Morning Report for February 25, 2008

Headquarters Daily Report

To top of page

REGION I

Plant Management Change for Vermont Yankee Nuclear Power Station

Licensee/Facility:

ENTERGY NUCLEAR OPERATIONS, INC.
Vermont Yankee
VERNON, Vermont
Dockets: 05000271
[1] GE-4
License No:
Notification:

MR Number: 1-2008-0003
Date: 02/25/2008

E-MAIL from Licensee

Discussion:


On February 22, Entergy announced that General Manager, Plant Operations (GMPO), William Maguire will be leaving Vermont Yankee to pursue opportunities outside of Entergy. Current Planning, Scheduling, and Outages Manager Chris Wamser will be the acting GMPO until a permanent replacement is selected. The management change will be effective at the end of March.

Accession Numbers:

Accession No Accession Date
ML080560291 02/25/2008

Contacts:

Name Office Abbrev Phone No E-Mail
POWELL, RAYMOND J R1 (610) 337-6967 RJP@nrc.gov


To top of page

REGION III

Management changes

Licensee/Facility:

FIRSTENERGY NUCLEAR OPERATING CO.
Davis-Besse
OAK HARBOR, Ohio
Dockets: 05000346
[1] B&W-L-LP
License No:

FirstEnergy Nuclear Operating Co.
Perry 1
PERRY, Ohio
Dockets: 05000440
[1] GE-6
Notification:

MR Number: 3-2008-0006
Date: 02/25/2008

Call to RA / fax from RIO

Discussion:

On Monday, February 25, Mr. Jim Lash, Senior Vice President of FirstEnergy Nuclear Operating Company Operations, announced that Mr. Mark Bazilla, Vice President Davis-Besse Nuclear Power Plant, and Mr. Barry Allen, Vice President Perry Nuclear Power Plant, will exchange positions. The position exchange is to be effective March 10, 2008.

Regional Action: None

Accession Numbers:

Accession No Accession Date
ML080560502 02/25/2008

Contacts:

Name Office Abbrev Phone No E-Mail
WRIGHT, GEOFFREY C R3 (630) 829-9602 GCW@nrc.gov

Page Last Reviewed/Updated Thursday, March 25, 2021