The U.S. Nuclear Regulatory Commission is in the process of rescinding or revising guidance and policies posted on this webpage in accordance with Executive Order 14151 Ending Radical and Wasteful Government DEI Programs and Preferencing, and Executive Order 14168 Defending Women From Gender Ideology Extremism and Restoring Biological Truth to the Federal Government. In the interim, any previously issued diversity, equity, inclusion, or gender-related guidance on this webpage should be considered rescinded that is inconsistent with these Executive Orders.

Event Notification Report for August 11, 1999

                    U.S. Nuclear Regulatory Commission
                              Operations Center

                              Event Reports For
                           08/10/1999 - 08/11/1999

                              ** EVENT NUMBERS **

35782  35790  35988  36010  36011  36012  36013  

+------------------------------------------------------------------------------+
|General Information or Other                     |Event Number:   35782       |
+------------------------------------------------------------------------------+
+------------------------------------------------------------------------------+
| REP ORG:  NUCLEAR LOGISTICS INC                |NOTIFICATION DATE: 06/01/1999|
|LICENSEE:  NUCLEAR LOGISTICS INC                |NOTIFICATION TIME: 11:07[EDT]|
|    CITY:  FORT WORTH               REGION:  4  |EVENT DATE:        04/19/1999|
|  COUNTY:                            STATE:  TX |EVENT TIME:             [CDT]|
|LICENSE#:                        AGREEMENT:  Y  |LAST UPDATE DATE:  08/10/1999|
|  DOCKET:                                       |+----------------------------+
|                                                |PERSON          ORGANIZATION |
|                                                |VERN HODGE(FAX)      NRR     |
|                                                |RICHARD CONTE        R1      |
+------------------------------------------------+                             |
| NRC NOTIFIED BY:  SEIKEN (FAX)                 |                             |
|  HQ OPS OFFICER:  CHAUNCEY GOULD               |                             |
+------------------------------------------------+                             |
|EMERGENCY CLASS:          N/A                   |                             |
|10 CFR SECTION:                                 |                             |
|CCCC 21.21               UNSPECIFIED PARAGRAPH  |                             |
|                                                |                             |
|                                                |                             |
|                                                |                             |
|                                                |                             |
+------------------------------------------------------------------------------+

                                   EVENT TEXT                                   
+------------------------------------------------------------------------------+
| PART 21 REPORT -  DEVIATION IN A NUCLEAR LOGISTICS INC (NLI) DC POWER        |
| SUPPLY.                                                                      |
|                                                                              |
| A DEVIATION HAS BEEN IDENTIFIED IN A NLI DC POWER SUPPLY, P/N                |
| NLI-LGS-G-24-OV-R-8018 WHICH HAVE BEEN SUPPLIED AS A CLASS 1E COMPONENT,     |
| THAT ALLOWS A PREMATURE OVER VOLTAGE PROTECTION ACTUATION TO OCCUR IN A      |
| CIRCUIT SPECIFIC APPLICATION.  THIS CONDITION OCCURRED DURING DIESEL         |
| GENERATOR STARTUP, SPECIFICALLY DURING DIESEL GENERATOR LOADING.  THIS ISSUE |
| WAS DETERMINED TO BE A DEVIATION ON 4/19/99, HOWEVER, TO DATE NLI HAS NOT    |
| BEEN ABLE TO DUPLICATE THIS CONDITION DURING LABORATORY TESTING.  DATA       |
| COLLECTION AND ADDITIONAL TESTING IS BEING PERFORMED TO RESOLVE THE          |
| DEVIATION.  IT THE PREMATURE OVER VOLTAGE PROTECTION ACTUATION IS DETERMINED |
| TO BE THE RESULT OF THE POWER SUPPLY DESIGN, OTHER NLI-L SERIES POWER        |
| SUPPLIES WILL BE TESTED TO DETERMINE THEIR SUSCEPTIBILITY TO SIMILAR         |
| CONDITIONS.  TESTING AND EVALUATION ACTIVITIES WILL BE COMPLETED ON 7/16/99. |
| THESE COMPONENTS HAVE BEEN SUPPLIED AS SAFETY-RELATED COMPONENTS TO PUBLIC   |
| SERVICE ELECTRIC AND GAS COMPANY.                                            |
|                                                                              |
| *** UPDATE ON 8/10/99 FROM NLI (FAX) TO POERTNER ***                         |
|                                                                              |
| NLI has been unable to duplicate the condition in laboratory testing.        |
| Additional field testing is scheduled for late August.  NLI has requested an |
| extension to September 10, 1999 to determine the reportability of the        |
| condition.                                                                   |
|                                                                              |
| HOO notified R1DO (GRAY),  NRR/PCED Vern Hodge (FAX)                         |
+------------------------------------------------------------------------------+

