Morning Report for March 14, 2003


                       Headquarters Daily Report

                         MARCH 14, 2003

*****************************************************
                    REPORT             NEGATIVE      
                    ATTACHED           INPUT RECEIVED

HEADQUARTERS                              X                   
REGION I                                  X                   
REGION II                                 X                   
REGION III             X                                      
REGION IV                                 X  

                 

PRIORITY ATTENTION REQUIRED  MORNING REPORT - REGION III  MARCH 14, 2003

Licensee/Facility:                     Notification:

Toledo Edison Co.                      MR Number: 3-03-0007
Davis Besse 1                          Date: 03/12/03
Oak Harbor,Ohio                        Senior Resident Inspector          
Dockets: 50-346
PWR/B&W-R-LP                          

Subject: DAVIS-BESSE MODE 5 ENTRY                                        

Discussion:

On March 12, 2003, at 3:12 p.m. (ET), the plant entered Mode 5 (Cold     
Shutdown) when the new reactor vessel head, obtained from the canceled   
Midland plant, was tensioned onto the reactor vessel. Significant work   
remains until the plant is scheduled to enter Mode 4 (Hot Shutdown).     

Regional Action:

Information Only.                                                        

Contact:  C. Lipa                    (630)829-9619

 