10 CFR PART 21 NOTIFICATION REGARDING HIGH FAILURE RATES OF BW/IP
(FORMERLY BORG-WARNER) PRESSURE SWITCHES INSTALLED ON BW/IP
ELECTRO-HYDRAULIC ACTUATORS USED IN THE GAS TREATMENT, SERVICE
WATER, AND HEATING AND VENTILATION SYSTEMS AT NINE MILE POINT
UNIT 2 (REFER TO EVENT #31822 FOR ADDITIONAL INFORMATION.)
ON FEBRUARY 20, 1997, NINE MILE POINT UNIT 2 MADE A NOTIFICATION
TO THE NRC REGARDING THE EXISTENCE OF A DEVIATION OR
NON-CONFORMANCE CONDITION IN A BASIC COMPONENT THAT WAS
REPORTABLE UNDER 10 CFR PART 21 GUIDELINES. THE BASIC COMPONENT
WAS IDENTIFIED AS A SAFETY-RELATED PRESSURE SWITCH SUPPLIED BY
BW/IP THAT MAY BE IN ONE OF FIVE PART NUMBERS, AND THE REPORT
CITED A HIGH FAILURE RATE OF THESE PRESSURE SWITCHES.
ENERTECH AND BW/IP ARE CURRENTLY INVESTIGATING THIS ISSUE.
ENERTECH IS ALERTING ALL POTENTIALLY AFFECTED CUSTOMERS OF A
REPORTED SAFETY-RELATED BASIC COMPONENT THAT IS CURRENTLY BEING
INVESTIGATED BY NINE MILE POINT UNIT 2 UNDER 10 CFR PART 21
GUIDELINES. SINCE ENERTECH WAS NOT PART OF THE NINE MILE POINT
EVALUATION PROCESS, ENERTECH HAS ALSO REQUESTED HARDWARE AND
DOCUMENTATION FROM NINE MILE POINT PERSONNEL FOR BW/IP EVALUATION
OF THE STATED SITUATION. ADDITIONALLY, ENERTECH REQUESTED
FEEDBACK FROM POTENTIALLY AFFECTED CUSTOMERS.
(REFER TO THE HOO LOG FOR CONTACT NAMES AND TELEPHONE NUMBERS.)