+------------------------------------------------------------------------------+
|Fuel Cycle Facility                              |Event Number:   35790       |
+------------------------------------------------------------------------------+
+------------------------------------------------------------------------------+
| FACILITY: PADUCAH GASEOUS DIFFUSION PLANT      |NOTIFICATION DATE: 06/03/1999|
|   RXTYPE: URANIUM ENRICHMENT FACILITY          |NOTIFICATION TIME: 14:44[EDT]|
| COMMENTS: 2 DEMOCRACY CENTER                   |EVENT DATE:        06/02/1999|
|           6903 ROCKLEDGE DRIVE                 |EVENT TIME:        16:30[CDT]|
|           BETHESDA, MD 20817    (301)564-3200  |LAST UPDATE DATE:  08/10/1999|
|    CITY:  PADUCAH                  REGION:  3  +-----------------------------+
|  COUNTY:  McCRACKEN                 STATE:  KY |PERSON          ORGANIZATION |
|LICENSE#:  GDP-1                 AGREEMENT:  Y  |DAVID HILLS          R3      |
|  DOCKET:  0707001                              |DON COOL             NMSS    |
+------------------------------------------------+                             |
| NRC NOTIFIED BY:  THOMAS WHITE                 |                             |
|  HQ OPS OFFICER:  FANGIE JONES                 |                             |
+------------------------------------------------+                             |
|EMERGENCY CLASS:          N/A                   |                             |
|10 CFR SECTION:                                 |                             |
|OCBA 76.120(c)(2)(i)     ACCID MT EQUIP FAILS   |                             |
|                                                |                             |
|                                                |                             |
|                                                |                             |
|                                                |                             |
+------------------------------------------------------------------------------+

