Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report
Accession Number: ML22194A236
Date Released: Monday, November 7, 2022
Package Contents
The following links on this page are to Adobe Portable Document Format (PDF) files. To obtain a free viewer for displaying this format, see our Plugins, Viewers, and Other Tools.
- ML22194A340 - Virgil C. Summer Nuclear Station Unit 1, Submittal of Revision 22 to Updated Final Safety Analysis Report (6/27/2022)
- ML22194A176 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Revision Summary (109 page(s), 6/27/2022)
- ML22194A291 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Chapter 1, Introduction and General Description of Plant (174 page(s), 6/27/2022)
- ML22194A187 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Chapter 2, Site Characteristics (1218 page(s), 6/27/2022)
- ML22194A118 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Chapter 3, Design of Structures, Components, Equipment and Systems (801 page(s), 6/27/2022)
- ML22194A117 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Chapter 4, Reactor (267 page(s), 6/27/2022)
- ML22194A342 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Chapter 5, Reactor Coolant System (300 page(s), 6/27/2022)
- ML22194A309 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Chapter 6, Engineered Safety Features (589 page(s), 6/27/2022)
- ML22194A220 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Chapter 7, Instrumentation and Controls (274 page(s), 6/27/2022)
- ML22194A184 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Chapter 8, Electric Power (229 page(s), 6/27/2022)
- ML22194A185 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Chapter 9, Auxiliary Systems - Redacted (401 page(s), 6/27/2022)
- ML22194A270 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Chapter 10, Steam and Power Conversion System (135 page(s), 6/27/2022)
- ML22194A113 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Chapter 11, Radioactive Waste Management (180 page(s), 6/27/2022)
- ML22194A192 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Chapter 12, Radiation Protection - Redacted (160 page(s), 6/27/2022)
- ML22194A296 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Chapter 13, Conduct of Operations (52 page(s), 6/27/2022)
- ML22194A215 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Chapter 14, Initial Tests and Operation (154 page(s), 6/27/2022)
- ML22194A143 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Chapter 15, Accident Analysis (454 page(s), 6/27/2022)
- ML22194A226 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Chapter 16, Technical Specifications (4 page(s), 6/27/2022)
- ML22194A189 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Chapter 17, Quality Assurance (52 page(s), 6/27/2022)
- ML22194A248 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Chapter 18, Aging Management Programs and Activities (33 page(s), 6/27/2022)
- ML22194A317 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 1.2-10, Redacted (1 page(s), 6/27/2022)
- ML22194A198 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 1.2-11, Redacted (1 page(s), 6/27/2022)
- ML22194A224 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 1.2-12, 12.1-15, Redacted (1 page(s), 6/27/2022)
- ML22194A323 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 1.2-13, Redacted (1 page(s), 6/27/2022)
- ML22194A312 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 1.2-1 4, Redacted (1 page(s), 6/27/2022)
- ML22194A326 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 1.2-15, 12.1-19, 12a.4-7, Redacted (1 page(s), 6/27/2022)
- ML22194A313 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 1.2-16, 12.1-19a, Redacted (1 page(s), 6/27/2022)
- ML22194A268 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 1.2-17, Figure 12.1-20, Redacted (1 page(s), 6/27/2022)
- ML22194A275 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 1.2-18, Redacted (1 page(s), 6/27/2022)
- ML22194A201 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 1.2-19, Redacted (1 page(s), 6/27/2022)
- ML22194A288 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 1.2-1, Redacted (1 page(s), 6/27/2022)
- ML22194A210 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 1.2-20, Redacted (1 page(s), 6/27/2022)
- ML22194A319 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 1.2-21, Redacted (1 page(s), 6/27/2022)
- ML22194A233 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 1.2-22, Redacted (1 page(s), 6/27/2022)
- ML22194A145 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 1.2-23, Figure 1.2-24, Redacted (1 page(s), 6/27/2022)
- ML22194A259 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 1.2-23, Redacted (1 page(s), 6/27/2022)
- ML22194A204 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 1.2-25, 12.1-5, Redacted (1 page(s), 6/27/2022)
- ML22194A170 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 1.2-26, Redacted (1 page(s), 6/27/2022)
- ML22194A232 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 1.2-27, Redacted (1 page(s), 6/27/2022)
- ML22194A178 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 1.2-28, Redacted (1 page(s), 6/27/2022)
- ML22194A181 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 1.2-28a, Redacted (1 page(s), 6/27/2022)
- ML22194A222 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 1.2-29, Redacted (1 page(s), 6/27/2022)
- ML22194A299 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 1.2-2, Redacted (1 page(s), 6/27/2022)
- ML22194A328 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 1.2-3, Fig. 12.1-2, 12.1-11, Redacted (1 page(s), 6/27/2022)
- ML22194A255 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 1.2-4, Redacted (1 page(s), 6/27/2022)
- ML22194A237 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 1.2-5 , 12.1-14, Redacted (1 page(s), 6/27/2022)
- ML22194A265 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 1.2-6, 12.1-16, 12A.4-6, Redacted (1 page(s), 6/27/2022)
- ML22194A297 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 1.2-8, Redacted (1 page(s), 6/27/2022)
- ML22194A216 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 1.2-9, 12.1-18, Redacted (6/27/2022)
- ML22194A300 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 1.2.7, Redacted (1 page(s), 6/27/2022)
- ML22194A221 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 2.4-1, Plot Plan - Service Water Pond: North, South and East Dams: Calculating Water Discharge Canal And Jetty (1 page(s), 6/27/2022)
- ML22194A324 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 2.4-6, Reference. (1 page(s), 6/27/2022)
- ML22194A195 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 2.5-108, Reference (1 page(s), 6/27/2022)
