Part 21 Report - 1998-271
ACCESSION #: 9805280008
Illinois Power Company
Clinton Power Station
P. O. Box 678
Clinton, IL 61727
Tel 217 935 5623
Fax 217 935 4632
Walter G. MacFarland IV
Senior Vice President
ILLINOIS and Chief Nuclear Officer
POWER
U-603004
An Illinova Company 4F.140
May 15, 1998
Docket No. 50-461
10CFR21.21
Document Control Desk
U.S. Nuclear Regulatory Commission
Washington, D.C. 20555
Subject: 10CFR21 Final Report 21-98-001: ITT Barton Model 580A Series
Differential Pressure Indicating Switch Operating Force
Concerns
Dear Madam or Sir:
On December 22, 1997, ITT Barton issued an Industry Advisory memo to
Illinois Power (IP) identifying a condition potentially affecting ITT
Barton Models 580A, 581A, 583A, and 583B, safety-related differential
pressure indicating switches supplied with certification to IEEE-323/344
qualifications. ITT Barton identified that the miniature switches used
inside the indicated instruments may have operating forces too low to
preclude switch contact chatter in some installations when subjected to
seismic induced vibrations.
ITT Barton had originally certified that these switches would not
experience contact chatter during seismic loadings of up to 12 Gs, as
long as the force required to operate the internal miniature switches is
high (i.e., between 76 and 95 grains). ITT Barton performs operating
force selection testing where all switches with operating force between
76 and 95 grams are identified and marked with a blue paint spot. All
remaining switches are marked with a yellow paint spot. ITT Barton
discovered that their manufacturing system had allowed the yellow paint
spot switches to be used along with the blue paint spot switches in
assembly of Models 580A, 581A, 583A, and 583B differential pressure
indicating switches supplied with IEEE 323/344 certification to ITT
Barton Qualification Reports R3-580A-9, R3-580A-10, R3-580A-29 or to
Westinghouse with Certification to ITT Barton Baseline Documents 0580-
11395, 0581-10325, and 0581-10225. The use of the low operating force
miniature switches instead of the originally qualified high operating
force miniature switches reduces the seismic qualification level from 12
Gs to 4 Gs (peak spectral acceleration).
IP determined that this issue was potentially reportable under the
provisions of 10CFR21 on January 7, 1998. Condition Report 1-98-01-056
was initiated to track investigation and resolution of this issue. IP
notified the NRC via letter U-602952
U-603004
Page 2
dated March 6, 1998, that the evaluation of this issue under the
provisions of 10CFR21 was not complete.
The evaluation of this issue is now complete and IP concludes that
this issue is not reportable under the provisions of 10CFR21 for Clinton
Power Station (CPS). The basis for the not reportable conclusion is that
four potentially affected safety-related differential pressure indication
switches were identified at CPS; an four are installed in the plant. Two
of the four potentially affected units were inspected and found
acceptable. A seismic evaluation of the remaining two potentially
affected units, not available for inspection due to plant conditions,
identified that the peak spectral acceleration calculated at the mounting
locations of these units is less than 4 Gs. Therefore, CPS is not
adversely affected by this issue.
Additional information about this issue may be obtained by
contacting R. D. Weber, Supervisor-Procurement Engineering, at (217) 935-
8881, extension 3785.
Sincerely your
Walter G. MacFarland, IV
Senior Vice President and
Chief Nuclear Officer
RSF/mlh
cc: NRC Clinton Licensing Project Manager
NRC Resident Inspector
Regional Administrator, Region III, USNRC
Illinois Department of Nuclear Safety
INPO Records Center
ITT Barton
*** END OF DOCUMENT ***
Page Last Reviewed/Updated Wednesday, March 24, 2021