Power Reactor Status Report for May 13, 2011
UNEVALUATED INFORMATION PROVIDED BY THE FACILITY
On this page:
Region 1
| Unit |
Power |
Down |
Reason or Comment |
Change in report (*) |
Number of Scrams (#) |
| Beaver Valley 1 |
100 |
|
|
|
|
| Beaver Valley 2 |
100 |
|
|
|
|
| Calvert Cliffs 1 |
100 |
|
|
|
|
| Calvert Cliffs 2 |
100 |
|
|
|
|
| FitzPatrick |
100 |
|
|
* |
|
| Ginna |
0 |
05/12/2011 |
DEFUELED |
|
|
| Hope Creek 1 |
100 |
|
|
* |
|
| Indian Point 2 |
100 |
|
|
|
|
| Indian Point 3 |
100 |
|
|
|
|
| Limerick 1 |
100 |
|
|
|
|
| Limerick 2 |
100 |
|
|
|
|
| Millstone 2 |
100 |
|
|
|
|
| Millstone 3 |
100 |
|
|
|
|
| Nine Mile Point 1 |
0 |
05/02/2011 |
AUTOMATIC SCRAM-SEE EN #46808; LINE 4 (115 KV) OFFSITE POWER LINE OOS |
|
|
| Nine Mile Point 2 |
100 |
|
|
|
|
| Oyster Creek |
100 |
|
|
|
|
| Peach Bottom 2 |
100 |
|
|
|
|
| Peach Bottom 3 |
100 |
|
|
|
|
| Pilgrim 1 |
14 |
|
MAINTENANCE HOLD |
* |
|
| Salem 1 |
100 |
|
|
|
|
| Salem 2 |
97 |
|
|
* |
|
| Seabrook 1 |
0 |
03/31/2011 |
REFUELING OUTAGE |
|
|
| Susquehanna 1 |
100 |
|
HIGH SYSTEM VOLTAGE ACTION |
|
|
| Susquehanna 2 |
0 |
04/04/2011 |
REFUELING OUTAGE |
|
|
| Three Mile Island 1 |
100 |
|
HIGH SYSTEM VOLTAGE ACTION |
* |
|
| Vermont Yankee |
100 |
|
|
* |
|
Region 2
| Unit |
Power |
Down |
Reason or Comment |
Change in report (*) |
Number of Scrams (#) |
| Browns Ferry 1 |
0 |
04/27/2011 |
REACTOR SCRAM DUE TO LOSS OF OFFSITE POWER - SEE EN #46793
500 KV OFFSITE LINES OOS |
|
|
| Browns Ferry 2 |
0 |
04/27/2011 |
REACTOR SCRAM DUE TO LOSS OF OFFSITE POWER - SEE EN #46793
500 KV OFFSITE LINES OOS |
|
|
| Browns Ferry 3 |
0 |
04/27/2011 |
REACTOR SCRAM DUE TO LOSS OF OFFSITE POWER - SEE EN #46793
500 KV OFFSITE LINES OOS |
|
|
| Brunswick 1 |
100 |
|
|
|
|
| Brunswick 2 |
100 |
|
|
|
|
| Catawba 1 |
0 |
04/23/2011 |
DEFUELED |
|
|
| Catawba 2 |
100 |
|
|
|
|
| Crystal River 3 |
0 |
09/25/2009 |
MAINTENANCE OUTAGE - CONTAINMENT TENSIONING ON HOLD |
|
|
| Farley 1 |
100 |
|
|
|
|
| Farley 2 |
100 |
|
|
|
|
| Harris 1 |
100 |
|
|
|
|
| Hatch 1 |
100 |
|
|
|
|
| Hatch 2 |
55 |
|
HOLDING POWER FOR 'B' FEEDPUMP REPAIR |
|
|
| McGuire 1 |
100 |
|
|
|
|
| McGuire 2 |
100 |
|
|
|
|
| North Anna 1 |
100 |
|
|
|
|
| North Anna 2 |
100 |
|
|
|
|
| Oconee 1 |
0 |
04/01/2011 |
DEFUELED |
|
|
| Oconee 2 |
100 |
|
|
|
|
| Oconee 3 |
100 |
|
|
|
|
| Robinson 2 |
100 |
|
|
|
|
| Saint Lucie 1 |
90 |
|
HOLDING POWER FOR ONE CIRC WATER PUMP OOS |
* |
|
| Saint Lucie 2 |
100 |
|
|
* |
|
| Sequoyah 1 |
100 |
|
GRID RISK YELLOW |
|
|
| Sequoyah 2 |
82 |
|
COASTDOWN TO REFUELING OUTAGE - GRID RISK YELLOW |
|
|
| Summer |
0 |
04/15/2011 |
CORE RELOAD COMPLETE |
* |
|
| Surry 1 |
100 |
|
|
|
|
| Surry 2 |
