Power Reactor Status Report for April 3, 2012
UNEVALUATED INFORMATION PROVIDED BY THE FACILITY
On this page:
Region 1
Unit | Power | Down | Reason or Comment | Change in report (*) | Number of Scrams (#) |
Beaver Valley 1 | 96 | | COASTDOWN TO REFUELING OUTAGE | | |
Beaver Valley 2 | 100 | | | | |
Calvert Cliffs 1 | 0 | 02/05/2012 | REFUELING OUTAGE HIGH SYSTEM VOLTAGE ACTION | | |
Calvert Cliffs 2 | 100 | | HIGH SYSTEM VOLTAGE ACTION | | |
FitzPatrick | 35 | | INCREASING POWER | * | |
Ginna | 100 | | | | |
Hope Creek 1 | 98 | | COASTDOWN TO REFUELING OUTAGE - HIGH SYSTEM VOLTAGE ACTION | * | |
Indian Point 2 | 45 | | HOLDING POWER FOR NUCLEAR INSTRUMENTATION TESTS | * | |
Indian Point 3 | 100 | | | | |
Limerick 1 | 100 | | | | |
Limerick 2 | 100 | | | | |
Millstone 2 | 100 | | | | |
Millstone 3 | 100 | | | | |
Nine Mile Point 1 | 100 | | | | |
Nine Mile Point 2 | 96 | | COASTDOWN TO REFUELING OUTAGE | * | |
Oyster Creek | 100 | | | | |
Peach Bottom 2 | 100 | | #2 STARTUP SOURCE OUTAGE FOR PLANNED MAINTENANCE | | |
Peach Bottom 3 | 100 | | #2 STARTUP SOURCE OUTAGE FOR PLANNED MAINTENANCE | | |
Pilgrim 1 | 100 | | | | |
Salem 1 | 100 | | | | |
Salem 2 | 100 | | | | |
Seabrook 1 | 85 | | HOLDING POWER BASED ON GENERATOR STATOR COOLING DELTA T LIMIT. | | |
Susquehanna 1 | 0 | 03/31/2012 | REFUELING OUTAGE | * | |
Susquehanna 2 | 100 | | | * | |
Three Mile Island 1 | 100 | | | * | |
Vermont Yankee | 100 | | | | |
Region 2
Unit | Power | Down | Reason or Comment | Change in report (*) | Number of Scrams (#) |
Browns Ferry 1 | 100 | | | | |
Browns Ferry 2 | 100 | | | | |
Browns Ferry 3 | 94 | | COASTDOWN TO REFUELING OUTAGE | | |
Brunswick 1 | 0 | 02/23/2012 | REFUELING OUTAGE | | |
Brunswick 2 | 100 | | | | |
Catawba 1 | 100 | | | | |
Catawba 2 | 0 | 03/10/2012 | VESSEL HEAD ON BUT NOT FULLY TENSIONED | * | |
Crystal River 3 | 0 | 09/25/2009 | DEFUELED - CONTAINMENT TENSIONING ON HOLD | | |
Farley 1 | 0 | 04/01/2012 | REFUELING OUTAGE | | |
Farley 2 | 100 | | | | |
Harris 1 | 100 | | | | |
Hatch 1 | 41 | | INCREASING POWER - LOSS OF MAIN CONDENSER VACUUM | * | |
Hatch 2 | 100 | | | | |
McGuire 1 | 100 | | | | |
McGuire 2 | 100 | | | | |
North Anna 1 | 0 | 03/10/2012 | REFUELING OUTAGE | | |
North Anna 2 | 100 | | | | |
Oconee 1 | 100 | | | | |
Oconee 2 | 100 | | | | |
Oconee 3 | 87 | | COASTDOWN TO REFUELING OUTAGE | * | |
Robinson 2 | 100 | | | * | |
Saint Lucie 1 | 0 | 03/30/2012 | NOP, NOT | * | |
Saint Lucie 2 | 100 | | | | |
Sequoyah 1 | 63 | | INCREASING POWER TO 100% | * | |
Sequoyah 2 | 100 | | | | |
Summer | 100 | | | | |
Surry 1 | 100 | | | | |
Surry 2 | 100 | | | | |
