressure switches used to actuate emergency core cooling system, primary containment isolation system, and other engineered safety feature systems revealed that these switches displayed the same types of behavior as the switches used for reactor scram. During the vessel water level drop tests at LaSalle 1 on June 2, one of two Series 103 switches used to provide a confirmatory water level input signal to the automatic depressurization system failed to function. On June 17, 1986, testing showed that the trippoint had shifted nonconservatively by 25 inches. In this application, the relative locations of the instrument taps are such that the system could not produce sufficient differential pressure to actuate the switch. Therefore, this amount of shift constitutes a functional failure of the switch. On June 25, the switch was disassembled and inspected. Rust . IEB 86-02 July 18, 1986 Page 3 of 9 (severe corrosion) was found inside the switch assembly and probably caused a cross shaft bearing, which is outboard of the O-rings, to seize. A similar event (Licensee Event Report 86-001-00) occurred at Oyster Creek 1 on January 17, 1986, during monthly surveillance of four SOR differential pressure switches which detect low water level in the reactor vessel. The "as-found" setpoints for three of the switches had drifted downward as much as 6 inches. During the subsequent 11 weeks, the level switches continued to perform erratically, each switch was replaced one or more times, and modified switches were installed. On April 7, after a modified switch had nonconservative setpoint drift, the Licensee performed daily surveillance until about April 12 when the reactor was shutdown for a six month outage. Increased surveillance frequency did not resolve the problem. Earlier concern for mechanical level indication equipment was expressed in NRC Generic Letter No. 84-23 which addressed water level instrumentation for BWR reactor vessels. The generic letter was based on NRC's evaluation of a report by S. Levy, Incorporated, which had been commissioned by a BWR Owner's Group. The generic letter addressed the need for BWR licensees to review plant experience related to mechanical level indication equipment, indicated that analog trip units have better reliability and greater accuracy than mechanical level indication equipment, and stated that BWR licensees should replace such equipment with analog transmitters unless operating experience indicates otherwise. Responses to Generic Letter No. 84-23 show that 80% of BWR licensees have replaced or plan to replace their mechanical level instrumentation with analog level transmitters. Recipients of this bulletin should recognize that while this bulletin focuses on more immediate problems with two similar models of mechanical differential pressure switches manufactured by SOR, Incorporated, the reliability of other mechanical instrumentation is also in question because it may be vulnerable to similar problems. Because the same urgency has not been demonstrated for other mechanical differential pressure switches, the NRC plans to address that matter separately. Discussion: DESCRIPTION OF SERIES 102 AND 103 DIFFERENTIAL PRESSURE SWITCHES The Series 102 and 103 differential pressure switches consist of a piston (Series 102) or a diaphragm (Series 103) which moves a lever that rotates a cross shaft. These components are contained in a steel case designed to withstand system pressure. Both ends of the cross shaft extend out of the wetted volume and O-ring seals are provided to form the pressure boundary and prevent leakage along the cross shaft. The condition of these surfaces and the O-rings will determine the extent to which frictional forces cause a torque which opposes rotation of the cross shaft. A lever is attached to each end of,the cross shaft. When the cross shaft rotates, one lever moves to actuate a microswitch. The other lever bears on a helical spring. An adjusting screw is used to change the compression of the spring and thus change the setpoint of the differential pressure switch. . IEB 86-02 July 18, 1986 Page 4 of 9 The case contains two ports on either side of the piston or diaphragm. The lower port on one side is connected to the system reference leg, and the lower port on the other side is connected to the lower instrument tap (i.e. variable leg). The upper ports on both sides are used as vents and are plugged when the switch is in service. The design of the cavity containing the diaphragm (or piston) is such that motion of the diaphragm is limited to 0.015 inch. Most of the time, the diaphragm is against one or the other of the mechanical stops which limit motion of the diaphragm. Thus the sum of the unbalanced hydraulic forces across the diaphragm is supported by one stop or the other except when the microswitch is forced to change position. This occurs when the absolute value of the torque caused by the unbalanced hydraulic forces changes from a value less than to a value greater than the torque caused by the helical spring. This movement causes the cross shaft and the levers to rotate 1.8 degrees. PROBLEM AREAS Differential pressure switches are often calibrated in situ after isolating them from the reactor system. A test rig consisting essentially of two bottles each containing water and air or nitrogen are connected to the differential pressure switch with one bottle on either side of the diaphragm. The differential pressure for calibration is established by adjusting the gas pressures in the bottles. Often, the lower pressure is at or near atmospheric pressure. When the SOR Model 103 differential