0 |
04/16/2011 |
DEFUELED |
|
|
| Turkey Point 3 |
100 |
|
|
|
|
| Turkey Point 4 |
0 |
05/05/2011 |
REPLACING RCP SEAL |
|
|
| Vogtle 1 |
100 |
|
|
|
|
| Vogtle 2 |
100 |
|
|
|
|
| Watts Bar 1 |
0 |
04/03/2011 |
REFUELING OUTAGE; TRANSMISSION SYSTEM ALERT ONE DUE TO LARGE AREA SYSTEM DAMAGE AS A RESULT OF TORNADOES |
* |
|
Region 3
| Unit |
Power |
Down |
Reason or Comment |
Change in report (*) |
Number of Scrams (#) |
| Braidwood 1 |
100 |
|
|
|
|
| Braidwood 2 |
37 |
|
HOLDING FOR FEEDWATER SYSTEM ISSUES |
* |
|
| Byron 1 |
100 |
|
|
|
|
| Byron 2 |
100 |
|
|
|
|
| Clinton |
97 |
|
100% ELECTRICAL CAPABILITY |
|
|
| D.C. Cook 1 |
100 |
|
|
|
|
| D.C. Cook 2 |
100 |
|
|
|
|
| Davis-Besse |
100 |
|
|
|
|
| Dresden 2 |
97 |
|
DUE TO CONDENSER VACCUM TEMPERATURES |
* |
|
| Dresden 3 |
98 |
|
DUE TO CONDENSER VACCUM TEMPERATURES |
* |
|
| Duane Arnold |
100 |
|
|
|
|
| Fermi 2 |
100 |
|
|
|
|
| Kewaunee |
100 |
|
|
|
|
| La Salle 1 |
100 |
|
|
|
|
| La Salle 2 |
100 |
|
|
|
|
| Monticello |
0 |
03/04/2011 |
EXITING REFUELING OUTAGE |
|
|
| Palisades |
100 |
|
|
|
|
| Perry 1 |
0 |
04/17/2011 |
REFUELING OUTAGE |
|
|
| Point Beach 1 |
100 |
|
|
|
|
| Point Beach 2 |
0 |
02/28/2011 |
REFUELING OUTAGE |
|
|
| Prairie Island 1 |
0 |
04/29/2011 |
REFUELING OUTAGE |
|
|
| Prairie Island 2 |
100 |
|
|
|
|
| Quad Cities 1 |
0 |
05/08/2011 |
REFUELING OUTAGE |
|
|
| Quad Cities 2 |
100 |
|
|
|
|
Region 4
| Unit |
Power |
Down |
Reason or Comment |
Change in report (*) |
Number of Scrams (#) |
| Arkansas Nuclear 1 |
46 |
|
HOLD DUE TO STORMS/DISPATCH REQUEST |
|
|
| Arkansas Nuclear 2 |
100 |
|
|
* |
|
| Callaway |
100 |
|
|
|
|
| Columbia Generating Station |
0 |
04/02/2011 |
REFUELING OUTAGE |
|
|
| Comanche Peak 1 |
100 |
|
|
|
|
| Comanche Peak 2 |
100 |
|
|
|
|
| Cooper |
78 |
|
INCREASING POWER |
* |
|
| Diablo Canyon 1 |
100 |
|
|
|
|
| Diablo Canyon 2 |
0 |
04/30/2011 |
DEFUELED |
* |
|
| Fort Calhoun |
0 |
04/09/2011 |
DEFUELED |
|
|
| Grand Gulf 1 |
96 |
|
POWER LIMITED 2ND STAGE MSR OUT OF SERVICE FOR THE ENTIRE CYCLE |
|
|
| Palo Verde 1 |
100 |
|
|
|
|
| Palo Verde 2 |
100 |
|
|
|
|
| Palo Verde 3 |
100 |
|
|
|
|
| River Bend 1 |
100 |
|
|
|
|
| San Onofre 2 |
100 |
|
|
|
|
| San Onofre 3 |
100 |
|
|
|
|
| South Texas 1 |
100 |
|
|
|
|
| South Texas 2 |
100 |
|
|
|
|
| Waterford 3 |
51 |
|
INCREASING POWER |
* |
|
| Wolf Creek 1 |
0 |
03/18/2011 |
REFUELING OUTAGE |
|
|
* - Power Reactor Status Report change within past 24 hours
# - Number of reactor scrams or trips within past 24 hours
Notes:- Reactor status data collected between 4 a.m. and 8 a.m. each day.
- All times are based on eastern time.
|
Page Last Reviewed/Updated Friday, March 30, 2012