                                   EVENT TEXT                                   
+------------------------------------------------------------------------------+
| THREE SPRINKLER SYSTEMS DECLARED INOPERABLE DUE TO CORRODED HEADS (24-hour   |
| report)                                                                      |
|                                                                              |
| The following text is a portion of a facsimile received from Paducah:        |
|                                                                              |
| "On 06/02/99 at 1630 CDT, the Plant Shift Superintendent (PSS) was notified  |
| that numerous sprinkler heads were corroded, affecting 16 sprinkler systems  |
| in C-337 and one system in C-333, such that the ability of the sprinklers to |
| flow sufficient water was called into question.  Subsequently, these         |
| sprinkler systems were declared inoperable, and TSR-required actions         |
| establishing roving fire patrols were initiated.  This deficiency was        |
| detected during scheduled system inspections conducted by Fire Protection    |
| personnel.  Currently, functionality of the sprinkler heads has not been     |
| fully evaluated by Fire Protection personnel, and the remaining cascade      |
| buildings are currently being inspected, and if necessary, this report will  |
| be updated to identify any additional areas.                                 |
|                                                                              |
| "It has been determined that this event is reportable under                  |
| 10CFR76.120(c)(2) as an event in which equipment is disabled or fails to     |
| function as designed."                                                       |
|                                                                              |
| The NRC resident inspector has been notified of this event.                  |
|                                                                              |
| * * * UPDATE AT 1022 ON 06/04/99 FROM CAGE TO TROCINE * * *                  |
|                                                                              |
| The following text is a portion of a facsimile received from Paducah:        |
|                                                                              |
| "Two sprinkler heads on system D-1 in C-337 and two sprinkler heads on       |
| system 27 in C-335 were identified to also be corroded.  These were          |
| identified to the PSS on 06/03/99 at 1600 CDT and 1601 CDT, respectively,    |
| and determined to require an update to this report by the PSS.               |
|                                                                              |
| "It has been determined that this event is reportable under                  |
| 10CFR76.120(c)(2) as an event in which equipment is disabled or fails to     |
| function as designed."                                                       |
|                                                                              |
| Paducah personnel notified the NRC resident inspector of this update.  The   |
| NRC operations officer notified the R3DO (Hills) and NMSS EO (Combs).        |
|                                                                              |
| * * * UPDATE AT 2152 ON 06/17/99 FROM WALKER TO POERTNER * * *               |
|                                                                              |
| The following text is a portion of a facsimile received from Paducah:        |
|                                                                              |
| "Three sprinkler heads on system C-15 and five sprinkler heads on system B-8 |
| in C-333 were identified to also be corroded.  The PSS was notified of this  |
| condition at 1300 CDT on 06/17/99 and determined that an update to this      |
| report was required."                                                        |
|                                                                              |
| "It has been determined that this event is reportable under                  |
| 10CFR76.120(c)(2) as an event in which equipment is disabled or fails to     |
| function as designed."                                                       |
|                                                                              |
| Paducah personnel notified the NRC resident inspector of this update.  The   |
| NRC operations officer notified the R3DO (Madera).                           |
|                                                                              |
| * * * UPDATE 1440 6/18/1999 FROM UNDERWOOD TAKEN BY STRANSKY * * *           |
|                                                                              |
| "Two sprinkler heads on system C-15 and one sprinkler head on system B-8 in  |
| C-333 were identified to have corrosion.  The PSS was notified of this       |
| condition at 1350 CDT on 06/18/99.  The area of the fire patrol for system   |
| C-15 was expanded to include the two heads identified as corroded.  The one  |
| head on system B-8 was in the area already being patrolled.  The PSS         |
| determined that an update to this report was required."                      |
|                                                                              |
| The NRC resident inspector has been informed of this update.  Notified R3DO  |
| (Madera).                                                                    |
|                                                                              |
| * * * UPDATE 1315 6/25/1999 FROM WALKER TAKEN BY STRANSKY * * *              |
|                                                                              |
| "Two sprinkler heads on system D-8 and three sprinkler heads on system D-7   |
| in C-337 were identified to have corrosion.  The PSS was notified of the     |
| condition on system D-8 at 0125 CDT on 06/25/99 and at 1019 CDT on 06/25/99  |
| for system D-7.  Both systems were immediately declared inoperable and LCO   |
| fire patrol actions were implemented.  It was determined that an update to   |
| this report was required."                                                   |
|                                                                              |
| The NRC resident inspector has been informed of this update.  Notified R3DO  |
| (Jordan).                                                                    |
|                                                                              |
| * * * UPDATE 2119 7/30/1999 FROM CAGE TAKEN BY STRANSKY * * *                |
|                                                                              |
| "Five sprinkler heads and one sprinkler piping tee on C-337 system D-7 were  |
| identified to have corrosion. The PSS was notified of these corroded system  |
| parts and declared the system inoperable at 0931 CDT on 07/30/99.  LCO       |
| required fire patrols of the affected area were initiated.  The PSS          |
| determined that an update to this event report was required."                |
|                                                                              |
| The NRC resident inspector has been informed of this update.  Notified R3DO  |
| (Wright).                                                                    |
|                                                                              |
| * * * UPDATE 1655 7/31/1999 FROM WHITE TAKEN BY STRANSKY * * *               |
|                                                                              |
| "Two sprinkler heads on C-337 System D-1 were identified to have corrosion.  |
| The PSS was notified of these corroded system parts and declared the system  |
| inoperable at 1155 on 7/31/99. LCO required fire patrols of the affected     |
| area were initiated. The PSS determined that an update to this report was    |
| required."                                                                   |
|                                                                              |
| The NRC resident inspector has been informed of this update. Notified R3DO   |
| (Wright).                                                                    |
|                                                                              |
| * * * UPDATE 1546 8/10/1999 FROM WHITE TAKEN BY STRANSKY * * *               |
|                                                                              |
| "Two sprinkler heads on C-337 system C-15 were identified to have corrosion. |
| The PSS was notified of these corroded system parts and declared the system  |
| inoperable at 1130 on 8/10/99. LCO required fire patrols of the affected     |
| area were initiated. The PSS determined that an update to this report was    |
| required."                                                                   |
|                                                                              |
| The NRC resident inspector has been informed of this update. Notified R3DO   |
| (Burgess).                                                                   |
+------------------------------------------------------------------------------+