- ML22194A129 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 2.5-109, Reference (1 page(s), 6/27/2022)
- ML22194A286 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 3.8.73, Plant Layout Final Auxiliary & Control Building Section H-H Looking West (1 page(s), 6/27/2022)
- ML22194A151 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 5.1-1, Sheet 3B, Piping System Flow Diagram Reactor Coolant (1 page(s), 6/27/2022)
- ML22194A321 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 5.1-1-3C, Revision 7, System Flow Diagram Reactor Coolant (1 page(s), 6/27/2022)
- ML22194A177 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 5.1-1, Sheet 2, Revision 31, System Flow Diagram Reactor Coolant System (1 page(s), 6/27/2022)
- ML22194A179 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 5.1-1, Sheet 3A, System Flow Diagram Reactor Coolant (1 page(s), 6/27/2022)
- ML22194A140 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 5.1-1, Sheet 1, System Flow Diagram Reactor Coolant (1 page(s), 6/27/2022)
- ML22194A214 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 5.2-4, Reactor Vessel Support Shoe (1 page(s), 6/27/2022)
- ML22194A175 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 5.2-8, Piping System Floor Diagram, ECCS Check Valve Testing (1 page(s), 6/27/2022)
- ML22194A161 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 5.2-8A, Revision 28, Piping System Flow Diagram NSSS Carbon Dioxide and Nitrogen Supply (1 page(s), 6/27/2022)
- ML22194A231 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 5.5-4, Piping System Flow Diagram Residual Heat Removal (1 page(s), 6/27/2022)
- ML22194A171 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 7.6-8, Chemical Volume Control Sys-Pen Access Areas Plan & Sections Below EL 436'-0" (1 page(s), 6/27/2022)
- ML22194A209 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 5.2-9, Piping System Reactor Building Cooling Unit Drain (1 page(s), 6/27/2022)
- ML22194A285 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 6.2-46, Piping System Flow Diagram Reactor Building Spray System (1 page(s), 6/27/2022)
- ML22194A188 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 6.2-47, System Reactor Building Spray System Reactor Building Above Elevation 524'-0" (1 page(s), 6/27/2022)
- ML22194A263 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 6.2-49, Building Service System Flow Diagram R.B Cooling System (1 page(s), 6/27/2022)
- ML22194A241 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 6.2-50, Sheet 1, Reference (1 page(s), 6/27/2022)
- ML22194A116 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 6.2-50, Sheet 2, Reference (1 page(s), 6/27/2022)
- ML22194A307 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 6.2-50, Sheet 3, Reference (1 page(s), 6/27/2022)
- ML22194A163 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 6.2-50, Sheet 4, Reference (1 page(s), 6/27/2022)
- ML22194A166 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 6.2-60A, Penetration #309 Details (1 page(s), 6/27/2022)
- ML22194A242 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 6.2-70, Piping System Main Steam (Nuclear)- Reactor Building Plan & Sections Above Elev. 4.36'-0" (1 page(s), 6/27/2022)
- ML22194A310 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 6.2-82, Design Engineering (1 page(s), 6/27/2022)
- ML22194A186 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 6.2-83, Rev. 9, Reactor Building Spray System - Auxiliary Bldg Plan Below EL. 397'-0" (1 page(s), 6/27/2022)
- ML22194A274 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 6.2-83, Drawing E-304-662 (1 page(s), 6/27/2022)
- ML22194A306 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 6.2-84, Piping System Reactor Building Spray System - Auxiliary Bldg Sections & Details (1 page(s), 6/27/2022)
- ML22194A114 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 6.3.1, Sheet 1, System Flow Diagram Safety Injection (1 page(s), 6/27/2022)
- ML22194A298 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 6.3-1, Sheet 2, Rev. 14, System Flow Diagram Safety Injection (1 page(s), 6/27/2022)
- ML22194A251 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 6.3-1, Sheet 3, Piping System Flow Diagram Safety Injection (1 page(s), 6/27/2022)
- ML22194A160 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 7.2-1, Sheet 1, Functional Diagrams Index and Symbols (1 page(s), 6/27/2022)
- ML22194A325 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 7.2-1, Sheet 14, Functional Diagrams Auxiliary Feedwater Pumps Startup (1 page(s), 6/27/2022)
- ML22194A196 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 7.2-1, Sheet 15, Functional Diagrams Turbine rip Runback And other Signals (1 page(s), 6/27/2022)
- ML22194A280 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 7.2-1, Sheet 5, Functional Diagrams Primary Coolant System Trip Signals (1 page(s), 6/27/2022)
- ML22194A316 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 7.2-1, Sheet 8, Functional Diagrams Safeguard Actuation Signals (1 page(s), 6/27/2022)
- ML22194A223 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 7.3-1, Functional Diagram ESF Loading Sequence System (1 page(s), 6/27/2022)
- ML22194A148 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 7.4-1, Front View Arrangement Control Room Evacuation Panel XPN-7200-CE (1 page(s), 6/27/2022)
- ML22194A339 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 7.5-1, Containment Isolation A And Safety Injection ESF Monitor Lights (1 page(s), 6/27/2022)
- ML22194A289 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 7.5-2, I & C Monitor Lights Cold Leg and Hot Leg Recirculation ESF Monitor Lights (1 page(s), 6/27/2022)
- ML22194A335 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 7.5-3, Revision 15, I & C Monitor Lights Safety Injection (BOP) ESF Monitor Lights (1 page(s), 6/27/2022)
- ML22194A304 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 7.5-4, I & C Monitor Lights Containment Isolation Phase B And Reactor Building Spray ESF Monitor Lights (1 page(s), 6/27/2022)
- ML22194A260 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 7.6-3A, System Auxiliary Steam & Condensate Inter. & Aux Building Plans & Isometric Below EL 485'0" (1 page(s), 6/27/2022)
- ML22194A311 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 7.6-4, Piping System Auxiliary Steam Auxiliary Building Plan & Section Below El 436'-0" (1 page(s), 6/27/2022)
- ML22194A207 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 7.6-5, Piping System Aux, Steam Intermediate & Aux. Bldgs. Plans Below El 463'-0" (1 page(s), 6/27/2022)
