Post-TMI Requirements (Generic Letter 82-10)



                               UNITED STATES 
                       NUCLEAR REGULATORY COMMISSION 
                          WASHINGTON, D. C. 20555  

                                May 5, 1982 

ALL LICENSEES OF OPERATING POWER REACTORS 

Gentlemen: 

SUBJECT:  POST-TMI REQUIREMENTS (Generic Letter 82-10) 

On October 30, 1980, the NRC staff sent to you NUREG-0737 which incorporated
into one document the TMI-related items that were approved by the Commission
for implementation at operating reactors. Items scheduled for implementation
on or before March 1, 1982 have been addressed by previous correspondence. 
This letter requests your commitments to implement on a timely basis the 
remainder of the NUREG-0737 items. 

The Enclosure identifies those items for which your schedule needs to be 
established or, if a schedule has previously been submitted, a 
reconfirmation of such dates. Two items, Equipment Qualification and RCS 
Vents, are currently required by Order or by the Regulations. For these 
items, licensees need not reply herein. All items from NUREG-0737 are 
listed, although as noted in the Table no reply is necessary at this time on 
selected items. 

Your attention is directed especially to two items, I.A.1.3.1 "Limit 
Overtime" and II.K.3.18 "ADS Actuation" where separate NRC actions have 
revised the scope and/or schedule for the implementation of these items. 
These are appropriately annotated in the Enclosed Table. 

Accordingly, pursuant to SS 50.54(f) of the NRC Regulations, licensees of 
operating power reactors are requested to furnish the following information 
within 30 days of the date of this letter: 

     (1)  For applicable items in the Enclosure that have been completed, 
          confirm their completion and furnish the date on which they were 
          completed. 

     (2)  For applicable items in the Enclosure that have not been 
          completed, propose a specific schedule for implementation which 
          you commit to meet. In those cases where a licensee's schedule is 
          beyond the schedules shown in NUREG-0737, provide: 

          (a)  justification for proposed schedule, 
          (b)  demonstration of need for proposed schedule, and 
          (c)  description of compensatory measures being taken in the 
               interim. 



8205060151 
.

                                    - 2 -

This request for information was approved by the Office of Management and 
Budget under clearance number, 3150-0065 which expires May 31, 1983. 
Comments on burden and duplication may be directed to the Office of 
Management and Budget, Reports Management Room 3208, New Executive Office 
Building, Washington, D.C. 20503. 

                              Sincerely, 


                              Darrell G. Eisenhut, Director 
                              Division of Licensing 
                              Office of Nuclear Reactor Regulation 

Enclosures: 
As Stated 
 