Event Notification Report for May 09, 2015
U.S. Nuclear Regulatory Commission
Operations Center
EVENT REPORTS FOR
05/08/2015 - 05/09/2015
Power Reactor
Event Number: 51060
Facility: INDIAN POINT
Region: 1 State: NY
Unit: [] [3] []
RX Type: [2] W-4-LP,[3] W-4-LP
NRC Notified By: LUKE HEDGES
HQ OPS Officer: JOHN SHOEMAKER
Region: 1 State: NY
Unit: [] [3] []
RX Type: [2] W-4-LP,[3] W-4-LP
NRC Notified By: LUKE HEDGES
HQ OPS Officer: JOHN SHOEMAKER
Notification Date: 05/09/2015
Notification Time: 18:19 [ET]
Event Date: 05/09/2015
Event Time: 17:50 [EDT]
Last Update Date: 05/09/2015
Notification Time: 18:19 [ET]
Event Date: 05/09/2015
Event Time: 17:50 [EDT]
Last Update Date: 05/09/2015
Emergency Class: UNUSUAL EVENT
10 CFR Section:
50.72(a) (1) (i) - EMERGENCY DECLARED 50.72(b)(2)(iv)(B) - RPS ACTUATION - CRITICAL 50.72(b)(2)(xi) - OFFSITE NOTIFICATION 50.72(b)(3)(iv)(A) - VALID SPECIF SYS ACTUATION
10 CFR Section:
50.72(a) (1) (i) - EMERGENCY DECLARED 50.72(b)(2)(iv)(B) - RPS ACTUATION - CRITICAL 50.72(b)(2)(xi) - OFFSITE NOTIFICATION 50.72(b)(3)(iv)(A) - VALID SPECIF SYS ACTUATION
Person (Organization):
DAN SCHROEDER (R1DO)
BILL DEAN (NRR)
ALLEN HOWE (NRR)
DAN DORMAN (R1RA)
JEFFERY GRANT (IRD)
DAN SCHROEDER (R1DO)
BILL DEAN (NRR)
ALLEN HOWE (NRR)
DAN DORMAN (R1RA)
JEFFERY GRANT (IRD)
| Unit | SCRAM Code | RX Crit | Initial PWR | Initial RX Mode | Current PWR | Current RX Mode |
|---|---|---|---|---|---|---|
| 3 | A/R | Y | 100 | Power Operation | 0 | Hot Standby |
UNUSUAL EVENT DECLARED DUE TO MAIN TRANSFORMER FIRE
"At 1750 EDT [05/09/15,] Indian Point Unit 3 experienced a fire on the 31 Main Transformer resulting in a unit trip. An Unusual Event was declared at 1801 EDT. The onsite fire brigade was mobilized. Offsite fire fighting assistance was requested. The fire was reported extinguished at 1815 EDT. The reactor was shutdown by an automatic trip. Plant response to the trip was as expected with no complications. The 31 and 33 Auxiliary Feed Pumps are operating and feeding the steam generators. Accountability is being performed."
The plant is stable in mode 3, all control rods fully inserted, with normal offsite electrical power, and decay heat is being released to the main condenser. There was no impact on Unit 2 which continues to operate at 100% power.
The licensee has notified the NRC Resident Inspector and state and local authorities.
Notified DHS SWO, FEMA OPS Center, DHS NICC Watch Officer, and Nuclear SSA via email.
* * * UPDATE FROM LUKE HEDGES TO JOHN SHOEMAKER AT 2037 ON 5/9/15 * * *
"Oil from 31 Main Transformer has spilled into the discharge canal and has made its way into the river. Plant personnel are sandbagging drains and release paths. IPEC [Indian Point Energy Center] has contacted its environmental contractor, who is expected onsite at 2100 EDT to assist with cleanup. The National Response Center was notified at 1945 EDT and issued notification number 1116011. A message was left with the Westchester County Department of Health at 1953 EDT. The NY State DEC [Department of Environment Conservation] was contacted at 1955 EDT and issued notification number 1501459."
The licensee has notified the NRC Resident Inspector.
Indian Point Unit 3 remains in an Unusual Event at this time.
Notified R1DO (Schroeder).
