Due to a lapse in appropriations, the NRC has ceased normal operations. However, excepted and exempted activities necessary to maintain critical health and safety functions—as well as essential progress on designated critical activities, including those specified in Executive Order 14300—will continue, consistent with the OMB-Approved NRC Lapse Plan.

Part 21 Report - 1997-410

LICENSEE: OMAHA PUBLIC POWER DISTRICT SITE: FT CALHOUN 1 EN NUMBER:32384 DOCKET: 05000285 EVENT DATE: 05-23-97 RX TYPE: PWR EVENT TIME: 10:40 VENDORS: CE NOTIFY DATE: 05-23-97 EMERGENCY CLASS: N/A REGION: 4 STATE: NE TIME: 17:50 OPS OFFICER: STEVE SANDIN 10 CFR SECTION: CDEG 21.21(c)(3)(i) DEFECTS/NONCOMPLIANCE UNIT SCRAM RX INIT INITIAL MODE CURR CURRENT MODE CODE CRIT PWR PWR 1 N Y 100 POWER OPERATION 100 POWER OPERATION THE LICENSEE IS MAKING A PART 21 NOTIFICATION REGARDING DEFECTIVE RAW WATER PUMP IMPELLERS. THE LICENSEE IDENTIFIED THAT THE REPLACEMENT IMPELLERS FOR BYRON JACKSON RAW WATER PUMPS HAD BLADE DIMENSIONS OUT OF TOLERANCE. AN ENGINEERING EVALUATION OF THE DIMENSIONAL INACCURACIES DETERMINED THAT PUMP DISCHARGE FLOWS USING THESE IMPELLERS WOULD NOT SATISFY ACCEPTANCE CRITERIA AND COULD POSE A SUBSTANTIAL SAFETY HAZARD UNDER CERTAIN CIRCUMSTANCES. THIS PROBLEM WAS INITIALLY IDENTIFIED ON 4/8/97. ONE OF THE IMPELLERS WAS INSTALLED AND SUBSEQUENTLY REMOVED FROM RAW WATER PUMP ASSEMBLY AC-10D WHICH FAILED POST MAINTENANCE TESTING. BOTH DEFECTIVE IMPELLERS WERE RETURNED TO THE SUPPLIER. THE LICENSEE DOES NOT KNOW IF OTHER FACILITIES ARE AFFECTED. THE LICENSEE INFORMED THE NRC RESIDENT INSPECTOR.

Page Last Reviewed/Updated Wednesday, March 24, 2021

Page Last Reviewed/Updated Wednesday, March 24, 2021