Information Notice No. 82-41: Failure of Safety/Relief Valves to Open at a BWR
SSINS NO.: 6835 IN 82-41 UNITED STATES NUCLEAR REGULATORY COMMISSION OFFICE OF INSPECTION AND ENFORCEMENT WASHINGTON, D. C. 20555 October 22, 1982 Information Notice No. 82-41: FAILURE OF SAFETY/RELIEF VALVES TO OPEN AT A BWR Addressees: All nuclear power reactor facilities holding an operating license (OL) or construction permit (CP). Purpose: This information notice is provided as a notification of a potentially significant problem pertaining to Target Rock two-stage safety/relief valves. It is expected that recipients will review the information for applicability to their facilities. No specific action or response is required at this time. Description of Circumstances: On July 3, 1982, Georgia Power Company's Hatch Unit 1 was operating at 100% power when a spurious high-pressure signal caused a reactor scram. The variation in pressure with time is shown in Figure 1. The main turbine had not tripped when a Group 1 isolation* occurred. High-pressure coolant injection (HPCI) and reactor core isolation cooling (RCIC) auto-started and injected and the recirculation pumps tripped. The main turbine was then manually tripped. When vessel water level recovered and reached the high water level trip set point, HPCI, RCIC, and the feedwater pump turbines tripped. Gradual vessel repressurization continued beyond the high-pressure scram setpoint on a 0.5 psi/sec ramp without relief valve actuation. About 1180 psig, three safety/relief valves (SRVs) automatically actuated, relieving vessel pressure rapidly. Upon the SRVs' closure, the main steam isolation valves were manually reopened and the reactor was cooled and depressurized to cold shutdown. During cooling and depressurizing, the remaining eight SRVs were manually actuated and functioned properly. The SRVs installed on Hatch 1 are the two-stage Target Rock model number 7567F (see Figure 2). All three SRVs that opened automatically were located on the same steam line and were the only valves on that line. Their setpoints were 1080, 1080, and 1090 psi. The remaining eight SRVs were set at 1080, *Closure of main steam isolation valves, main steam drain isolation valves, and recirculation loop sample isolation valves. 8208190239 . IN 82-41 October 22, 1982 Page 2 of 3 1090, or 1100 psi. All had been refurbished and steam set at Wyle Labs during the previous refueling outage and had most recently been actuated in August of 1981. Following the July 3, 1982 event, the top works or pilot section (see Figure 3) of all the SRVs were removed and sent to Wyle Labs, where they were tested in the as-received condition. Six passed their first test, four passed on retest, and the final valve passed on the second retest -- all without setpoint spring adjustment. The average first actuation pressure was 0.9% above nameplate with the highest pressure required being 4.1% above nameplate. No abnormal leakage characteristics were observed for any of the valves. No apparent mechanical failure was found in the top works at Wyle Labs or the valve bodies inspected at Hatch. Three additional licensees--TVA, Northeast Nuclear Energy Company, and Boston Edison--had reported that two-stage Target Rock valves, tested in the as-received condition at Wyle Labs, failed to actuate within 1% of the setpoint. (Reference LER 50-259/81-25, 50-296/81-74, 50-293/81-62, 50-260/82-27). (The excessive leakage and the damaged internals of the Pilgrim valves may present quite a different problem from that of Hatch, Browns Ferry, or Millstone.) The Hatch 1 event of July 3, 1982 was potentially the most significant in terms of both (1) the fraction of valves that failed to open at their setpoint, and (2) the pressure above setpoint required to open the valves. The General Electric Company (GE) and the Target Rock Company have joined Georgia Power in attempting to determine the cause of the failure of the valves to actuate. A GE analysis suggests that the most likely cause of the high actuation pressure is some combination of friction in the labyrinth seal area and/or sticking of the pilot disc in its seat. The slow repressurization ramp and the extended period during which the valves were not actuated are also considered possible contributors to the incident. To define the problem and to improve the probability of actuation of the SRVs, Georgia Power has instituted a program at Hatch whereby nine of the eleven Unit 1 valves will be exercised regularly. Two valves will not be exercised and will be utilized for possible future testing. Unit 2 valves will be subjected to a similar program. Also, Georgia Power has arranged with GE and with cooperating licensees for screening tests to be done on additional SRVs at Wyle Labs. Valves which are pressurized at the 0.5 psi ramp to 103% of nameplate rating without actuating are to be candidates for diagnostic testing to determine the magnitude of forces in the disc-to-seat interface and the labyrinth seal area. Further, examination of interior surfaces will be conducted to locate any physical damage. Two such candidates were found in the recent testing of three SRVs belonging to Northeast Nuclear Energy Company's Millstone Unit 1. . IN 82-41 October 22, 1982 Page 3 of 3 If you have any questions regarding this matter, please contact the Regional Administrator of the appropriate NRC Regional Office, or this office. Edward L. Jordan, Director Division of Engineering and Quality Assurance Office of Inspection and Enforcement Technical Contact: M. S. Wegner, IE 301-492-4511 Attachments: 1. Appendix A: Figures 1 through 3 2. List of Recently Issued IE Information Notices
Page Last Reviewed/Updated Tuesday, March 09, 2021
Page Last Reviewed/Updated Tuesday, March 09, 2021