* * * UPDATE FROM LUKE HEDGES TO JOHN SHOEMAKER AT 2141 ON 5/9/15 * * *
"Indian Point Unit 3 exited the Unusual Event at 2103 EDT. The basis for exiting the Unusual Event is that the fire is out and field operators report they have been successful in cooling the transformer."
The licensee has notified the NRC Resident Inspector and state and local authorities.
Notified R1DO (Schroeder), R1RA (Lew), NRR (Dean), NRR EO (Morris), NRR EO (Howe), and IRD (Grant).
Notified DHS SWO, FEMA OPS Center, DHS NICC Watch Officer, and Nuclear SSA via email.
"At 1750 EDT [05/09/15,] Indian Point Unit 3 experienced a fire on the 31 Main Transformer resulting in a unit trip. An Unusual Event was declared at 1801 EDT. The onsite fire brigade was mobilized. Offsite fire fighting assistance was requested. The fire was reported extinguished at 1815 EDT. The reactor was shutdown by an automatic trip. Plant response to the trip was as expected with no complications. The 31 and 33 Auxiliary Feed Pumps are operating and feeding the steam generators. Accountability is being performed."
The plant is stable in mode 3, all control rods fully inserted, with normal offsite electrical power, and decay heat is being released to the main condenser. There was no impact on Unit 2 which continues to operate at 100% power.
The licensee has notified the NRC Resident Inspector and state and local authorities.
Notified DHS SWO, FEMA OPS Center, DHS NICC Watch Officer, and Nuclear SSA via email.
* * * UPDATE FROM LUKE HEDGES TO JOHN SHOEMAKER AT 2037 ON 5/9/15 * * *
"Oil from 31 Main Transformer has spilled into the discharge canal and has made its way into the river. Plant personnel are sandbagging drains and release paths. IPEC [Indian Point Energy Center] has contacted its environmental contractor, who is expected onsite at 2100 EDT to assist with cleanup. The National Response Center was notified at 1945 EDT and issued notification number 1116011. A message was left with the Westchester County Department of Health at 1953 EDT. The NY State DEC [Department of Environment Conservation] was contacted at 1955 EDT and issued notification number 1501459."
The licensee has notified the NRC Resident Inspector.
Indian Point Unit 3 remains in an Unusual Event at this time.
Notified R1DO (Schroeder).
* * * UPDATE FROM LUKE HEDGES TO JOHN SHOEMAKER AT 2141 ON 5/9/15 * * *
"Indian Point Unit 3 exited the Unusual Event at 2103 EDT. The basis for exiting the Unusual Event is that the fire is out and field operators report they have been successful in cooling the transformer."
The licensee has notified the NRC Resident Inspector and state and local authorities.
Notified R1DO (Schroeder), R1RA (Lew), NRR (Dean), NRR EO (Morris), NRR EO (Howe), and IRD (Grant).
Notified DHS SWO, FEMA OPS Center, DHS NICC Watch Officer, and Nuclear SSA via email.
Power Reactor
Event Number: 51061
Facility: DAVIS BESSE
Region: 3 State: OH
Unit: [1] [] []
RX Type: [1] B&W-R-LP
NRC Notified By: JOHN PHILLIPPE
HQ OPS Officer: JOHN SHOEMAKER
Region: 3 State: OH
Unit: [1] [] []
RX Type: [1] B&W-R-LP
NRC Notified By: JOHN PHILLIPPE
HQ OPS Officer: JOHN SHOEMAKER
Notification Date: 05/09/2015
Notification Time: 19:45 [ET]
Event Date: 05/09/2015
Event Time: 18:55 [EDT]
Last Update Date: 05/09/2015
Notification Time: 19:45 [ET]
Event Date: 05/09/2015
Event Time: 18:55 [EDT]
Last Update Date: 05/09/2015
Emergency Class: UNUSUAL EVENT
10 CFR Section:
50.72(a) (1) (i) - EMERGENCY DECLARED 50.72(b)(3)(iv)(A) - VALID SPECIF SYS ACTUATION 50.72(b)(2)(iv)(B) - RPS ACTUATION - CRITICAL
10 CFR Section:
50.72(a) (1) (i) - EMERGENCY DECLARED 50.72(b)(3)(iv)(A) - VALID SPECIF SYS ACTUATION 50.72(b)(2)(iv)(B) - RPS ACTUATION - CRITICAL
Person (Organization):
RICHARD SKOKOWSKI (R3DO)
PEDERSON (R3RA)
JENNIFER UHLE (NRR)
SCOTT MORRIS (NRR)
JEFFERY GRANT (IRD)
