Due to a lapse in appropriations, the NRC has ceased normal operations. However, excepted and exempted activities necessary to maintain critical health and safety functions—as well as essential progress on designated critical activities, including those specified in Executive Order 14300—will continue, consistent with the OMB-Approved NRC Lapse Plan.

Power Reactor Status Report for January 18, 2024

UNEVALUATED INFORMATION PROVIDED BY THE FACILITY

On this page:

Region 1

Unit Power Down Reason or Comment Change in Report (*) Scrams (#)
Beaver Valley 1 100 *
Beaver Valley 2 100 *
Calvert Cliffs 1 98 Coastdown To Refueling Outage *
Calvert Cliffs 2 100 *
FitzPatrick 100
Ginna 100
Hope Creek 1 100
Limerick 1 100
Limerick 2 100
Millstone 2 100
Millstone 3 16 Holding Power, Not sync to the grid *
Nine Mile Point 1 100
Nine Mile Point 2 98 Moisture Separator Reheater Issue;
Peach Bottom 2 100
Peach Bottom 3 100
Salem 1 100
Salem 2 100
Seabrook 1 100
Susquehanna 1 100
Susquehanna 2 100

Region 2

Unit Power Down Reason or Comment Change in Report (*) Scrams (#)
Browns Ferry 1 100 Conservative Ops Alert
Browns Ferry 2 100 Conservative Ops Alert
Browns Ferry 3 96 Coastdown To Refueling Outage; Conservative Ops Alert
Brunswick 1 99 Coastdown To Refueling Outage
Brunswick 2 100
Catawba 1 100 Conservative Ops Alert
Catawba 2 100 Conservative Ops Alert
Farley 1 100 Conservative Ops Alert
Farley 2 100 Conservative Ops Alert
Harris 1 100 *
Hatch 1 88 Reduced Power Due to Moisture Carryover, Vibration in EHC System; Conservative Ops Warning *
Hatch 2 100 Conservative Ops Warning *
McGuire 1 100
McGuire 2 100
North Anna 1 100
North Anna 2 100
Oconee 1 100
Oconee 2 100
Oconee 3 100
Robinson 2 100
Saint Lucie 1 100
Saint Lucie 2 100
Sequoyah 1 100 Conservative Ops Alert *
Sequoyah 2 100 Conservative Ops Alert *
Summer 100
Surry 1 100
Surry 2 100
Turkey Point 3 100
Turkey Point 4 100
Vogtle 1 100 Conservative Ops Alert
Vogtle 2 100 Conservative Ops Alert
Vogtle 3 100 Conservative Ops Alert
Vogtle 4 0 Monitoring ADS Vibrations during Heatup; Conservative Ops Alert
Watts Bar 1 100 Conservative Ops Alert *
Watts Bar 2 100 Conservative Ops Alert *

Region 3

Unit Power Down Reason or Comment Change in Report (*) Scrams (#)
Braidwood 1 100 *
Braidwood 2 100 *
Byron 1 100 *
Byron 2 100 *
Clinton 100 Cold Weather Alert *
D.C. Cook 1 100 *
D.C. Cook 2 100 *
Davis-Besse 100 *
Dresden 2 100 Cold Weather Alert
Dresden 3 100 Cold Weather Alert
Fermi 2 22 Reduce Power Due to Condenser Tube Leak; *
LaSalle 1 96 Coastdown To Refueling Outage; *
LaSalle 2 100 *
Monticello 100 *
Perry 1 100
Point Beach 1 100
Point Beach 2 100
Prairie Island 1 0 2023-10-20 See EN 56803
Prairie Island 2 0 2023-10-07 Refueling Outage
Quad Cities 1 100
Quad Cities 2 100

Region 4

Unit Power Down Reason or Comment Change in Report (*) Scrams (#)
Arkansas Nuclear 1 100
Arkansas Nuclear 2 100
Callaway 100
Columbia Generating Station 100
Comanche Peak 1 100 *
Comanche Peak 2 100 *
Cooper 100
Diablo Canyon 1 100
Diablo Canyon 2 100
Grand Gulf 1 100 Cold Weather Alert; *
Palo Verde 1 100
Palo Verde 2 100
Palo Verde 3 100
River Bend Station 1 100 Cold Weather Alert; *
South Texas 1 100
South Texas 2 100
Waterford 3 0 2023-10-14 Refueling Outage
Wolf Creek 1 100

* - Power Reactor Status Report change within past 24 hours
# - Number of reactor scrams or trips within past 24 hours

Notes:
  • Reactor status data collected between 4 a.m. and 8 a.m. each day.
  • All times are based on eastern time.