Inspection
Report Date |
Description |
12/18/2020 |
Framatome Fuel Facility, Richland, WA, limited scope inspection to assess compliance with selected portions of their quality assurance (QA) and Part 21 programs, specifically as they pertain to activities conducted at their facility related to the design, fabrication, corrective actions, and testing of fuel assemblies for NRC’s regulated facilities.
|
12/15/2020 |
Lake Engineering, Greenville, RI, limited scope inspection to assess compliance with selected portions of their quality assurance (QA) and Part 21 programs, specifically as they pertain to the design, fabrication, testing, and commercial-grade dedication of safety-related snubber components and services for the operating nuclear power plants.
|
12/01/2020 |
SAFER PEICO, Phoenix, AZ, limited scope inspection to assess compliance with selected portions of their quality assurance (QA) and Part 21 programs, specifically, as they pertain to implementation of the storing, handling, and supplying of portable equipment to be used by licensees to comply with 10 CFR 50.155, "Mitigation of beyond-design-basis events" and NRC Order EA-12-049 (ADAMS Accession No. ML12056A045).
|
11/13/2020 |
Ametek Solidstate Controls, Columbus, OH, limited scope inspection to assess compliance with selected portions of their quality assurance (QA) and Part 21 programs, specifically as they pertain to Ametek's design, fabrication, testing, and commercial-grade dedication of safety related components to operating nuclear power plants.
|
10/14/2020 |
C&D Technologies, Blue Bell, PA, limited scope inspection to assess compliance with selected portions of their quality assurance (QA) and Part 21 programs, specifically as they pertain to activities conducted at your facility of services supplied to NRC's regulated facilities.
|
10/14/2020 |
EnerSys, Reading, PA, limited scope inspection to assess compliance with selected portions of their quality assurance (QA) and Part 21 programs, specifically, the quality assurance program and Part 21 implementation, will be reviewed as they pertain to their design, fabrication, testing, and commercial-grade dedication of safety-related components to operating nuclear power plants.
|
08/04/2020 |
Valcor Engineering Corporation, Springfield, NJ, limited scope inspection to assess compliance with selected portions of their quality assurance (QA) and Part 21 programs, specifically as they pertain to activities conducted at your facility related to the design, fabrication, assembly, and testing of valves and replacement valve parts for NRC’s regulated facilities.
|
04/22/2020 |
Framatome, Lynchburg, VA, follow-up limited scope inspection to assess compliance with selected portions of their quality assurance (QA) and Part 21 programs, specifically, as they pertain to Framatome’s activities associated to the unresolved item (URI) 99901300/2019-201-01 documented in inspection report No. 99901300/2019-201 dated September 20, 2019 (ADAMS As session No. ML19261A188).
|
04/03/2020 |
EnerSys, Hays, KS, limited scope inspection to assess compliance with selected portions of their quality assurance (QA) and Part 21 programs, specifically, as they pertain to the fabrication, assembly, and testing of safety-related batteries and components being supplied to the U.S. operating nuclear power plants.
- No Announcement Letter
- No Response Required
|
04/03/2020 |
ASCO, L.P., Aiken, SC, limited scope inspection to assess compliance with selected portions of their quality assurance (QA) and Part 21 programs, specifically, as they pertain to the design, fabrication, testing, and commercial-grade dedication of safety-related solenoid valves to operating nuclear power plants.
|
04/02/2020 |
Westinghouse, New Stanton, PA, limited scope inspection to assess compliance with selected portions of their quality assurance (QA) and Part 21 programs, specifically as they pertain to WEC’s testing of safety-related components that comprise the uninterruptable power supply system for the AP1000 reactors currently under construction at Vogtle Units 3 and 4.
|
03/25/2020 |
Sargent & Lundy, Chicago, IL, limited scope inspection to assess compliance with selected portions of their quality assurance (QA) and Part 21 programs, specifically, as they pertain to activities conducted at their facility of services supplied to NRC's regulated facilities.
|
02/26/2020 |
Westinghouse Electric Company, Hopkins, SC, limited scope inspection to assess compliance with selected portions of their quality assurance (QA) and Part 21 programs, specifically as they pertain to activities conducted at their facility related to the design, fabrication, assembly, and testing of fuel assemblies for NRC’s regulated facilities.
|
01/27/2020 |
Rosemount Nuclear Instruments, Inc., Chanhassen, MN, limited scope inspection to assess compliance with selected portions of their quality assurance (QA) and Part 21 programs.
|
01/22/2020 |
Bechtel Power Corporation, Reston, VA, limited scope inspection to assess compliance with selected portions of their quality assurance (QA) and Part 21 programs, specifically as they pertain to Bechtel’s design, qualification, and commercial-grade dedication activities related to basic components supplied to U.S. NRC regulated facilities.
|
01/08/2020 |
Fisher Controls International, LLC, Marshalltown, IA, limited scope inspection to assess compliance with selected portions of their quality assurance (QA) and Part 21 programs, specifically as they pertain to activities conducted at their facility related to the quality activities associated with the design, fabrication, assembly, and testing of valves, actuators, actuator accessories, replacement parts and/or appurtenances being supplied to US Nuclear Power Plants.
|