pressure switch is calibrated to a setpoint at atmospheric pressure and then connected to a system operating at a static pressure of about 1000 psig, the actual setpoint shifts in most cases in the conservative direction toward less differential pressure required to trip. In other cases, the offset of setpoint due to calibration at atmospheric pressure has been found to be in the opposite direction. The manufacturer has stated that each switch has unique characteristics and that switches with the same model number do not all behave in the same way. It has been postulated that this may be caused by deformation or movement of the O-rings on the cross shaft when system pressure is applied. For water level applications and depending on the location of the lower instrument tap relative to the required setpoint, offset may be so large that the switch will not actuate before the level drops below the tap. In this case, the switch would not actuate no matter how low the level dropped. The vendor has indicated to the staff that factory tests showed an offset between behavior at atmospheric pressure and behavior at system pressure and that this information is provided to all customers. It has been the practice at LaSalle to calibrate at atmospheric pressure without compensating for errors due to static pressure effects. For minimum flow applications where it is necessary to open a valve in a recirculation line to protect a pump in an emergency core cooling system, assurance is needed that offset will not delay that action and result in pump damage. Testing of Series 103 differential pressure switches at LaSalle showed that application of a static pressure to the switch for a period of time also . IEB 86-02 July 18, 1986 Page 5 of 9 resulted in a significant shift in the setpoint of the switch, and that the shift due to prolonged pressure was generally in the opposite direction from the shift due to the initial application of static pressure. After being calibrated at atmospheric pressure, a static pressure of 1000 psig was maintained. A recheck of the setpoint of one switch at the end of 24 hours showed that the setpoint had shifted by a net amount that was nonconservative by about 10 inches. Subsequent rechecks continued to show shifting but in lesser amounts. To be valid, it appears that calibration and tests would need to be rechecked after static pressure has been maintained for at least 48 hours. Recent testing at LaSalle has also shown that the point at which trip occurs depends on whether the switch setpoint is being approached from low differential pressure or high differential pressure. This is particularly important for automated blocking valves in the recirculation lines which protect emergency core cooling pumps from damage when system flow is low. When flow decreases to a value below the setpoint, the switches should actuate to open the valves. Conversely, when flow increases, the switches should deactuate to provide maximum flow to the core. In addition to showing offset problems, some of the Series 103 switches evidence sticky behavior, i.e. a larger change in differential pressure is required to actuate the switch on the first demand than on subsequent operations and on subsequent tests actuation may be erratic. It is believed that starting friction and the condition of the cross shaft surfaces may cause these problems. If the O-rings stick, then the torque that they apply is added to the torque applied by the calibration spring. SOR is conducting a long range test with switches that have more highly polished finishes on those parts of the cross shafts that are in contact with O-rings. It has been common practice at LaSalle to actuate the switches several times and then to record the differential pressures required for the third or fourth actuation. It appears that the Licensee has not emphasized that the "as-found" condition of the switch is the value of differential pressure required to actuate the switch during the first demand. It is this value that must be used to determine whether the switch and its system would have performed their intended functions if called upon to do so. The life of Series 103 switches has been said to be 20 to 40 years. However, the shelf life of the elastomeric material used in the O-rings is considerably less than 40 years. The O-rings may need to be changed several times during the life of the plant. Further, there is some concern for the effect of reactor water on the O-rings, cross shaft surfaces bearing on the O-rings, and on the diaphragm material, and possible corrosion of the cross shaft bearings. OBJECTIVES OF REQUIRED ACTIONS General Design Criterion 21 "Protection System Reliability and Testability" requires that the protection system be highly reliable. It is clear that the SOR differential pressure switches that have been tested carefully to date have not performed reliably. . IEB 86-02 July 18, 1986 Page 6 of 9 A significant uncertainty exists as to where SOR differential pressure switches are currently installed or planned to be installed. A list provided by SOR, Inc. included one utility that had ordered the switches but later decided not to install the switches. The NRC later learned that another utility that was not on the SOR list had installed SOR switches. It is important to assessing the safety impact to know with certainty which plants have SOR switches installed and in what plant systems. Since these switches were installed predominately as environmentally qualified electrical equipment important to safety, as described in 10 CFR 50.49(b), this Bulletin requests all licensees to