- ML22194A137 - Virgil C. Summer Nuclear Station, Unit 1 Revision 22 to Updated Final Safety Analysis Report, Figure 7.6-6, Piping System Chemical Volume Control Sys. Aux. Bldg. Plan Below El. 436'-0" North of R. B. Center Line Design... (6/27/2022)
- ML22194A135 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 7.6-7, Chemical Volume Control Sys-Aux Building Plan & Sections Below EL 436'-0" South Of R.B Center Line (1 page(s), 6/27/2022)
- ML22194A173 - Virgil C. Summer Nuclear Station, Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 8.3-2B, Electrical Duct Runs for Diesel Generator Circuits Main Plant Area - East End Design Engineering (1 page(s), 6/27/2022)
- ML22194A329 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 8.3-2C, Rev. 7, Electrical Duct Runs For Diesel Generator Circuits Outdoor Area - East End (1 page(s), 6/27/2022)
- ML22194A141 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 8.2-2D, Electrical Duct Runs For Diesel Generator Circuits To Service Water Intake Structure (1 page(s), 6/27/2022)
- ML22194A262 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 8.2-1, Rev. 3, Sie Transmission Map (1 page(s), 6/27/2022)
- ML22194A320 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 8.2-2, Rev. 18, Electrical One Line Diagram 230KV Substation Layout (1 page(s), 6/27/2022)
- ML22194A341 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 8.2-2A, Electrical General Arrangement 230 KV Substitution Arrangement (1 page(s), 6/27/2022)
- ML22194A256 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 8.2-2B, Electrical 230KV Substation Arrangement Plan - BUs Sections 2 & 3 (1 page(s), 6/27/2022)
- ML22194A205 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 8.2-2C, Electrical 230KV Substation Arrangement Plan - BUS Sections 1 & 3 (1 page(s), 6/27/2022)
- ML22194A239 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 8.2-2D, Electrical Overhead Line Arrangement 230KV and 115KV Outdoor Transformer Area (1 page(s), 6/27/2022)
- ML22194A235 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 8.2-3, Sheet 1, Electrical One Line and Relay Diagram Balance of Plant Power System (1 page(s), 6/27/2022)
- ML22194A315 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 8.2-4, Rev. 34, Electrical One Line And Relay Diagram Engineered Safety Features Power System (1 page(s), 6/27/2022)
- ML22194A208 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 8.3-0B, Outdoor Cable Bus Layout & Sections Safeguard Transformer Area (1 page(s), 6/27/2022)
- ML22194A305 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 8.3-0, Outdoor Cable Bus Layout & Sections Emergency Auxiliary Transformer Area (1 page(s), 6/27/2022)
- ML22194A146 - Virgil C. Summer Nuclear Station, Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 8.3-0A, Outdoor Cable Bus Layout & Sections Unit Auxiliary Transformer Area Husky Products Inc. (1 page(s), 6/27/2022)
- ML22194A206 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 8.3-0b, Outdoor Cable Bus Layout & Sections Safeguard Transformer Area (1 page(s), 6/27/2022)
- ML22194A252 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 8.3-C, Indoor Cable Bus Layout & Sections Plan View, Elevation 436'-0" (1 page(s), 6/27/2022)
- ML22194A124 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 8.3-0D, Indoor Cable Bus Layout & Sections Plan View, Elevation 436'-0", Col D-F.I & 8-11.1 (1 page(s), 6/27/2022)
- ML22194A264 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 8.3-E, Indoor Cable Bus Layout & Sections Plan View, Elevation 412'-0" (1 page(s), 6/27/2022)
- ML22194A200 - Virgil C. Summer Nuclear Station, Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 8.3-0F, Revision 4, Indoor Cable Bus Layout & Sections Plan View, Elevation 412'-0", Col. 8 to 11.1 & Col. A to C (6/27/2022)
- ML22194A276 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 8.3-0G, Indoor Cable Bus Layout & Sections Plan View, Elevation 412'-0", Col. 8 to 11.1 & Col. A to C (1 page(s), 6/27/2022)
- ML22194A213 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 8.3-0H, Electrical Diesel Generator Starting Control Logic Diagram (1 page(s), 6/27/2022)
- ML22194A318 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 8.3-0i, Electrical Diesel Generator Shutdown Control Logic Diagram (1 page(s), 6/27/2022)
- ML22194A136 - Virgil C. Summer Nuclear Station, Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 8.3-0J, Electrical Diesel Generatior Breaker Logic Diagram Design Engineering (1 page(s), 6/27/2022)
- ML22194A278 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 8.3-0k, Electrical 7.2 KV Bus 1DA - Normal Incoming Breaker Logic Diagram (1 page(s), 6/27/2022)
- ML22194A272 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 8.3-0l, Electrical 7.2 KV 1DA - Emergency Incoming Breaker Logic Diagram (1 page(s), 6/27/2022)
- ML22194A197 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 8.3-0o, Electrical 7.2 KV Bus 1DA-1DB Undervoltage Relaying Logic Diagram (1 page(s), 6/27/2022)
- ML22194A294 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 8.3-1, Sheet 1, Elec. One Line and Relay Diagram Engineered Safety Features Vital AC Sys. (1 page(s), 6/27/2022)
- ML22194A343 - Virgil C. Summer Nuclear Station, Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 8.3-2, Electrical One Line and Relay Diagram Engineered Safety Features Vital AC System Design Engineering. Sheet 2 (1 page(s), 6/27/2022)
- ML22194A165 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 8.3-2a, Revision 14, Sheet 1, Electrical Duct Runs For Diesel Generator Circuits Main Plant Area West End (1 page(s), 6/27/2022)
- ML22194A134 - Virgil C. Summer Nuclear Station, Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 8.3-2aa, Revision 21, Elec. One Line and Relay Diagram Vital DC System Design Engineering. Sheet 3 (1 page(s), 6/27/2022)
- ML22194A258 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 8.3-2ab, Electrical One Line And Relay Diagram Engineered Safety Features Vital DC System (1 page(s), 6/27/2022)
- ML22194A332 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 8.3-2b, Revision 11, Electrical Duct Runs for Diesel Generator Circuits Main Plant Area - East End (1 page(s), 6/27/2022)
- ML22194A126 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 8.3-2c, Electrical Duct Runs For Diesel Generator Circuits Outdoor Area - East End (1 page(s), 6/27/2022)
- ML22194A190 - Virgil C. Summer Nuclear Station, Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 8.3-2d, Electrical Duct Runs for Diesel Generator Circuits to Service Water Intake Structure Design Engineering (1 page(s), 6/27/2022)