!!!!!!!!! THIS EVENT HAS BEEN RETRACTED. THIS EVENT HAS BEEN RETRACTED  !!!!!!!
+------------------------------------------------------------------------------+
|Power Reactor                                    |Event Number:   35988       |
+------------------------------------------------------------------------------+
+------------------------------------------------------------------------------+
| FACILITY: WATERFORD                REGION:  4  |NOTIFICATION DATE: 08/03/1999|
|    UNIT:  [3] [] []                 STATE:  LA |NOTIFICATION TIME: 12:10[EDT]|
|   RXTYPE: [3] CE                               |EVENT DATE:        08/02/1999|
+------------------------------------------------+EVENT TIME:        16:43[CDT]|
| NRC NOTIFIED BY:  WEMETT                       |LAST UPDATE DATE:  08/10/1999|
|  HQ OPS OFFICER:  CHAUNCEY GOULD               +-----------------------------+
+------------------------------------------------+PERSON          ORGANIZATION |
|EMERGENCY CLASS:          N/A                   |TOM STETKA           R4      |
|10 CFR SECTION:                                 |                             |
|AIND 50.72(b)(2)(iii)(D) ACCIDENT MITIGATION    |                             |
|NLCO                     TECH SPEC LCO A/S      |                             |
|                                                |                             |
|                                                |                             |
+-----+----------+-------+--------+-----------------+--------+-----------------+
|UNIT |SCRAM CODE|RX CRIT|INIT PWR|   INIT RX MODE  |CURR PWR|  CURR RX MODE   |
+-----+----------+-------+--------+-----------------+--------+-----------------+
|3     N          N       0        Hot Shutdown     |0        Cold Shutdown    |
|                                                   |                          |
|                                                   |                          |
+------------------------------------------------------------------------------+
                                   EVENT TEXT                                   
+------------------------------------------------------------------------------+
| THE LICENSEE DETERMINED A CONDITION THAT WOULD HAVE PREVENTED THE CVC SYSTEM |
| FROM FULFILLING ITS INTENDED SAFETY FUNCTION.                                |
|                                                                              |
| At 1643 CDT on 8/2/99 with charging pumps 'A' and 'B' operating, the control |
| room received the "CHARGING HEADER FLOW LO" annunciator.  The operator       |
| observed that charging header flow indicated 0.0 gpm. The control room       |
| personnel selectively secured charging pump 'A' and observed that the        |
| charging header flow returned to the expected flow (44.0 gpm) for a single   |
| operating charging pump.  At 1650 charging pump 'A' was restarted to         |
| investigate if the condition was repeatable.  Operations personnel were      |
| observing the charging pumps locally during this period.  The condition was  |
| identified as repeatable, however, operations personnel could not            |
| conclusive identify locally any abnormalities.  Charging pump 'A' was        |
| declared inoperable and was secured in the "OFF" condition to preclude any   |
| unplanned starts due to automatic actuations (pressurizer level deviation or |
| SIAS) and Technical Specification 3.1.2.4 was entered at 1654 (CDT). The     |
| on-coming shift isolated and danger tagged charging pump 'A'.   After review |
| of the information by licensing personnel on August 3, 1999, it was          |
| determined that this failure may have prevented the CVC System from          |
| fulfilling its intended safety function.                                     |
| The plant was in a 72 hr LCO action statement to have both charging pumps    |
| operable while in modes 1,2,3, & 4.  The plant entered mode 5 within the 72  |
| hr action statement.  The cause of the problem is being investigated.        |
|                                                                              |
| The resident inspector will be notified.                                     |
|                                                                              |
| ***RETRACTION on 08/10/99 at 1107 ET by Arthur Wemett taken by MacKinnon***  |
|                                                                              |
|                                                                              |
| A team was appointed to investigate the event that was observed on August 2, |
| 1999. Plant  data and discussions with individuals were performed to         |
| identify pertinent facts and potential failure modes.  Additional            |
| troubleshooting was performed August 6, 1999 to confirm which components     |
| were operating correctly or possibly failed.  The result of the              |
| troubleshooting concluded that a failure of the charging flow transmitter    |
| was occurring at low pressures (indicator was sporadic).  The flow was       |
| verified by other plant parameters (i.e., temperatures, pressures, and       |
| levels) and by the use of a temporary installed ultrasonic flow meter.  The  |
| transmitter was removed from service and replaced.  The transmitter was      |
| tested by maintenance and the failure could be repeated.                     |
|                                                                              |
| The failure of the charging flow transmitter gave the indication that        |
| charging flow was lost but at no time during the plant evolution was actual  |
| flow lost.   Based on this information we are retracting the four hour       |
| notification under 10CFR50.72(b)(2)(iii)(D) that was made on August 3,       |
| 1999.                                                                        |
|                                                                              |
| HOO notified R4DO (Powers).                                                  |
+------------------------------------------------------------------------------+

