2009 - Bell Bend Nuclear Power Plant Application

On this page:

This page includes links to files in non-HTML format. See Plugins, Viewers, and Other Tools for more information.

Applicant Documents

The following table provides access to the COL Application and other documents that PPL Bell Bend, LLC submitted in 2009 for Bell Bend Nuclear Power Plant.

Date Description
12/17/09 Alternative site evaluation revision 1
12/16/09 Preliminary plot plan changes for Bell Bend Nuclear Power Plant
12/08/09 Schedule update for revisions to the combined license application for Bell Bend Nuclear Power Plant
11/25/09 Letter from Mr. Rocco R. Sgarro, PPL Bell Bend LLC, to NRC providing revised Environmental Report Section 9.3 and 10.4 for revised alternative site analysis
09/09/09 Letter from Mr. Rocco R. Sgarro, PPL Bell Bend LLC, to NRC transmitting Bell Bend Nuclear Power Plant alternative site evaluation
07/09/09 Submittal of BBNPP Turbine Information
06/29/09 Letter from Mr. Rocco R. Sgarro, PPL Bell Bend LLC, to NRC providing environmental site audit response items
06/29/09 BBNPP Submittal of Additional Information Related to Site Specific Ground Motion Response Spectra
06/24/09 Letter from Mr. Rocco R. Sgarro, PPL Bell Bend LLC, to NRC providing environmental site audit response items
06/17/09 BBNPP Submittal of Additional Information BNP-2009-123
05/29/09 Bell Bend Supplemental Information - Impingement and Entrainment Study, Part 11K
05/28/09 Bell Bend Nuclear Power Plant April 2009 NRC Environmental Audit Response Status
04/06/09 Bell Bend Nuclear Power Plant Identification of Adams Accession Number
02/27/09

PPL Bell Bend, LLC's transmittal letter for Bell Bend Nuclear Power Plant COLA - Revision 1 - incorporates supplements dated 11/18, 11/24, 12/1 and 12/8/2008

See Application

02/12/09 Bell Bend Nuclear Power Plant Supplemental Information for the Bell Bend COLA - FSAR Section 2.5.2

NRC Documents

The following table provides access to documents and correspondence that the NRC has issued in 2009 in connection with its review of the COL application that PPL Bell Bend, LLC submitted for Bell Bend Nuclear Power Plant.

Date Description
10/29/09 Summary of the Environmental Site Audit Related to the Review of the Combined License Application
07/22/09 Scoping Summary Report Related to the Environmental Scoping Process for the Bell Bend Nuclear Power Plant Combined License Application
05/27/09 Bell Bend Nuclear Power Plant Combined License Application Review Schedule
03/19/09 Notice of Hearing and Opportunity To Petition for Leave To Intervene