- ML22194A308 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 8.3-2e, Miscellaneous Outdoor Structures Yard Duct Run - Turbine Building To Service Water Intake Structure (1 page(s), 6/27/2022)
- ML22194A338 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 8.3-2f, Miscellaneous Outdoor Structures Yard Duct Run Electrical Manhole EMH0002 Design Engineering (1 page(s), 6/27/2022)
- ML22194A119 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 8.3-2g, Electrical Duct Banks Control Complex, Intermediate Building & Turbine Building (1 page(s), 6/27/2022)
- ML22194A169 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 8.3-4, Electrical One Line and Relay Diagrams Balance of Plant-Vital AC-DC System (1 page(s), 6/27/2022)
- ML22194A246 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 8.3-4a, Electrical One Line and Relay Diagrams Balance of Plant-Vital AC-DC System (1 page(s), 6/27/2022)
- ML22194A159 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 8.3-4b, R4, Electrical One Line and Relay Diagrams Balance of Plant-Vital AC-DC System (1 page(s), 6/27/2022)
- ML22194A218 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 8.3-5, Electrical 230KV Substation D.C. Station Service Diagram (1 page(s), 6/27/2022)
- ML22194A199 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 8.3-5a, Electrical 230 KV Substation Unit 1 Relay House DC One Line Diagram and Panel Schedules (1 page(s), 6/27/2022)
- ML22194A110 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 8.3-6, 125 VDC Main Dist. PNL. (1 page(s), 6/27/2022)
- ML22194A191 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 8.3-7, 125V DC Main Dist. PNL. (1 page(s), 6/27/2022)
- ML22194A240 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 8.3-8, Electrical Reactor, Turbine And Generator Trip Diagram (1 page(s), 6/27/2022)
- ML22194A247 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 8.3-0c, Indoor Cable Bus Layout & Sections Plan View, Elevation 436'-0" (1 page(s), 6/27/2022)
- ML22194A211 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 8.G-2, Electrical Containment Penetration Conductor Overcurrent Protection Devices (1 page(s), 6/27/2022)
- ML22194A174 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 8.G-6, Electrical Containment Penetration Conductor Overcurrent Protection Devices (1 page(s), 6/27/2022)
- ML22194A284 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 8.G-8, Electrical Containment Penetration Conductor Overcurrent Protection Devices (1 page(s), 6/27/2022)
- ML22194A133 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 8.G-9, Electrical Containment Penetration Conductor Overcurrent Protection Devices (1 page(s), 6/27/2022)
- ML22194A172 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 8G-1, Rev. 8, Electrical Containment Penetration Conductor Overcurrent Protection Devices (1 page(s), 6/27/2022)
- ML22194A287 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 8G-10, Electrical Containment Penetration Conductor Overcurrent Protection Devices (1 page(s), 6/27/2022)
- ML22194A132 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 8G-2, Electrical Containment Penetration Conductor Overcurrent Protection Devices (1 page(s), 6/27/2022)
- ML22194A293 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 8G-2, Sheet 2, Electrical Containment Penetration Conductor Overcurrent Protection Devices (1 page(s), 6/27/2022)
- ML22194A138 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 8G-3, Electrical Containment Penetration Conductor Overcurrent Protection Devices (1 page(s), 6/27/2022)
- ML22194A257 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 8G-4, Elec. Containment Penetration Conductor Overcurrent Protection Devices (1 page(s), 6/27/2022)
- ML22194A267 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 8G-5, Electrical Containment Penetration Conductor Overcurrent Protection Devices (1 page(s), 6/27/2022)
- ML22194A167 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 8G-6, RN 07-006, Electrical Containment Penetration Conductor Overcurrent Protection Devices (1 page(s), 6/27/2022)
- ML22194A162 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 8G-7, Electrical Containment Penetration Conductor Overcurrent Protection Devices (1 page(s), 6/27/2022)
- ML22194A250 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 8G-8, Electrical Containment Penetration Conductor Overcurrent Protection Devices (1 page(s), 6/27/2022)
- ML22194A301 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 8G-9, Electrical Containment Penetration Conductor Overcurrent Protection Devices (1 page(s), 6/27/2022)
- ML22194A217 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.1-3, Piping System Flow Diagram Spent Fuel Cooling (1 page(s), 6/27/2022)
- ML22194A327 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.2-1, Drawing D-302-221, Sheet 1, Rev. 32, Service Water Cooling (1 page(s), 6/27/2022)
- ML22194A150 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.2-1, RN 12-014, Piping System Flow Diagram Service Water Cooling (1 page(s), 6/27/2022)
- ML22194A334 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.2-2, Sheet 1, Rev. 7, RN 10-012, Service Water Cooling A - Train Outside RB (1 page(s), 6/27/2022)
- ML22194A112 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.2-2, Sheet 3, RN 10-012, Piping System Flow Diagram Service Water Cooling B - Train Outside RB (1 page(s), 6/27/2022)
- ML22194A111 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.2-2, Sheet 1, Piping System Flow Diagram Service Water Cooling A - Train Outside RB (1 page(s), 6/27/2022)
- ML22194A292 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.2-2, Sheet 2, Service Water Cooling A - Train Cooling to RBCU Loop (1 page(s), 6/27/2022)
- ML22194A303 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.2-2, Sheet 3, Piping System Flow Diagram Service Water Cooling B - Train Outside RB (1 page(s), 6/27/2022)
- ML22194A227 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.2-2, Sheet 4, Service Water Cooling B - Train Cooling to RBCU Loop (1 page(s), 6/27/2022)
- ML22194A115 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.2-2, Sheet 1, Rev. 11, Service Water Cooling A - Train Outside RB (1 page(s), 6/27/2022)
- ML22194A144 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.2-2, Drawing D-302-222, Sheet 2, Piping System Flow Diagram Service Water Cooling A - Train Cooling to RBCU Loop (1 page(s), 6/27/2022)
- ML22194A283 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.2-2, Sheet 3, Drawing D-302-222, Rev. 5, Service Water Cooling B - Train Outside RB (1 page(s), 6/27/2022)
- ML22194A155 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.2-2, Sheet 1, Drawing D-302-222-0001, Rev. 10, Service Water Cooling A - Train Outside RB (1 page(s), 6/27/2022)