+------------------------------------------------------------------------------+
|Fuel Cycle Facility                              |Event Number:   36010       |
+------------------------------------------------------------------------------+
+------------------------------------------------------------------------------+
| FACILITY: PORTSMOUTH GASEOUS DIFFUSION PLANT   |NOTIFICATION DATE: 08/10/1999|
|   RXTYPE: URANIUM ENRICHMENT FACILITY          |NOTIFICATION TIME: 09:49[EDT]|
| COMMENTS: 2 DEMOCRACY CENTER                   |EVENT DATE:        08/09/1999|
|           6903 ROCKLEDGE DRIVE                 |EVENT TIME:        11:30[EDT]|
|           BETHESDA, MD 20817    (301)564-3200  |LAST UPDATE DATE:  08/10/1999|
|    CITY:  PIKETON                  REGION:  3  +-----------------------------+
|  COUNTY:  PIKE                      STATE:  OH |PERSON          ORGANIZATION |
|LICENSE#:  GDP-2                 AGREEMENT:  N  |BRUCE BURGESS        R3      |
|  DOCKET:  0707002                              |DON COOL             NMSS    |
+------------------------------------------------+                             |
| NRC NOTIFIED BY:  RICK LARSON                  |                             |
|  HQ OPS OFFICER:  WILLIAM POERTNER             |                             |
+------------------------------------------------+                             |
|EMERGENCY CLASS:          N/A                   |                             |
|10 CFR SECTION:                                 |                             |
|NBNL                     RESPONSE-BULLETIN      |                             |
|                                                |                             |
|                                                |                             |
|                                                |                             |
|                                                |                             |
+------------------------------------------------------------------------------+

                                   EVENT TEXT                                   
+------------------------------------------------------------------------------+
| BULLETIN 91-01 24 HOUR REPORT                                                |
|                                                                              |
| Operations personnel during a walkdown of the seal exhaust system discovered |
| that a nuclear criticality safety analysis (NCSA) requirement, maximum oil   |
| volume, could not be verified when an oil level was observed in the pumps    |
| separator's sight glass.  The pumps in question were used for the highly     |
| enriched uranium (HEU) program, and after it's suspension, prior to March    |
| 1997, the pumps were placed out of service.  Visible oil level in the sight  |
| glass without supporting documentation for oil capacity of these pumps       |
| constitutes a loss of one control (Volume) for double contingency.  The      |
| second control (Interaction) was maintained.                                 |
|                                                                              |
| There was no loss of hazardous/radioactive material or                       |
| radioactive/radiological contamination exposure as a result of this event.   |
|                                                                              |
| The licensee notified the NRC resident inspector and DOE.                    |
+------------------------------------------------------------------------------+

