Part 21 Report - 1995-007
ACCESSION #: 9501040170
TELEPHONE (815)
727-2600
POST OFFICE BOX
3339
JOLIET, IL
60434
CRANE NUCLEAR OPERATIONS
CRANE VALVES 104 NORTH CHICAGO STREET JOLIET, IL
60431
December 28, 1994
Document Control Desk
U.S. Nuclear Regulatory Commission
Washington, DC 20555
SUBJECT: INTERIM REPORT #2 of 10CFR Part 21 Evaluation
REFERENCE: Crane Letter Dated August 30, 1994 and Northern
States
Power Letter of April 18, 1994
Gentlemen:
This letter is a follow-up to the referenced letter, in which Crane
Valves
Nuclear Operations advised that we were undertaking an
investigation with
respect to the January 1994 incident at Prairie Island Nuclear
Generating
Plant involving Crane Design Gate Valves.
Additional information has been received from nuclear plants that
also
have Crane Design Gate Valves of the same model.
It is expected that the evaluation will be completed within the
next 30
days. Any questions can be directed to my attention at
815-740-7571.
Sincerely,
Henry G.L. McCullough, P.E.
Manager Engineering/
Quality Assurance
HGMcC/cs
cc: John Carlson
Bruce Harry
Kevin Hutchinson
File
*** END OF DOCUMENT ***