- ML22194A158 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.2-2, Sheet 4, Rev. 4, Drawing D-302-222, System Flow Diagram Service Water Cooling (1 page(s), 6/27/2022)
- ML22194A269 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.2-2, Service Water Cooling (1 page(s), 6/27/2022)
- ML22194A245 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.2-24, Piping System Flow Diagram Reactor Make-Up Water System (1 page(s), 6/27/2022)
- ML22194A336 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.2-24, RN 14-043, Drawing 302-791, Revision 27, Piping System Flow Diagram Reactor Make-Up Water System (1 page(s), 6/27/2022)
- ML22194A120 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Chapter 9, Figure 9.2-4, D-302-611_R40, 2018-08, Piping System Flow Diagram Component Cooling (1 page(s), 6/27/2022)
- ML22194A202 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.2-4, Rev. 39, RN 12-014, Component Cooling (1 page(s), 6/27/2022)
- ML22194A164 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.2-5, Piping System Flow Diagram Component Cooling System Inside Reactor Building (1 page(s), 6/27/2022)
- ML22194A154 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.2-5, Rev. 27, RN 10-021, Component Cooling System Inside Reactor Building (1 page(s), 6/27/2022)
- ML22194A157 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.2-5, Drawing D-302-612, Rev. 28, System Flow Diagram Component Cooling System Inside Reactor Building. (1 page(s), 6/27/2022)
- ML22194A219 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.2-6, Drawing D-302-613, Rev. 21, System Flow Diagram Component Cooling System Non. ESS. Equipment Cooling. (1 page(s), 6/27/2022)
- ML22194A203 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.2-7, Drawing D-302-614, Rev. 16, Component Cooling System to NSSS Pumps (1 page(s), 6/27/2022)
- ML22194A254 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.2-8, Drawing D-302-161, Rev. 28, Water Treatment System (1 page(s), 6/27/2022)
- ML22194A238 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.2-9, Rev. 23, Piping System Flow Diagram Demineralized Water (1 page(s), 6/27/2022)
- ML22194A281 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.2-9A, Drawing D-302-162, Rev. 15, System Flow Diagram Filtered Water (1 page(s), 6/27/2022)
- ML22194A212 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.2-9B, Drawing D-302-164, Rev. 20, System Flow Diagram Demineralized Water (1 page(s), 6/27/2022)
- ML22194A122 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.2-9B, Rev. 24, System Flow Diagram Demineralized Water (1 page(s), 6/27/2022)
- ML22194A121 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.2-9B, Drawing D-302-164, Rev. 20, System Flow Diagram Demineralized Water (6/27/2022)
- ML22194A277 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.2-9b, Rev. 19, Demineralized Water (1 page(s), 6/27/2022)
- ML22194A266 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.2-9B, Drawing D-302-164, Rev. 21, System Flow Diagram Demineralized Water (1 page(s), 6/27/2022)
- ML22194A282 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.2-9B, Drawing D-302-164, Rev. 22, System Flow Diagram Demineralized Water (1 page(s), 6/27/2022)
- ML22194A337 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.2-9c, Rev. 5, Piping System Flow Diagram Domestic Water System (1 page(s), 6/27/2022)
- ML22194A243 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.3-1, Piping System Flow Diagram, Station Service Air (1 page(s), 6/27/2022)
- ML22194A153 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.3-10, Rev. 9, Building Service Floor & Equipment Drains Station Drainage Flow Diagram Intermediate Building. (1 page(s), 6/27/2022)
- ML22194A331 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.3-11, Rev. 10, Building Service Pumping Station Drainage Flow Diagram Fuel Handling Building (1 page(s), 6/27/2022)
- ML22194A149 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.3-12, Rev. 28, Piping System Flow Diagram Reactor and Auxiliary Building Sump Bumps (1 page(s), 6/27/2022)
- ML22194A330 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.3-13, Rev. 21, Nuclear Drains to Waste Holdup Tank (1 page(s), 6/27/2022)
- ML22194A152 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.3-13A, Rev. 7, Nuclear Valve Leak-Off Drains To Recycle Holdup Tank (1 page(s), 6/27/2022)
- ML22194A445 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.3-14, Rev. 32, Piping System Flow Diagram Non-Nuclear Plant Drains (1 page(s), 6/27/2022)
- ML22194A394 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.3-15, Rev. 15, Plant Industrial and Sanitary Waste Gilbert Associates (1 page(s), 6/27/2022)
- ML22194A442 - Virgil C. Summer Nuclear Station, Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.3-16, Sheet 1A, System Flow Diagram Chemical and Volume Control. (1 page(s), 6/27/2022)
- ML22194A449 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.3-6, Rev. 14, Sheet 1B, Chemical And Volume Control (1 page(s), 6/27/2022)
- ML22194A395 - Virgil C. Summer Nuclear Station, Unit 1, Revision 21 to Updated Final Safety Analysis Report, Figure 9.3-16, Sheet 1C, Piping System Flow Diagram Chemical and Volume Control. (1 page(s), 6/27/2022)
- ML22194A383 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.3-16, Rev. 14, Sheet 2, Piping System Flow Diagram Chemical and Volume Control (1 page(s), 6/27/2022)
- ML22194A352 - Virgil C. Summer Nuclear Station, Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.3-16, Sheet 4, System Flow Diagram Chemical and Volume Control. (1 page(s), 6/27/2022)
- ML22194A356 - Virgil C. Summer Nuclear Station, Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.3-16, Sheet 3, Piping System Flow Diagram Chemical and Volume Control Design Engineering (1 page(s), 6/27/2022)
- ML22194A355 - Virgil C. Summer Nuclear Station, Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.3-16, Sheet 5, Piping System Flow Diagram Chemical and Volume Control Design Engineering (1 page(s), 6/27/2022)
- ML22194A429 - Virgil C. Summer Nuclear Station, Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.3-16, Sheet 1C, of Drawing E-302-673, Revision 20, Piping System Flow Diagram Chemical and Volume Control Design Engineering (1 page(s), 6/27/2022)
- ML22194A426 - Virgil C. Summer Nuclear Station, Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.3-16, Sheet 3 of Drawing E-302-675, Revision 37, Piping System Flow Diagram Chemical and Volume Control Design Engineering (1 page(s), 6/27/2022)