+------------------------------------------------------------------------------+
|Power Reactor                                    |Event Number:   36011       |
+------------------------------------------------------------------------------+
+------------------------------------------------------------------------------+
| FACILITY: COMANCHE PEAK            REGION:  4  |NOTIFICATION DATE: 08/10/1999|
|    UNIT:  [1] [2] []                STATE:  TX |NOTIFICATION TIME: 14:09[EDT]|
|   RXTYPE: [1] W-4-LP,[2] W-4-LP                |EVENT DATE:        08/10/1999|
+------------------------------------------------+EVENT TIME:        13:00[CDT]|
| NRC NOTIFIED BY:  GREGORY BRYAN                |LAST UPDATE DATE:  08/10/1999|
|  HQ OPS OFFICER:  BOB STRANSKY                 +-----------------------------+
+------------------------------------------------+PERSON          ORGANIZATION |
|EMERGENCY CLASS:          N/A                   |DALE POWERS          R4      |
|10 CFR SECTION:                                 |                             |
|NINF                     INFORMATION ONLY       |                             |
|                                                |                             |
|                                                |                             |
|                                                |                             |
+-----+----------+-------+--------+-----------------+--------+-----------------+
|UNIT |SCRAM CODE|RX CRIT|INIT PWR|   INIT RX MODE  |CURR PWR|  CURR RX MODE   |
+-----+----------+-------+--------+-----------------+--------+-----------------+
|1     N          Y       100      Power Operation  |100      Power Operation  |
|2     N          Y       100      Power Operation  |100      Power Operation  |
|                                                   |                          |
+------------------------------------------------------------------------------+
                                   EVENT TEXT                                   
+------------------------------------------------------------------------------+
| COURTESY CALL REGARDING DISCOVERY OF FISH KILL IN CIRCULATING WATER INTAKE   |
|                                                                              |
| The licensee notified the Texas State Parks and Wildlife Agency regarding    |
| the discovery of several thousand dead shad in the vicinity of the           |
| circulating water intake. The state informed the licensee that this          |
| discovery was not reportable, hence the licensee is providing this           |
| notification to the NRC as a courtesy. The following information was         |
| provided by the licensee via facsimile:                                      |
|                                                                              |
| "Approximately two to three thousand shad were observed floating in the      |
| vicinity of the circulating water intake area. No sport fish were observed   |
| in this area. The likely cause of the die-off was stress to the shad due to  |
| dissolved oxygen depletion and high ambient temperatures. A survey of the    |
| main reservoir revealed few (less than ten) floating fish in the main water  |
| body. Consequently, this condition appears to be limited to the intake area  |
| only. A courtesy call to the Texas Parks and Wildlife was made at            |
| approximately 1100 on 08/07/99. The agency indicated that no formal          |
| reporting was required. A follow-up survey of the main reservoir on 08/08/99 |
| confirmed that only shad in the intake area remained affected and no         |
| floating fish were observed in the main water body of the reservoir. A       |
| walk-down of the intake structure on 08/09/99 revealed several thousand      |
| floating shad collected in front of the Unit 1 trash racks extending out     |
| approximately 10 feet from the trash racks."                                 |
|                                                                              |
| The NRC resident inspector has been informed of this notification by the     |
| licensee.                                                                    |
+------------------------------------------------------------------------------+

