Morning Report for March 15, 2004

Headquarters Daily Report

To top of page

REGION III

Davis-Besse Plant Status

Licensee/Facility:

FIRSTENERGY NUCLEAR OPERATING CO.
Davis-Besse
AKRON, Ohio
Dockets: 05000346
[1] B&W-L-LP
License No:
Notification:

MR Number: 3-2004-0019
Date: 03/15/2004

RIII-Via Teleconf. with Site

Discussion:

This information is current as of 7:30 am (EST) on March 15, 2004. The plant is currently in Mode 1 at 14% reactor power. The plant entered Mode 1 on March 14, 2004, at 11:59 p.m.

Upcoming key events include conducting initial grid synchronization for Main Turbine-Generator testing, performing a readiness and effectiveness review prior to exceeding 50% power, placing a second main feedwater pump in service, and power ascension to 100% power. Absent significant performance or equipment problems these events are scheduled to be accomplished in the next five to seven days.

Ongoing resident inspector coverage, and around-the-clock inspection and oversight of licensee activities continues with NRC resident inspector and examiner support from all Regional Offices. This coverage, which commenced March 9, is expected to be in place for approximately two weeks.

Regional Action: For Information Only

Accession Numbers:

Accession No Accession Date
ML040750288 03/15/2004

Contacts:

Name Office Abbrev Phone No E-Mail
LIPA, C A R3 (630) 829-9619 CAL@nrc.gov

Page Last Reviewed/Updated Wednesday, March 24, 2021