Turkey Point 3 | 0 | 02/26/2012 | DEFUELED - NOUE DUE TO FIRE IN PROTECTED AREA - SEE EN #47797. | * | |
Turkey Point 4 | 100 | | | | |
Vogtle 1 | 100 | | | | |
Vogtle 2 | 100 | | | | |
Watts Bar 1 | 100 | | | | |
Region 3
Unit | Power | Down | Reason or Comment | Change in report (*) | Number of Scrams (#) |
Braidwood 1 | 100 | | | | |
Braidwood 2 | 100 | | | | |
Byron 1 | 100 | | FEED WATER FLOW INVESTIGATION - POWER LIMITED TO 99.6% | * | |
Byron 2 | 100 | | FEED WATER FLOW INVESTIGATION - POWER LIMITED TO 99.9% | * | |
Clinton | 97 | | 100% ELECTRICAL CAPABILITY | | |
D.C. Cook 1 | 100 | | | | |
D.C. Cook 2 | 0 | 03/21/2012 | DEFUELED | | |
Davis-Besse | 100 | | | | |
Dresden 2 | 100 | | | | |
Dresden 3 | 100 | | | | |
Duane Arnold | 100 | | | | |
Fermi 2 | 0 | 03/25/2012 | REFUELING OUTAGE | | |
Kewaunee | 100 | | | | |
La Salle 1 | 100 | | | | |
La Salle 2 | 100 | | | | |
Monticello | 100 | | | | |
Palisades | 60 | | COOLING TOWER REPLACEMENT | | |
Perry 1 | 100 | | | | |
Point Beach 1 | 100 | | | | |
Point Beach 2 | 100 | | | | |
Prairie Island 1 | 100 | | | | |
Prairie Island 2 | 0 | 02/21/2012 | DEFUELED | | |
Quad Cities 1 | 100 | | MONITORING TURBINE VIBRATION - ENTERED/EXITED TS REQUIRED SHUTDOWN DUE TO BOTH EDGS INOPERABLE - SEE EN #47799 | * | |
Quad Cities 2 | 0 | | REFUELING OUTAGE | * | |
Region 4
Unit | Power | Down | Reason or Comment | Change in report (*) | Number of Scrams (#) |
Arkansas Nuclear 1 | 100 | | | | |
Arkansas Nuclear 2 | 100 | | | | |
Callaway | 100 | | | | |
Columbia Generating Station | 100 | | | | |
Comanche Peak 1 | 100 | | | | |
Comanche Peak 2 | 0 | 04/01/2012 | MAINTENANCE OUTAGE | | |
Cooper | 100 | | | | |
Diablo Canyon 1 | 82 | | INCREASING POWER TO 100% - MORRO BAY MIDWAY #1 230 KV LINE OOS FOR MAINTENANCE TILL JUNE | * | |
Diablo Canyon 2 | 100 | | MORRO BAY MIDWAY #1 230 KV LINE OOS FOR MAINTENANCE TILL JUNE | | |
Fort Calhoun | 0 | 04/09/2011 | REFUELING OUTAGE | | |
Grand Gulf 1 | 0 | 02/19/2012 | REFUELING OUTAGE | | |
Palo Verde 1 | 100 | | | | |
Palo Verde 2 | 100 | | | | |
Palo Verde 3 | 0 | 03/16/2012 | LOADING FUEL IN CORE | | |
River Bend 1 | 100 | | | | |
San Onofre 2 | 0 | 01/09/2012 | REFUELING OUTAGE | | |
San Onofre 3 | 0 | 01/31/2012 | FORCED OUTAGE - S/G REPAIR | | |
South Texas 1 | 100 | | | | |
South Texas 2 | 0 | 11/28/2011 | MAINTENANCE OUTAGE | | |
Waterford 3 | 100 | | | | |
Wolf Creek 1 | 100 | | | | |
* - Power Reactor Status Report change within past 24 hours
# - Number of reactor scrams or trips within past 24 hours
Notes:
- Reactor status data collected between 4 a.m. and 8 a.m. each day.
- All times are based on eastern time.
Page Last Reviewed/Updated Wednesday, March 24, 2021