Unit | Power | Down | Reason or Comment | Change in report(*) | Number of Scrams(#) |
BEAVER VALLEY 1 | 100 | | | | |
BEAVER VALLEY 2 | 0 | 09/22/2000 | REFUELING OUTAGE - FUEL RELOAD COMPLETE | * | |
CALVERT CLIFFS 1 | 100 | | | | |
CALVERT CLIFFS 2 | 100 | | | | |
FITZPATRICK 1 | 0 | 10/07/2000 | REFUELING OUTAGE - FUEL SHUFFLE IN PROGRESS | | |
GINNA 1 | 0 | 09/18/2000 | REFUELING OUTAGE - LOOPS NOT FILLED | * | |
HOPE CREEK 1 | 100 | | | | |
INDIAN POINT 2 | 0 | 02/15/2000 | DEFUELED | | |
INDIAN POINT 3 | 100 | | | | |
LIMERICK 1 | 100 | | | | |
LIMERICK 2 | 100 | | | | |
MILLSTONE 2 | 100 | | | | |
MILLSTONE 3 | 100 | | | | |
NINE MILE POINT 1 | 85 | | INCREASING POWER AFTER EXITING A PLANNED MAINTENANCE OUTAGE | * | |
NINE MILE POINT 2 | 100 | | | | |
OYSTER CREEK 1 | 79 | | COASTDOWN TO REFUELING OUTAGE | | |
PEACH BOTTOM 2 | 87 | | INCREASING POWER AFTER REDUCING TO 70% FOR PERFORMANCE OF A ROD PATTERN ADJUSTMENT | * | |
PEACH BOTTOM 3 | 100 | | | | |
PILGRIM 1 | 100 | | | | |
SALEM 1 | 100 | | | | |
SALEM 2 | 0 | 10/05/2000 | ENTERING REFUELING OUTAGE - HEAD DETENSIONING IN PROGRESS | * | |
SEABROOK 1 | 93 | | COASTDOWN TO REFUELING OUTAGE | * | |
SUSQUEHANNA 1 | 100 | | | | |
SUSQUEHANNA 2 | 100 | | | | |
THREE MILE ISLAND 1 | 100 | | | | |
VERMONT YANKEE 1 | 100 | | | | |
Region 2
Unit | Power | Down | Reason or Comment | Change in report(*) | Number of Scrams(#) |
BROWNS FERRY 1 | 0 | 03/03/1985 | DEFUELED | | |
BROWNS FERRY 2 | 100 | | | | |
BROWNS FERRY 3 | 100 | | | | |
BRUNSWICK 1 | 100 | | | | |
BRUNSWICK 2 | 100 | | | | |
CATAWBA 1 | 88 | | COASTDOWN TO REFUELING OUTAGE | | |
CATAWBA 2 | 100 | | | | |
CRYSTAL RIVER 3 | 100 | | | | |
FARLEY 1 | 90 | | HOLDING POWER AT THIS LEVEL TO PERFORM COOLING TOWER REPAIRS | * | |
FARLEY 2 | 100 | | | | |
HARRIS 1 | 100 | | | | |
HATCH 1 | 0 | 09/29/2000 | REFUELING OUTAGE - INITIAL (PARTIAL) CORE OFFLOAD COMPLETE | | |
HATCH 2 | 100 | | | | |
MCGUIRE 1 | 100 | | | | |
MCGUIRE 2 | 0 | 09/01/2000 | EXITING REFUELING OUTAGE | | |
NORTH ANNA 1 | 100 | | | | |
NORTH ANNA 2 | 100 | | | | |
OCONEE 1 | 100 | | | | |
OCONEE 2 | 100 | | | | |
OCONEE 3 | 100 | | | | |
ROBINSON 2 | 100 | | | | |
SAINT LUCIE 1 | 100 | | | | |
SAINT LUCIE 2 | 100 | | . | | |
SEQUOYAH 1 | 0 | 10/06/2000 | FORCED MAINTENANCE OUTAGE | * | |
SEQUOYAH 2 | 82 | | COASTDOWN TO REFUELING OUTAGE | * | |
SUMMER 1 | 0 | 10/07/2000 | REFUELING OUTAGE - PREPARING FOR FUEL OFFLOAD | * | |
SURRY 1 | 100 | | | | |
SURRY 2 | 0 | 09/30/2000 | REFUELING OUTAGE - DEFUELED | | |
TURKEY POINT 3 | 100 | | | | |
TURKEY POINT 4 | 0 | 09/24/2000 | REFUELING OUTAGE - FUEL RELOAD IN PROGRESS | * | |