identify each such installation. The NRC intends to evaluate this information, in combination with the results of other actions required by this Bulletin, to determine if further actions should be required. Licensees, who have SOR switches installed, are requested to determine which of those switches are installed in systems which are subject to Limiting Conditions for Operations of the plant Technical Specifications. For SOR differential switches that are not in systems subject to Technical Specifications, licensees are expected to review the information in this Bulletin and consider actions, if appropriate, to preclude problems similar to those discussed in this Bulletin from occurring. For SOR differential pressure switches that are installed in systems subject to Technical Specifications, the Bulletin requests licensees to take certain actions to assure that these switches and systems will be capable of performing acceptably, if called upon during an actual plant transient or accident. First, each licensed reactor operator (and senior reactor operator) on duty should be made aware of the potential problem that may occur at his/her plant. This information should include a knowledge of the incident at Lasalle, where SOR differential pressure switches are installed in his/her plant, how to detect a malfunction or failure of any of these switches, and the remedial actions that he/she should be prepared to take if a malfunction were to occur. Second, the Bulletin requests licensees to conduct special operability tests of each system that is subject to Technical Specifications that involve SOR differential pressure switches. Special tests are necessary to determine the actual trippoint of the switches and the operability of the systems since tests of the type typically conducted may not be adequate to reveal the type of problems that have been revealed at the LaSalle station. It is important that the tests simulate the conditions of the operation of the system. Further, the test results from LaSalle suggest that the system operating conditions should be maintained for at least 48 hours before attempting to measure the performance of the SOR switches. For those systems that are not testable during plant power operations, it is anticipated that licensees will use test rigs in order to simulate operating conditions and not impact plant operations. It is also expected that licensees may take credit for the 48 hours that the switch was at system operating conditions prior to connecting the test rig, in order to minimize the time the switch/system is bypassed or tripped. If the test rig can be connected to the switch so as to make a virtually "bumpless" transfer from the system to the test rig without . IEB 86-02 July 18, 1986 Page 7 of 9 tripping the switch, such credit may be appropriate. A primary objective of the special tests is to determine how the switch will respond to its first demand after being at system operating conditions for a period of time. Special care may be necessary to assure that the first actuation is measured. If one channel of a system of redundant channels (or similar equipment in redundant safety systems) is found to have an actual trippoint that is outside the Technical Specifications or otherwise unacceptable for adequately reliable system operation, then the redundant channels (or similar equipment) should be tested as soon thereafter as practical. The short term corrective actions to be taken to return the set of channels to operable status should be based on an analysis that conservatively considers the performance of the set of redundant channels (or similar equipment). In view of the generic safety concerns and the possibility of common mode failures, unacceptable performance of an SOR differential pressure switch should be reported to the NRC in accordance with 10 CFR 50.72 and 10 CFR 50.73. Since the conduct of any special test could have potential adverse affects, the requirements for follow-up tests to verify continuing proper functioning of the switches and systems have been minimized to the extent possible consistent with the safety objective. The Bulletin requests that licensees propose an interim performance monitoring program that would cover the time between the special tests and full implementation of long term corrective actions. The objectives of the program are to detect any instance of unacceptable performance, to provide for timely initiation of additional corrective action, and to gather additional switch performance data. The Bulletin requests licensees to determine what long term corrective actions may be appropriate and will be taken. Part of this determination would include considering the potential effects of common mode failures. This determination should be based upon an analysis using the worst observed shift of the actual trippoint from the calibration setpoint for SOR switches in each general type of application, e.g., water level measurement or main steam flow measurement. The purpose of the analysis is to determine if improvements in calibration and testing methods, improvements in setpoint methodology, additional safety analysis to establish a revised licensing basis for the plant, change in the Technical Specifications, repair, modifications, or replacement, or other improvements are needed in order to meet existing regulatory requirements (e.g., General Design Criterion 21 or plant technical specifications). The analysis should demonstrate that the long term corrective action will provide an adequate margin for safety so as to assure high functional reliability. Actions Required of