- ML22194A444 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.3-16, Sheet 4, Drawing E-302-676, Rev. 15, Chemical and Volume Control (1 page(s), 6/27/2022)
- ML22194A411 - Virgil C. Summer Nuclear Station, Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.3-16, Sheet 1A of Drawing E-302-671, Rev. 11, Piping System Flow Diagram Chemical and Volume Control Design Engineering (1 page(s), 6/27/2022)
- ML22194A400 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.4-1, Rev. 30, Control Room Normal And Emergency air Handling System (1 page(s), 6/27/2022)
- ML22194A322 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.3-2, Rev. 46, Piping System Flow Diagram Instrument Air (1 page(s), 6/27/2022)
- ML22194A422 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.4-2, Rev. 22, Building Service System Flow Diagram Relay and Computer Room Cooling System (1 page(s), 6/27/2022)
- ML22194A261 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.3-3, Rev. 21, Reactor Building Instrument Air Services (1 page(s), 6/27/2022)
- ML22194A314 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.3-4, Rev. 40, Nuclear Sampling (1 page(s), 6/27/2022)
- ML22194A427 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.4-4, Rev. 18, Control Building Control Access Exhaust (1 page(s), 6/27/2022)
- ML22194A362 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.4-5, Rev. 16, Building Service System Flow Diagram Computer Rooms & SAS Room Cooling Unit (1 page(s), 6/27/2022)
- ML22194A127 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.3-6, Rev. 6, Building Service Floor and Equipment Drains Station Drainage Flow Diagram - Auxiliary Building Elev. 485'-0" to Elev. 426'-6" (1 page(s), 6/27/2022)
- ML22194A376 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.4-6, Rev. 19, Building Service - System Flow Diagram Aux. Building Main Supply Sys. Flow Diagram (1 page(s), 6/27/2022)
- ML22194A374 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.4-7, Rev. 21, Building Service System Flow Diagram Auxiliary Building HEPA EXH System Flow Diagram (1 page(s), 6/27/2022)
- ML22194A345 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.3-8, Rev. 14, Building Service Floor & Equipment Drains Station Drainage Flow Diagram Turbine Building (1 page(s), 6/27/2022)
- ML22194A402 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.4-8, Rev. 31, Building Service System Flow Diagram Auxiliary Building Charcoal Exhaust System Flow Diagram (1 page(s), 6/27/2022)
- ML22194A403 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.4-9, Rev. 23, Building Service System Flow Diagram Auxiliary Building Main Exhaust System (1 page(s), 6/27/2022)
- ML22194A398 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.4-11, Rev. 27, Building Service System Flow Diagram Fuel Handling Building Charcoal Exhaust System & Air Supply Distribution (1 page(s), 6/27/2022)
- ML22194A405 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.4-12, Rev. 8, Building Service System Flow Diagram Turbine Building Ventilation System (1 page(s), 6/27/2022)
- ML22194A410 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.4-15, Rev. 12, Building Service System Flow Diagram Intermediate Building ESF SWGR Rooms and Speed Switch Rooms Cooling Systems (1 page(s), 6/27/2022)
- ML22194A388 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.4-17, Rev. 17, Intermediate Building General Ventilation and Pump Area Cooling Systems (1 page(s), 6/27/2022)
- ML22194A385 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Chapter 9, Figure 9.4-19, Rev. 17, Building Service System Flow Diagram Service Water Intake Screen and Pimp House Building Ventilation System (1 page(s), 6/27/2022)
- ML22194A381 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.3-20, Rev. 22, Piping System Flow Diagram Normal and Post-Accident Sampling (1 page(s), 6/27/2022)
- ML22194A234 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.3-3A, Rev. 13, System Flow Diagram Instrument Air Backup (1 page(s), 6/27/2022)
- ML22194A244 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.3-5, Rev. 8, Floor & Equipment Drains Station Drainage Flow Diagram Reactor Building (1 page(s), 6/27/2022)
- ML22194A225 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Chapter 9, Figure 9.3-7, Rev. 13, Building Service Floor and Equipment Drains Station Drainage Flow Diagram Auxiliary Building El. 412'-0" to El. 374'-0" (6/27/2022)
- ML22194A249 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.3-9, Rev. 10, Floor & Equipment Station Drainage Flow Diagram Control Building (1 page(s), 6/27/2022)
- ML22194A368 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.4-10, Rev. 21, Building Service System Flow Diagram Auxiliary Building Pump Room Cooling System (1 page(s), 6/27/2022)
- ML22194A360 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.4-12, Rev. 8, Turbine Building Ventilation System (1 page(s), 6/27/2022)
- ML22194A367 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.4-14, Rev. 12, CRDM Switch Gear Room Cooling System And Water Chiller Area Ventilation System (1 page(s), 6/27/2022)
- ML22194A419 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.4-16, Rev. 15, Battery RM. & Charging RM. BOP Charger Area Ventilation System (1 page(s), 6/27/2022)
- ML22194A435 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.4-18, Rev. 20, System Flow Diagram Boron Recycle (1 page(s), 6/27/2022)
- ML22194A373 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.4-18, Rev. 11, Building Services System Flow Diagram Diesel General Areas Vent System (1 page(s), 6/27/2022)
- ML22194A432 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.4-20, Rev. 19, Service Building First Floor And Second Floor (1 page(s), 6/27/2022)
- ML22194A391 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.4-21, Rev. 11, Service Building Second Floor (1 page(s), 6/27/2022)
- ML22194A382 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.4-22, Drawing D-302-841, Rev. 36, Chilled Water Pump & Chiller Area (1 page(s), 6/27/2022)
- ML22194A440 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.4-22, Rev. 31, Chilled Water Pump & Chiller Area (1 page(s), 6/27/2022)
- ML22194A375 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.4-23, Rev. 19, Piping System Flow Diagram Chilled Water - To Cooling Coils "A" (1 page(s), 6/27/2022)
- ML22194A454 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.4-24, Rev. 18, Piping System Flow Diagram Chilled Water - To Cooling Coils "B" (1 page(s), 6/27/2022)
- ML22194A437 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.4-25, Sheet 1, Drawing D-302-851, Piping System Flow Diagram Industrial Cooling Water (1 page(s), 6/27/2022)