+------------------------------------------------------------------------------+
|Power Reactor                                    |Event Number:   36012       |
+------------------------------------------------------------------------------+
+------------------------------------------------------------------------------+
| FACILITY: CLINTON                  REGION:  3  |NOTIFICATION DATE: 08/10/1999|
|    UNIT:  [1] [] []                 STATE:  IL |NOTIFICATION TIME: 14:23[EDT]|
|   RXTYPE: [1] GE-6                             |EVENT DATE:        08/10/1999|
+------------------------------------------------+EVENT TIME:        12:30[CDT]|
| NRC NOTIFIED BY:  ROBERT POWERS                |LAST UPDATE DATE:  08/10/1999|
|  HQ OPS OFFICER:  BOB STRANSKY                 +-----------------------------+
+------------------------------------------------+PERSON          ORGANIZATION |
|EMERGENCY CLASS:          N/A                   |BRUCE BURGESS        R3      |
|10 CFR SECTION:                                 |                             |
|AOUT 50.72(b)(1)(ii)(B)  OUTSIDE DESIGN BASIS   |                             |
|                                                |                             |
|                                                |                             |
|                                                |                             |
+-----+----------+-------+--------+-----------------+--------+-----------------+
|UNIT |SCRAM CODE|RX CRIT|INIT PWR|   INIT RX MODE  |CURR PWR|  CURR RX MODE   |
+-----+----------+-------+--------+-----------------+--------+-----------------+
|1     N          Y       100      Power Operation  |100      Power Operation  |
|                                                   |                          |
|                                                   |                          |
+------------------------------------------------------------------------------+
                                   EVENT TEXT                                   
+------------------------------------------------------------------------------+
| EMERGENCY DIESEL GENERATOR DECLARED INOPERABLE DUE TO FUEL OIL LEAK          |
|                                                                              |
| "Abnormal readings from the lube oil analysis of the division 2 diesel       |
| generator lead to further testing of its lube oil. Gas chromatography        |
| analysis of the division 2 diesel generator lube oil showed a 5.7% fuel oil  |
| dilution. Vendor recommendations were to not operate the diesel with greater |
| than 5.0% fuel oil dilution. The division 2 diesel generator was tagged out  |
| for maintenance and declared inoperable on 8/9/99 at 1330 central time.      |
| During maintenance of the division 2 diesel generator it was discovered that |
| the 12th cylinder of the 16 cylinder engine fuel injector return line        |
| fitting was weeping fuel oil.                                                |
|                                                                              |
| "This notification is being made pursuant to 10CFR5072(b)(1)(ii)(B) as a     |
| condition outside of the design basis of the plant because of the discovery  |
| that the division 2 diesel generator has been incapable of performing its    |
| design function (intended safety function) for an extended period of time    |
| during operation."                                                           |
|                                                                              |
| The NRC resident inspector has been informed of this notification by the     |
| licensee.                                                                    |
+------------------------------------------------------------------------------+

+------------------------------------------------------------------------------+
|Power Reactor                                    |Event Number:   36013       |
+------------------------------------------------------------------------------+
+------------------------------------------------------------------------------+
| FACILITY: SURRY                    REGION:  2  |NOTIFICATION DATE: 08/10/1999|
|    UNIT:  [1] [2] []                STATE:  VA |NOTIFICATION TIME: 17:14[EDT]|
|   RXTYPE: [1] W-3-LP,[2] W-3-LP                |EVENT DATE:        08/10/1999|
+------------------------------------------------+EVENT TIME:        16:30[EDT]|
| NRC NOTIFIED BY:  RAWLEIGH DILLARD             |LAST UPDATE DATE:  08/10/1999|
|  HQ OPS OFFICER:  BOB STRANSKY                 +-----------------------------+
+------------------------------------------------+PERSON          ORGANIZATION |
|EMERGENCY CLASS:          N/A                   |CHARLES OGLE         R2      |
|10 CFR SECTION:                                 |                             |
|AOUT 50.72(b)(1)(ii)(B)  OUTSIDE DESIGN BASIS   |                             |
|                                                |                             |
|                                                |                             |
|                                                |                             |
+-----+----------+-------+--------+-----------------+--------+-----------------+
|UNIT |SCRAM CODE|RX CRIT|INIT PWR|   INIT RX MODE  |CURR PWR|  CURR RX MODE   |
+-----+----------+-------+--------+-----------------+--------+-----------------+
|1     N          Y       100      Power Operation  |100      Power Operation  |
|2     N          Y       100      Power Operation  |100      Power Operation  |
|                                                   |                          |
+------------------------------------------------------------------------------+
                                   EVENT TEXT                                   
+------------------------------------------------------------------------------+
| CONTROL ROOM PENETRATION OUTSIDE OF 10 CFR 50, APPENDIX R DESIGN BASIS       |
|                                                                              |
| The licensee has identified a 12" x 12" through-wall penetration between the |
| emergency switchgear room and the control room annex that was not filled in  |
| accordance with the licensee's fire barrier construction standards. The      |
| penetration was filled with mineral wool that did not meet the three hour    |
| fire rating requirements for the control room. The licensee has posted a     |
| continuous fire watch in this area as a compensatory measure. The NRC        |
| resident inspector will be informed by the licensee.                         |
+------------------------------------------------------------------------------+
