The U.S. Nuclear Regulatory Commission is in the process of rescinding or revising guidance and policies posted on this webpage in accordance with Executive Order 14151 Ending Radical and Wasteful Government DEI Programs and Preferencing, and Executive Order 14168 Defending Women From Gender Ideology Extremism and Restoring Biological Truth to the Federal Government. In the interim, any previously issued diversity, equity, inclusion, or gender-related guidance on this webpage should be considered rescinded that is inconsistent with these Executive Orders.

Power Reactor Status Report for November 16, 2007

UNEVALUATED INFORMATION PROVIDED BY THE FACILITY

On this page:

Region 1

Unit Power Down Reason or Comment Change in report (*) Number of Scrams (#)
Beaver Valley 1 100        
Beaver Valley 2 100        
Calvert Cliffs 1 100        
Calvert Cliffs 2 100        
FitzPatrick 65   REDUCED POWER DUE TO HIGH WINDS TO PREEMPT COMPLICATIONS OF POTENTIAL ALGAE INTRUSION *  
Ginna 100        
Hope Creek 1 24   INCREASING POWER *  
Indian Point 2 100        
Indian Point 3 100        
Limerick 1 100        
Limerick 2 100        
Millstone 2 100        
Millstone 3 100        
Nine Mile Point 1 100        
Nine Mile Point 2 4   INCREASING POWER *  
Oyster Creek 100        
Peach Bottom 2 100   STARTUP SOURCE 343 OOS 500 KV LINE 5012 BLOCKED *  
Peach Bottom 3 100   STARTUP SOURCE 343 OOS 500 KV LINE 5012 BLOCKED *  
Pilgrim 1 100   LINE 342 AT PARTIAL CAPACITY - IF OTHER 345KV LINE IS LOST ISO WILL REQUEST REDUCTION TO 500 MWE    
Salem 1 100        
Salem 2 100        
Seabrook 1 100   POWER REDUCTION THREAT DUE TO GRID WORK IN NEW YORK UNTIL JANUARY    
Susquehanna 1 100        
Susquehanna 2 100   VOLTAGE REGULATOR IN MANUAL    
Three Mile Island 1 0 10/21/2007 REFUELING OUTAGE    
Vermont Yankee 100        

Region 2

Unit Power Down Reason or Comment Change in report (*) Number of Scrams (#)
Browns Ferry 1 70   1 OF 7 500 KV TRANSMISSION LINES OOS FOR MAINTENANCE AND LIMESTONE INTERBANK TIE LINE OOS. LOWERED POWER FOR ROD PATTERN ADJUSTMENT *  
Browns Ferry 2 100   1 OF 7 500 KV TRANSMISSION LINES OOS FOR MAINTENANCE AND LIMESTONE INTERBANK TIE LINE OOS.    
Browns Ferry 3 100   1 OF 7 500 KV TRANSMISSION LINES OOS FOR MAINTENANCE AND LIMESTONE INTERBANK TIE LINE OOS.    
Brunswick 1 100        
Brunswick 2 100        
Catawba 1 100        
Catawba 2 20   HOLDING FOR VOLTAGE REGULATOR TESTING *  
Crystal River 3 0 11/02/2007 REFUELING OUTAGE - DEFUELED    
Farley 1 84   INCREASING POWER *  
Farley 2 100        
Harris 1 100        
Hatch 1 100        
Hatch 2 100        
McGuire 1 100        
McGuire 2 100        
North Anna 1 100        
North Anna 2 100        
Oconee 1 100        
Oconee 2 100        
Oconee 3 0 10/26/2007 DEFUELED    
Robinson 2 100        
Saint Lucie 1 100        
Saint Lucie 2 0 09/30/2007 DEFUELED    
Sequoyah 1 1   PHYSICS TESTING *  
Sequoyah 2 100        
Summer 100        
Surry 1 0 10/20/2007 REFUELING OUTAGE    
Surry 2 100        
Turkey Point 3 99   TROUBLESHOOTING ISSUE WITH ERDADS INPUT FOR HEAT BALANCE    
Turkey Point 4 100        
Vogtle 1 98   100% ELECTRICAL CAPABILITY    
Vogtle 2 98   100% ELECTRICAL CAPABILITY    
Watts Bar 1 100        

Region 3

Unit Power Down Reason or Comment Change in report (*) Number of Scrams (#)
Braidwood 1 100        
Braidwood 2 100        
Byron 1 100        
Byron 2 100        
Clinton 97   100% ELECTRICAL CAPABILITY    
D.C. Cook 1 100        
D.C. Cook 2 100        
Davis-Besse 100        
Dresden 2 0 10/28/2007 REFUELING OUTAGE    
Dresden 3 99   100% ELECTRICAL CAPABILITY    
Duane Arnold 98   100% ELECTRICAL CAPABILITY    
Fermi 2 0 11/14/2007 RX SCRAM. SEE EN# 43784 *  
Kewaunee 100        
La Salle 1 92   COASTDOWN TO REFUELING OUTAGE    
La Salle 2 100        
Monticello 100        
Palisades 100        
Perry 1 100        
Point Beach 1 100        
Point Beach 2 100        
Prairie Island 1 100   161 KV BUS OOS FOR MAINTENANCE    
Prairie Island 2 100   161 KV BUS OOS FOR MAINTENANCE    
Quad Cities 1 97   100% ELECTRICAL CAPABILITY    
Quad Cities 2 97   100% ELECTRICAL CAPABILITY    

Region 4

Unit Power Down Reason or Comment Change in report (*) Number of Scrams (#)
Arkansas Nuclear 1 100        
Arkansas Nuclear 2 100        
Callaway 100        
Columbia Generating Station 100        
Comanche Peak 1 100        
Comanche Peak 2 100        
Cooper 100        
Diablo Canyon 1 100     *  
Diablo Canyon 2 100     *  
Fort Calhoun 100        
Grand Gulf 1 94   HOLDING POWER TO TROUBLESHOOT EHC CONTROL FLUID PRESSURE ISSUES *  
Palo Verde 1 99   S/G HIGH RATE BLOWDOWN IN PROGRESS *  
Palo Verde 2 100        
Palo Verde 3 0 09/29/2007 DEFUELED    
River Bend 1 75   HOLDING FOR SCHEDULED MAINTENANCE    
San Onofre 2 98   S/G LIMITATIONS *  
San Onofre 3 100        
South Texas 1 100        
South Texas 2 100        
Waterford 3 100        
Wolf Creek 1 100        

* - Power Reactor Status Report change within past 24 hours
# - Number of reactor scrams or trips within past 24 hours

Notes:
  • Reactor status data collected between 4 a.m. and 8 a.m. each day.
  • All times are based on eastern time.

Page Last Reviewed/Updated Wednesday, March 24, 2021