All Licensees: 1. Within 7 days, submit a report on the extent to which SOR Model 102 or 103 differential pressure switches are installed (or planned) as electrical equipment important to safety, as defined in 10 CFR 50.49(b). Include in the report: the model number of the switch, the system in which it is installed (e.g., low pressure safety injection), the application of the switch (e.g., water level measurement, system flow measurement), and the . IEB 86-02 July 18, 1986 Page 8 of 9 function of the switch (e.g. , control of minimum flow recirculation valve). A negative report, if appropriate, is required. Actions Required of Licensees That Have SOR Model 102 or 103 Differential Pressure Switches Installed in Systems That Are Subject to Limiting Conditions for Operation in Technical Specifications: 2. Within 7 days, take positive action to assure that licensed reactor operators on duty are prepared for potential malfunctions of SOR switches. 3. Within 30 days, conduct a special test of each SOR switch to determine if the switch and system function properly or if short term corrective actions are necessary. The tests are to determine if the switches/systems will respond acceptably on the first demand after being at system operating conditions for a period of time. The tests should be planned and conducted so as to minimize any potential adverse affects of the testing. If any corrective action includes the replacement of SOR switches with mechanical differential pressure switches by another manufacturer, the licensee should , submit a technical justification, including a reliability demonstration. Repeat the special tests on a monthly basis until two consecutive successful tests are attained. 4. Report failures in accordance with 10 CFR 50.72 and 10 CFR 50.73. 5. Within 60 days, develop, implement and submit a written report describing your interim performance monitoring program to provide continuing assurance that the performance of the switches and plant systems remains acceptably reliable until long term corrective actions are fully implemented. 6. Within 60 days, submit a written report which describes the margin and basis for switch actuation. The report should also describe the long term corrective actions to be taken, including the implementation schedule, the impacts of potential common mode failures, and an analysis to demonstrate that the system involved will meet regulatory requirements and function reliably. The report should include specific information on the installed SOR switches: the manufacturer's specified range for the switch, the nominal and allowable values for the calibration setpoint in the Technical Specifications in the same terms as the manufacturer's specified range for the switch, the relative locations of the instrument taps for water level monitoring applications, sources of systematic errors such as the differences in elevations of the installation of condensing pots, and "as found" and any subsequent test data for any switch that does not conform to the Technical Specifications or is otherwise unacceptable. Recipients of this Bulletin who hold construction permits and licensees of plants that are shutdown for an extended period (e.g., Browns Ferry) are not required to complete the actions of this Bulletin on the schedule shown. In each case, compliance with this Bulletin should be addressed prior to the next critical operation of the plant or within 1 year, whichever occurs first. . IEB 86-02 July 18, 1986 Page 9 of 9 If, because of plant unique conditions, a licensee should determine that any action requested by this Bulletin jeopardizes plant safety, the action should not be initiated and the NRC should be notified as soon as practical. This notification should include the basis for the determination. Further, if a licensee determines that, even with "best efforts," an action requested by this Bulletin can not reasonably be completed within the prescribed schedule, the NRC should be notified within 7 days of receipt of the Bulletin. The written reports shall be submitted to the appropriate Regional Administrator under oath or affirmation under the provisions of Section 182a of the Atomic Energy Act of 1954, as amended. Also, the original copy of the cover letters and a copy of the reports shall be transmitted to the U.S. Nuclear Regulatory Commission, Document Control Desk, Washington, DC, 20555 for reproduction and distribution. The request for information was approved by the Office of Management and Budget under blanket clearance number 3150-0012. Comments on burden and duplication may be directed to the Office of Management and Budget, Reports Management, Room 3208, New Executive Office Building, Washington, DC, 20503. If you have any questions regarding this matter, please contact the Regional Administrator of the appropriate NRC Regional Office or one of the technical contacts listed below. James M. Taylor, Director Office of Inspection and Enforcement Attachments: 1. Plants with Similar SOR Switches 2. List of Recently IE Bulletins Technical Contacts: J. T. Beard, NRR (301) 492-4415 Roger W. Woodruff, IE (301) 492-7205 . Attachment 1 IEB 86-02 July 18, 1986 PLANTS WITH SERIES 102 OR 103 DIFFERENTIAL PRESSURE SWITCHES Series 102: Florida Power and Light Series 103: Commonwealth Edison General Public Utilities - Nuclear Corporation Houston Lighting & Power Company Northeast Utilities Pennsylvania Power & Light Southern California Edison Tennessee Valley Authority Washington Public Power Supply System
Page Last Reviewed/Updated Tuesday, March 09, 2021
Page Last Reviewed/Updated Tuesday, March 09, 2021