VOGTLE 1 | 0 | 09/17/2000 | REFUELING OUTAGE - REACTOR COOLANT SYSTEM FILL AND VENT IN PROGRESS | * | |
VOGTLE 2 | 100 | | | | |
WATTS BAR 1 | 100 | | | | |
Region 3
Unit | Power | Down | Reason or Comment | Change in report(*) | Number of Scrams(#) |
BRAIDWOOD 1 | 100 | | | | |
BRAIDWOOD 2 | 100 | | | | |
BYRON 1 | 17 | | EXITING REFUELING OUTAGE - HOLDING POWER AT THIS LEVEL WITH THE UNIT OFF LINE DUE TO TURBINE PROBLEMS | * | |
BYRON 2 | 100 | | | | |
CLINTON 1 | 86 | | INCREASING POWER AFTER DECREASING TO 70% FOR PERFORMANCE OF A FEEDWATER PUMP CHANGEOUT - PLAN TO INCREASE TO 97% POWER TO CONTINUE A COASTDOWN TO REFUELING OUTAGE | * | |
COOK 1 | 0 | 09/08/1997 | REFUELING OUTAGE - DEFUELED | | |
COOK 2 | 100 | | | | |
DAVIS BESSE 1 | 100 | | | | |
DRESDEN 2 | 100 | | | | |
DRESDEN 3 | 100 | | | * | |
DUANE ARNOLD 1 | 100 | | | | |
FERMI 2 | 100 | | | | |
KEWAUNEE 1 | 96 | | MAXIMUM POWER DUE TO PLUGGED STEAM GENERATOR TUBES | | |
LASALLE 1 | 93 | | HOLDING POWER AT THIS LEVEL TO WORK ON A HEATER DRAIN VALVE | | |
LASALLE 2 | 97 | | HOLDING POWER AT THIS LEVEL DUE TO THERMAL LIMITS | * | |
MONTICELLO 1 | 100 | | | | |
PALISADES 1 | 100 | | | | |
PERRY 1 | 95 | | HOLDING POWER AT THIS LEVEL DUE TO MSR #2A AND #2B BEING ISOLATED | | |
POINT BEACH 1 | 90 | | REDUCED POWER FOR PLANNED 345-kV LINE MAINTENANCE | | |
POINT BEACH 2 | 99 | | COASTDOWN TO REFUELING OUTAGE | * | |
PRAIRIE ISLAND 1 | 100 | | | | |
PRAIRIE ISLAND 2 | 100 | | | | |
QUAD CITIES 1 | 80 | | COASTDOWN TO REFUELING OUTAGE | * | |
QUAD CITIES 2 | 100 | | | | |
Region 4
Unit | Power | Down | Reason or Comment | Change in report(*) | Number of Scrams(#) |
ARKANSAS NUCLEAR 1 | 100 | | | | |
ARKANSAS NUCLEAR 2 | 0 | 09/15/2000 | REFUELING OUTAGE - REPLACING STEAM GENERATORS - DEFUELED | | |
CALLAWAY 1 | 100 | | | | |
COMANCHE PEAK 1 | 100 | | | | |
COMANCHE PEAK 2 | 0 | 09/30/2000 | REFUELING OUTAGE - DEFUELED | | |
COOPER 1 | 100 | | | | |
DIABLO CANYON 1 | 0 | 10/08/2000 | ENTERING REFUELING OUTAGE. | | |
DIABLO CANYON 2 | 100 | | | | |
FT CALHOUN 1 | 100 | | | | |
GRAND GULF 1 | 100 | | | | |
PALO VERDE 1 | 100 | | | | |
PALO VERDE 2 | 0 | 10/03/2000 | REFUELING OUTAGE - FUEL OFFLOAD IN PROGRESS | | |
PALO VERDE 3 | 99 | | | | |
RIVER BEND 1 | 95 | | POWER UP RATE IN PROGRESS | | |
SAN ONOFRE 2 | 0 | 10/07/2000 | ENTERING REFUELING OUTAGE | * | |
SAN ONOFRE 3 | 100 | | | | |
SOUTH TEXAS 1 | 100 | | | | |
SOUTH TEXAS 2 | 100 | | | | |
WATERFORD 3 | 100 | | | | |
WNP-2 | 100 | | | | |
WOLF CREEK 1 | 0 | 09/29/2000 | REFUELING OUTAGE - DEFUELED | * | |
* - Power Reactor Status Report change within past 24 hours
# - Number of reactor scrams or trips within past 24 hours