- ML22194A377 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.4-25, Sheet 2, Rev. 4, Industrial Cooling Water (1 page(s), 6/27/2022)
- ML22194A351 - Virgil C. Summer Nuclear Station, Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.4-25, Rev. 35, Piping System Flow Diagram Industrial Cooling Water Design Engineering (1 page(s), 6/27/2022)
- ML22194A396 - Virgil C. Summer Nuclear Station, Unit 1, Revision 22 to Final Safety Analysis Report, Figure 9.4-26, of Drawing E-922-541, Revision 6, Building Service Substation Relay House Floor El. 436'-0" (1 page(s), 6/27/2022)
- ML22194A371 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.4-26c, Rev. 7, Building Service System Flow Diagram Water Treating Building Heating and Cooling System (1 page(s), 6/27/2022)
- ML22194A353 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.4-26D, Rev. 0, Building Service System Flow Diagram Unit 1 Relay House (1 page(s), 6/27/2022)
- ML22194A369 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.4-29, Rev. 12, Building Service System Flow Diagram R.B. Charcoal Cleanup, Secondary Compt. Cooling & Reactor Compt. Cooling (1 page(s), 6/27/2022)
- ML22194A447 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Chapter 9, Figure 9.4-3, Rev 21, NRC17 (1 page(s), 6/27/2022)
- ML22194A446 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.4-31, Rev. 15, Building Service System Flow Diagram R.B.C.R.D.M. SHROUD Vent System (1 page(s), 6/27/2022)
- ML22194A412 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.4-32, Rev. 24, System Flow Diagram CRDM Cooling Water (1 page(s), 6/27/2022)
- ML22194A448 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.4-32, Rev. 22, System Flow Diagram CRDM Cooling Water (1 page(s), 6/27/2022)
- ML22194A409 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.4-33, Rev. 6, Building Service System Flow Diagram Technical Support Center and Main Control Board Ventilation System (1 page(s), 6/27/2022)
- ML22194A399 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.4-35, Rev. 1, Sheet 2, Building Services Flow System Diagram EB HVAC DG1 Room (1 page(s), 6/27/2022)
- ML22194A386 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.4-35, Sheet 1, Rev. 0, System Flow Diagram EB HVAC - Electrical And Battery Room (1 page(s), 6/27/2022)
- ML22194A414 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.4-36, Rev. 1, System Flow Diagram AEB DG2 Room HVAC (1 page(s), 6/27/2022)
- ML22194A424 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.5-1, Sheet 2, Redacted (1 page(s), 6/27/2022)
- ML22194A363 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.5-1, Sheet 3, Rev. 11, Redacted (1 page(s), 6/27/2022)
- ML22194A420 - Virgil C. Summer Nuclear Station, Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.5-1, Sheet 1, Drawing D-302-231, Revision 40, Redacted (1 page(s), 6/27/2022)
- ML22194A392 - Virgil C. Summer Nuclear Station, Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.5-1, Sheet 5, Drawing 2018-04_NRC 18, Revision 9, Redacted (1 page(s), 6/27/2022)
- ML22194A443 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.5-11, Rev. 16, Redacted (1 page(s), 6/27/2022)
- ML22194A433 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.5-1A, Redacted (1 page(s), 6/27/2022)
- ML22194A450 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.5-1B, Redacted (1 page(s), 6/27/2022)
- ML22194A413 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.5-1CB, Redacted (1 page(s), 6/27/2022)
- ML22194A408 - Virgil C. Summer Nuclear Station, Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.5-1D, Redacted (1 page(s), 6/27/2022)
- ML22194A358 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.5-1E, Redacted (1 page(s), 6/27/2022)
- ML22194A348 - Virgil C. Summer Nuclear Station, Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.5-1f, Revision 55_2015-04_NRC15_Redacted (1 page(s), 6/27/2022)
- ML22194A364 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.5-2, Redacted (1 page(s), 6/27/2022)
- ML22194A404 - Virgil C. Summer Nuclear Station, Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 9.5-7, Redacted (1 page(s), 6/27/2022)
- ML22194A147 - Virgil C. Summer Nuclear Station, Unit 1, Revision 22 to Final Safety Analysis Report, Figures 9.5-1, Sheet 1, Drawing D-302-231, Redacted (1 page(s), 6/27/2022)
- ML22194A168 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 2.5-109, Service Water Pond Embankments Cal & Jetty Plan - West Embankment (1 page(s), 6/27/2022)
- ML22194A290 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 2.5-108, Service Water Pond Embankments Canal & Jetty Plan - East Dam (1 page(s), 6/27/2022)
- ML22194A156 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 3.7-51, I & C Detail STM Gen XSG-2C-RC Upper Lateral Support Earthquake Instrument YM-1785 (1 page(s), 6/27/2022)
- ML22194A131 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 3.7-52, I & C Detail Intermediate Building Earthquake Instr YM-1786 (1 page(s), 6/27/2022)
- ML22194A193 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 3.7-53, Auxiliary Building Earthquake INSTR YM-1787 (1 page(s), 6/27/2022)
- ML22194A273 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 6.2-51, Building Service HVAC Reactor Building Cooling System (1 page(s), 6/27/2022)
- ML22194A125 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 6.2-58, Piping System Flow Diagram Post Accident Hydrogen Removal And Alternate Purge System (1 page(s), 6/27/2022)
- ML22194A253 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 6.2-59, System Flow Diagram Reactor Building Leak Rate Testing System (1 page(s), 6/27/2022)
- ML22194A109 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 6.2-60, Instrument Location Layout Integrated Leak Rate Test Sensor Locations (1 page(s), 6/27/2022)
- ML22194A295 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 6.2-65, Reactor Building Pipe Sleeves & Liner Plate Sectional Plans (1 page(s), 6/27/2022)
- ML22194A183 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 6.2-66, Reactor Building Pipe Sleeves Sections and Details (1 page(s), 6/27/2022)
- ML22194A130 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 6.2-67, Reactor Building Pipe Sleeves Sections And Details (1 page(s), 6/27/2022)
- ML22194A142 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 6.2-69, Piping Systems Reactor Coolant Main Loop Plan (1 page(s), 6/27/2022)
- ML22194A430 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 10.2-2, Rev. 6, Control Diagram Turbine Stop Valve. (1 page(s), 6/27/2022)
- ML22194A397 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 10.2-3A, Control Diagram Turbine Stop Valve. (1 page(s), 6/27/2022)
