The U.S. Nuclear Regulatory Commission is in the process of rescinding or revising guidance and policies posted on this webpage in accordance with Executive Order 14151 Ending Radical and Wasteful Government DEI Programs and Preferencing, and Executive Order 14168 Defending Women From Gender Ideology Extremism and Restoring Biological Truth to the Federal Government. In the interim, any previously issued diversity, equity, inclusion, or gender-related guidance on this webpage should be considered rescinded that is inconsistent with these Executive Orders.

Power Reactor Status Report for November 16, 2015

UNEVALUATED INFORMATION PROVIDED BY THE FACILITY

On this page:

Region 1

Unit Power Down Reason or Comment Change in report (*) Number of Scrams (#)
Beaver Valley 1 100        
Beaver Valley 2 100        
Calvert Cliffs 1 100   HIGH SYSTEM VOLTAGE ACTION *  
Calvert Cliffs 2 100   HIGH SYSTEM VOLTAGE ACTION *  
FitzPatrick 100        
Ginna 100        
Hope Creek 1 100   HIGH SYSTEM VOLTAGE ACTION *  
Indian Point 2 100        
Indian Point 3 100        
Limerick 1 100        
Limerick 2 100        
Millstone 2 100        
Millstone 3 100        
Nine Mile Point 1 100        
Nine Mile Point 2 100        
Oyster Creek 75   INCREASING POWER *  
Peach Bottom 2 100   MAINTAIN < 100 MVARS DUE TO VIBRATION ISSUE ON UNIT 2 MAIN GENERATOR    
Peach Bottom 3 91   EPU TESTING HOLD    
Pilgrim 1 100        
Salem 1 100        
Salem 2 0 10/22/2015 REFUELING OUTAGE    
Seabrook 1 74   INCREASING POWER *  
Susquehanna 1 0 11/12/2015 REACTOR SCRAM DUE TO MSIV CLOSURE - SEE EN# 51532 HIGH SYSTEM VOLTAGE ACTION *  
Susquehanna 2 100   HIGH SYSTEM VOLTAGE ACTION *  
Three Mile Island 1 0 10/29/2015 REFUELING OUTAGE HIGH SYSTEM VOLTAGE ACTION *  

Region 2

Unit Power Down Reason or Comment Change in report (*) Number of Scrams (#)
Browns Ferry 1 0 11/15/2015 PLANNED OUTAGE *  
Browns Ferry 2 100        
Browns Ferry 3 100        
Brunswick 1 100        
Brunswick 2 100        
Catawba 1 100        
Catawba 2 100     *  
Farley 1 100        
Farley 2 100     *  
Harris 1 100        
Hatch 1 100     *  
Hatch 2 100        
McGuire 1 100        
McGuire 2 100        
North Anna 1 100        
North Anna 2 100        
Oconee 1 100        
Oconee 2 100        
Oconee 3 100        
Robinson 2 100        
Saint Lucie 1 100        
Saint Lucie 2 100        
Sequoyah 1 100        
Sequoyah 2 0 11/13/2015 REFUELING OUTAGE    
Summer 0 10/02/2015 REFUELING OUTAGE    
Surry 1 0 10/13/2015 FORCED OUTAGE    
Surry 2 0 10/18/2015 REFUELING OUTAGE *  
Turkey Point 3 0 10/18/2015 REFUELING OUTAGE *  
Turkey Point 4 100        
Vogtle 1 100        
Vogtle 2 100        
Watts Bar 1 100        
Watts Bar 2 0   OPERATING LICENSE ISSUED 10/22/15 - AWAITING INITIAL CORE LOAD    

Region 3

Unit Power Down Reason or Comment Change in report (*) Number of Scrams (#)
Braidwood 1 100     *  
Braidwood 2 100        
Byron 1 76   LOAD DROP PER DISPATCHER ORDER *  
Byron 2 71   LOAD DROP PER DISPATCHER ORDER    
Clinton 99   100% ELECTRICAL GENERATION    
D.C. Cook 1 100        
D.C. Cook 2 96   FW HEATER TUBE LEAK    
Davis-Besse 100        
Dresden 2 0 11/01/2015 REFUELING OUTAGE *  
Dresden 3 100        
Duane Arnold 100        
Fermi 2 0 09/13/2015 REFUELING OUTAGE *  
La Salle 1 100     *  
La Salle 2 100        
Monticello 100        
Palisades 100        
Perry 1 100        
Point Beach 1 100        
Point Beach 2 100        
Prairie Island 1 100        
Prairie Island 2 0 10/16/2015 REFUELING OUTAGE    
Quad Cities 1 100        
Quad Cities 2 100     *  

Region 4

Unit Power Down Reason or Comment Change in report (*) Number of Scrams (#)
Arkansas Nuclear 1 100        
Arkansas Nuclear 2 60   INCREASING POWER *  
Callaway 100        
Columbia Generating Station 100        
Comanche Peak 1 100        
Comanche Peak 2 81   HOLDING POWER FOR CORE TESTING *  
Cooper 100        
Diablo Canyon 1 100        
Diablo Canyon 2 100        
Fort Calhoun 100        
Grand Gulf 1 100        
Palo Verde 1 100        
Palo Verde 2 20   GENERATOR IS CONNECTED TO THE GRID - HOLDING POWER FOR ENGINEERING TESTING *  
Palo Verde 3 100        
River Bend 1 75   INCREASING POWER *  
South Texas 1 0 10/17/2015 UNUSUAL EVENT DUE TO RCS LEAKAGE SEE EN# 51536 - REACTOR STARTUP DELAYED DUE TO REACTOR COLANT PUMP REPAIR *  
South Texas 2 100        
Waterford 3 0 10/25/2015 REFUELING OUTAGE    
Wolf Creek 1 100        

* - Power Reactor Status Report change within past 24 hours
# - Number of reactor scrams or trips within past 24 hours

Notes:
  • Reactor status data collected between 4 a.m. and 8 a.m. each day.
  • All times are based on eastern time.

Page Last Reviewed/Updated Thursday, March 25, 2021