Issued Combined Licenses for Levy Nuclear Plant, Units 1 and 2

On July 30, 2008, Duke Energy Florida, LLC (DEF) submitted its application for combined licenses (COLs) for two Westinghouse Advanced Passive 1000 (AP1000) Pressurized Water Reactors (PWRs) designated as Levy Nuclear Plant, Units 1 and 2.

For detail (including the latest submittal of the application, the related review schedule, and the associated staff documentation), see the following topics on this page:

Reference Documents

In accordance with Title 10, Part 52, of the Code of Federal Regulations (10 CFR Part 52), "Licenses, Certifications, and Approvals for Nuclear Power Plants," a COL application may reference a standard design certification, an early site permit, both, or neither. Many COL applications have referenced an application for design certification, in accordance with 10 CFR 52.55(c). On that basis, the application referenced Westinghouse's application to amend the AP1000 standard design certification and cited the following amended design control document (DCD) in its COL original application for Levy Nuclear Plant, Units 1 & 2:

In Revision 1 to the Levy Nuclear Plant, Units 1 & 2 COL application dated October 2, 2009, Progress Energy Florida updated the application to reflect that its application now incorporates by reference AP1000 DCD Revision 17.

In Revision 3 to the Levy Nuclear Plant, Units 1 & 2 COL application dated October 4, 2011, Progress Energy Florida updated the application to reflect that its application now incorporates by reference AP1000 DCD Revision 19. All subsequent revisions to the COL application also incorporate by reference AP1000 DCD Revision 19.

To top of page

Application Information

The following table provides access to the COL Application that Progress Energy Florida submitted for Levy Nuclear Plant, Units 1 & 2. Beginning in April 2014, the applicant changed to Duke Energy Florida, Inc. Beginning December 2015, the applicant changed to Duke Energy Florida, LLC.

Some combined license applications were submitted with hyperlinks to various reference documents. Currently, the hyperlinks in those applications are not active. These hyperlinks represent an advanced feature that could be activated when the agency upgrades to web-based ADAMS, at which point these applications and documents such as the Final Safety Analysis Report and associated Technical/Topical Reports would be linked together. In the interim, and for those applications that do not have the hyperlink feature, the reference documents may be viewed under the Reference Documents section of the combined license application page. In addition, DVDs of the various documents are available by contacting the Public Document Room staff.

Part Description Revision
1 Administrative and Financial Information Rev. 8
Rev. 7
Rev. 6
Rev. 5
Rev. 4
Rev. 3
Rev. 2
Rev. 1
Rev. 0
2 Final Safety Analysis Report (FSAR) Rev. 9
Rev. 8
Rev. 7
Rev. 6
Rev. 5
Rev. 4
Rev. 3
Rev. 2
Rev. 1
Rev. 0
3 Environmental Report Rev. 1
Rev. 0
4 Technical Specifications Rev. 7
Rev. 6
Rev. 5
Rev. 4
Rev. 3
Rev. 2
Rev. 1
Rev. 0
5 Emergency Plan Rev. 7
Rev. 6
Rev. 5
Rev. 4
Rev. 3
Rev. 2
Rev. 1
Rev. 0
6 Limited Work Authorization (LWA) Rev. 1
Rev. 0
7 Departures and Exemption Requests Rev. 6
Rev. 5
Rev. 4
Rev. 3
Rev. 2
Rev. 1
Rev. 0
8 Safeguards/Security Plans [This Part contains safeguards information which is withheld from public availability]  
9 [This Part contains other information which is withheld from public availability]  
10 License Conditions and Inspection, Tests, Analyses and Acceptance Criteria (ITAAC) Rev. 8
Rev. 7
Rev. 6
Rev. 5
Rev. 4
Rev. 3
Rev. 2
Rev. 1
Rev. 0
11 Information Incorporated By Reference Rev. 7*
Rev. 6
Rev. 5
Rev. 4
Rev. 2
Rev. 1
Rev. 0

To top of page

Review Schedule

Key Milestones Completion Date
Actual - A
Target - T
Application Tendered 07/30/08 - A
Acceptance Review
Acceptance Review Start
08/04/08 - A
Docketing Decision Letter Issued/Acceptance Review Complete
10/06/08 - A
Review Schedule Established/Schedule Letter Issued to Applicant
02/18/09 - A
Safety Review
Phase A - Requests for Additional Information (RAIs) and Supplemental RAIs
(Formerly Phase 1)
03/29/10 - A
Phase B - Advanced Final safety evaluation report (SER) without Open Items
(Formerly Phase 2)
09/15/11 - A
Phase C - ACRS Review of Advanced Final SER
(Formerly Phase 3)
01/24/12 - A
Phase D - Final SER
(Formerly Phase 4)
05/31/16 - A
Environmental Review
Phase 1 - Environmental impact statement (EIS) scoping summary report issued
05/28/09 - A
Phase 2 - Draft EIS issued to EPA
08/06/10 - A
Phase 3 - Responses to public comments on draft EIS completed*
04/27/12 - A
Phase 4 - Final EIS issued to EPA
04/27/12 - A
Hearing
Commission holds mandatory hearing
07/28/16 - A
License
Commission decision on issuance of COL
10/20/16 - A

* NRC staff responses to public comments on the Draft EIS are included in Appendix E of the Final EIS

To top of page

Safety Evaluations

This section lists the Safety Evaluations that the NRC has issued in connection with its review of the COL application for Levy Nuclear Plant, Units 1 and 2.

To top of page

Topical Reports

The NRC has issued no Topical Reports in connection with its review of the COL application for Levy Nuclear Plant, Units 1 and 2.

To top of page

Combined Licenses

This provides the COLs that the NRC issued on October 27, 2016 in connection with its review of the COL application for Levy Nuclear Plant, Units 1 and 2.

To top of page

To top of page

Contacts

Contacts for the Levy Nuclear Plant, Units 1 and 2 COL Application
Safety Project Manager Billy Gleaves
Environmental Project Manager Mallecia Sutton
Contact a Public Affairs Officer

To top of page