- ML22194A423 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 10.3-1, Rev. 42, System Flow Diagram Main Steam (Nuclear) (1 page(s), 6/27/2022)
- ML22194A378 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 10.3-2, Rev. 36, System Flow Diagram Main Steam (Non-Nuclear) (1 page(s), 6/27/2022)
- ML22194A434 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 10.3-3, Rev. 12, System Flow Diagram Main Reheat Steam (Non-Nuclear) (1 page(s), 6/27/2022)
- ML22194A428 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 10.4-3, Main System System Steam Dump/Turbine Bypass (MS) (1 page(s), 6/27/2022)
- ML22194A354 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 10.2-4, Rev. 6, Control Diagram Turbine Trip (1 page(s), 6/27/2022)
- ML22194A389 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 10.3-4, Rev. 17, System Flow Diagram Main Steam Dump System. (1 page(s), 6/27/2022)
- ML22194A406 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 10.2-5, System Flow Diagram Generator Gas & Vents (1 page(s), 6/27/2022)
- ML22194A431 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 10.4-5, System Flow Diagram Circulating Water Cooling (1 page(s), 6/27/2022)
- ML22194A372 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 10.4-6, System Flow Diagram Circulating Water Cooling (1 page(s), 6/27/2022)
- ML22194A439 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 10.4-10, System Flow Diagram Feedwater (Non-Nuclear) (1 page(s), 6/27/2022)
- ML22194A357 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 10.4-11, System Flow Diagram Feedwater (Non-Nuclear) (1 page(s), 6/27/2022)
- ML22194A436 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 10.4-12, System Flow Diagram Feedwater (Nuclear) (1 page(s), 6/27/2022)
- ML22194A359 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 10.4-13, System Flow Diagram Steam Generator Blowdown (1 page(s), 6/27/2022)
- ML22194A441 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 10.4-14, Nuclear Blowdown Processing System Holdup Tank and Demineralizer (1 page(s), 6/27/2022)
- ML22194A350 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 10.4-15, Rev. 16, System Flow Diagram Nuclear Blowdown Processing System Spent Resin Storage Tank (1 page(s), 6/27/2022)
- ML22194A438 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 10.4-17, Piping System Flow Diagram, Liquid Effluents From Nuclear Plant to Fairfield Penstock (1 page(s), 6/27/2022)
- ML22194A390 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 10.4-4, Revision 3, Sheet 1, Design Engineering (1 page(s), 6/27/2022)
- ML22194A379 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 10.4-4, I & C Loop Diagram Main Steam System Steam Dump/Turbine Bypass (MB) (1 page(s), 6/27/2022)
- ML22194A417 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 10.4-7A, System Flow Diagram Condensate Polishing (1 page(s), 6/27/2022)
- ML22194A380 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 11.3-4, Revision 19, Sheet 1 of 3, Piping System Flow Diagram Waste Processing (1 page(s), 6/27/2022)
- ML22194A425 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 11.3-4, Sheet 2, Piping System Flow Waste Processing (1 page(s), 6/27/2022)
- ML22194A418 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 11.3-4, Sheet 3, Piping System Flow Diagram Waste Processing (1 page(s), 6/27/2022)
- ML22194A451 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 12.1-1, Redacted (1 page(s), 6/27/2022)
- ML22194A416 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 12.1-10, Redacted (1 page(s), 6/27/2022)
- ML22194A453 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 12.1-11, Redacted (1 page(s), 6/27/2022)
- ML22194A421 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 12.1-11a, Redacted (1 page(s), 6/27/2022)
- ML22194A393 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 12.1-12, Redacted (1 page(s), 6/27/2022)
- ML22194A361 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 12.1-13, Redacted (1 page(s), 6/27/2022)
- ML22194A230 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 12.1-14, Redacted (1 page(s), 6/27/2022)
- ML22194A123 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 12.1-15, Redacted (1 page(s), 6/27/2022)
- ML22194A229 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 12.1-16, Redacted (1 page(s), 6/27/2022)
- ML22194A279 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 12.1-17, Redacted (1 page(s), 6/27/2022)
- ML22194A344 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 12.1-18, Redacted (1 page(s), 6/27/2022)
- ML22194A194 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 12.1-19, Redacted (1 page(s), 6/27/2022)
- ML22194A228 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 12.1-19a, Redacted (1 page(s), 6/27/2022)
- ML22194A384 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 12.1-2, Redacted (1 page(s), 6/27/2022)
- ML22194A271 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 12.1-22, Reactor Building - Miscellaneous Steel Fuel Transfer Canal Shielding (1 page(s), 6/27/2022)
- ML22194A370 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 12.1-2a, Redacted (1 page(s), 6/27/2022)
- ML22194A401 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 12.1-3, Redacted (1 page(s), 6/27/2022)
- ML22194A366 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 12.1-4, Redacted (1 page(s), 6/27/2022)
- ML22194A349 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 12.1-5, Sheet 1, Redacted (1 page(s), 6/27/2022)
- ML22194A407 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 12.1-5, Redacted (1 page(s), 6/27/2022)
- ML22194A365 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 12.1-6, Redacted (1 page(s), 6/27/2022)
- ML22194A452 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 12.1-7, Redacted (1 page(s), 6/27/2022)
- ML22194A387 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 12.1-8, Plant Layout Final Reactor & Fuel Handling Buildings Section A-A Looking West (1 page(s), 6/27/2022)
- ML22194A415 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 12.1-9, Redacted (1 page(s), 6/27/2022)
- ML22194A128 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Figure 12A.4-1 thru 12A.4-8, Redacted (1 page(s), 6/27/2022)
- ML22194A333 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Drawing E-726-232, Rev. 2, Intake Structure Retaining Walls Bottom Slab Reinforcement Plans Retaining Walls 1 and 2 (1) (1 page(s), 6/27/2022)
- ML22194A180 - Virgil C. Summer Nuclear Station Unit 1, Revision 22 to Updated Final Safety Analysis Report, Drawing E-726-232, Rev. 2, Condenser Cir. Water Intake Structure Retaining Walls Bottom Slab Reinforcement Plans Retaining Walls 1 and 2 (1 page(s), 6/27/2022)