RICHARD SKOKOWSKI (R3DO)
PEDERSON (R3RA)
JENNIFER UHLE (NRR)
SCOTT MORRIS (NRR)
JEFFERY GRANT (IRD)
| Unit | SCRAM Code | RX Crit | Initial PWR | Initial RX Mode | Current PWR | Current RX Mode |
|---|---|---|---|---|---|---|
| 1 | M/R | Y | 100 | Power Operation | 0 | Hot Standby |
UNUSUAL EVENT DECLARED DUE TO STEAM LEAK IN THE TURBINE BUILDING
At 1855 EDT, a steam leak from the #1 moisture separator reheater in the turbine building was reported to the control room. Operators performed a rapid down power to approximately 30% at which time the reactor was manually tripped. At 1910 EDT an Unusual Event was declared. The steam feed rupture control system was manually initiated (this includes actuation of both turbine-driven Auxiliary Feedwater Pumps) and the steam leak was isolated. Station air compressor #2 (non-safety related) tripped. Station air compressor #1 automatically started.
The unit is currently in mode 3 (Hot Standby) and stable. Steam is being discharged through the atmospheric dumps as a means of decay heat removal. There is no known primary to secondary leakage. All systems functioned as expected. There were no reported injuries and personnel accountability is in progress.
The licensee notified state and local agencies and informed the NRC Resident Inspector.
Notified DHS SWO, FEMA Ops Center, NICC Watch Officer and FEMA NWC and NuclearSSA via email.
* * * UPDATE AT 2201 EDT ON 5/9/15 FROM GERRY WOLF TO S. SANDIN * * *
The licensee exited the Unusual Event at 2121 EDT based on the following:
"At 2121 hours EDT, the Unusual Event at the Davis-Besse Nuclear Power Station was terminated. The steam leak has been isolated and plant conditions are stable. Cooling continues to be maintained via the auxiliary feedwater system.
"The initiation of auxiliary feedwater at the start of the event is reportable as a Specified System Actuation per 10CFR50.72(b)(3)(iv)(A)."
The licensee notified state and local agencies and informed the NRC Resident Inspector.
Notified R3DO (Skokowski), NRR EO (Morris) and IRD (Grant).
Notified DHS SWO, FEMA Ops Center, NICC Watch Officer and FEMA NWC and NuclearSSA via email.
At 1855 EDT, a steam leak from the #1 moisture separator reheater in the turbine building was reported to the control room. Operators performed a rapid down power to approximately 30% at which time the reactor was manually tripped. At 1910 EDT an Unusual Event was declared. The steam feed rupture control system was manually initiated (this includes actuation of both turbine-driven Auxiliary Feedwater Pumps) and the steam leak was isolated. Station air compressor #2 (non-safety related) tripped. Station air compressor #1 automatically started.
The unit is currently in mode 3 (Hot Standby) and stable. Steam is being discharged through the atmospheric dumps as a means of decay heat removal. There is no known primary to secondary leakage. All systems functioned as expected. There were no reported injuries and personnel accountability is in progress.
The licensee notified state and local agencies and informed the NRC Resident Inspector.
Notified DHS SWO, FEMA Ops Center, NICC Watch Officer and FEMA NWC and NuclearSSA via email.
* * * UPDATE AT 2201 EDT ON 5/9/15 FROM GERRY WOLF TO S. SANDIN * * *
The licensee exited the Unusual Event at 2121 EDT based on the following:
"At 2121 hours EDT, the Unusual Event at the Davis-Besse Nuclear Power Station was terminated. The steam leak has been isolated and plant conditions are stable. Cooling continues to be maintained via the auxiliary feedwater system.
"The initiation of auxiliary feedwater at the start of the event is reportable as a Specified System Actuation per 10CFR50.72(b)(3)(iv)(A)."
The licensee notified state and local agencies and informed the NRC Resident Inspector.
Notified R3DO (Skokowski), NRR EO (Morris) and IRD (Grant).