EA-98-513 - Saint Lucie 1 (Florida Power & Light Co.)
March 31, 1999
EA 98-513
Florida Power & Light Company
ATTN: Mr. T. F. Plunkett
President
- Nuclear Division
P. O. Box 14000
Juno Beach, Florida 33408-0420
SUBJECT: NOTICE OF VIOLATION AND EXERCISE OF DISCRETION
(NRC
INSPECTION REPORT NOS. 50-335/98-14, 50-389/98-14)
Dear Mr. Plunkett:
This refers to the inspection conducted on October 10-23 and November
2-6, 1998, at the St. Lucie facility. The purpose of the inspection was
to further evaluate the issues identified during the Fire Protection Functional
Inspection (FPFI) that was conducted in March and April 1998. The results
of the inspection were discussed with your staff at an exit meeting conducted
on December 4, 1998, and were formally transmitted to you by letter dated
December 4, 1998. An open, predecisional enforcement conference was conducted
in the Region II office on January 7, 1999, with you and members of your
staff to discuss the apparent violations, the root causes, and corrective
actions to preclude recurrence. A list of conference attendees, copies
of the Nuclear Regulatory Commission's (NRC) slides, and Florida and Power
Light Company's (FP&L) presentation materials are enclosed.
Based on the information developed during the inspections and the information
that you provided during the conference, the NRC has determined that four
violations of NRC requirements occurred. One of the violations is cited
in the enclosed Notice of Violation (Notice) and the circumstances surrounding
all four violations are described in detail in the subject inspection
report and summarized below.
The first violation, as described in the Notice, involves an inadequate
fire protection procedure intended to implement the alternative shutdown
capability in the event of a main control room evacuation. At the conference
and as documented in NRC Inspection Report Nos. 50-335/98-14, 50-389/98-14,
the NRC initially determined that a violation of 10 CFR 50, Appendix R,
Sections III.L.2.e and III.L.3 occurred, based on the understanding that,
for fires in the control room or in the cable spreading room, the normal
heating, ventilation, and air conditioning (HVAC) support functions would
be lost due to a loss of offsite power. We also previously determined
that heat and smoke from a postulated cable spreading room fire could
affect the habitability of the Hot Shutdown Control Panel (HSCP) room
and the switchgear room. However, based on new information FP&L provided
at the conference, the NRC has concluded that the issue is more appropriately
characterized as a procedural inadequacy involving the procedures needed
to provide operator habitability, as it appears that HVAC equipment would
have been available to provide the process cooling necessary for the HSCP
room and the 1B Electrical Equipment room. Specifically, process cooling
to these areas could be achieved through manual operation of HVAC equipment
whose control circuits and components were protected from fire. As discussed
at the conference, Procedure 1-ONOP-100.02, "Control Room Inaccessibility,"
was the procedure plant operators would have used to evacuate the control
room in the event of a fire, and this procedure did not provide the necessary
direction to plant operators to place in service the appropriate HVAC
equipment and take other actions to ensure acceptable habitability conditions
in the 1B Electrical Equipment room and HSCP room. You pointed out at
the conference that even absent specific procedural guidance, there was
likelihood that operators would transition to Emergency Operating Procedure
(EOP) 1-EOP-99, "Appendices/Figures/Tables," which did provide direction
to energize the 1B Switchgear Room Exhaust Fan. However, operation of
this fan alone, per the EOP, could have caused smoke migration which would
have further impacted habitability of the HSCP, absent other, unproceduralized
actions. Based on further review of this issue, the NRC has concluded
that the lack of procedural guidance to ensure proper and expeditious
operation of HVAC equipment supporting the 1B Electrical Equipment room and
HSCP room is a violation of 10 CFR 50, Appendix R, Section III.L.3. The
root cause of the violation was FP&L's failure to adequately address
HSCP habitability in the original Unit 1 Safe Shutdown Analysis and Alternate
Shutdown Procedure.
As part of its consideration of the Severity Level of this violation,
the NRC independently assessed its risk significance. As presented at
the conference, your staff concluded the increase in risk was low. Our
analysis concludes that, although the contribution to risk of the violation
when viewed in isolation may be low, when viewed in the context of the
overall fire protection program at this facility, the violation is of
moderate risk significance. Specifically, the FPFI noted other deficiencies
in detection and suppression capabilities at the facility. Such deficiencies
credibly increase the frequency of the conditions under which the habitability
of the HSCP room becomes an issue, and thus increase the risk. Additionally,
there was uncertainty as to the potential for smoke migration to the HSCP
room which would adversely affect the success of achieving and maintaining
safe shutdown conditions, upon energization of the available HVAC system.
The NRC has normally categorized at Severity Level III those violations,
in which a postulated fire could so damage equipment that shut down could
not be achieved and maintained using the applicable equipment identified
in the fire hazards analysis in accordance with applicable requirements.
In this case, the absence of instructions in the designated procedure,
to provide HVAC support to ensure habitability of the HSCP room, posed
an additional challenge to achieving safe shutdown. For these reasons,
the violation has been categorized in accordance with the "General Statement
of Policy and Procedures for NRC Enforcement Actions" (Enforcement Policy),
NUREG-1600 at Severity Level III.
In accordance with the Enforcement Policy, a base civil penalty in the
amount of $55,000 is considered for a Severity Level III violation. Because
your facility has been the subject of escalated enforcement action within
the last two years(1), the NRC considered
whether credit was warranted for Identification and Corrective
Action in accordance with the civil penalty assessment process described
in Section VI.B.2 of the Enforcement Policy. This violation was identified
by the NRC. However, based on the information provided by FP&L at
the conference, the NRC has determined that credit is warranted for identification
of this issue because the FP&L SSA Revalidation effort, in progress
at the time of the inspection, was sufficient in scope to conclude that
FP&L would have likely identified this issue absent NRC involvement.
Your corrective actions for the violation were prompt and comprehensive.
FP&L immediately revised the Alternate Shutdown Procedure to include
interim manual actions to operate HVAC equipment and create an adequate
ventilation path to support the 1B Switchgear Room and HSCP room habitability.
This was considered an acceptable interim measure until modifications
to protect the HSCP fan circuits, scheduled for completion in 1999, are
completed. In addition, cameras were installed to serve as a continuous
fire watch for this fire area. As such, the NRC concluded that credit
is warranted for the factors of Identification and Corrective
Action.
Therefore, to encourage prompt identification and comprehensive correction
of violations, I have been authorized, after consultation with the Director,
Office of Enforcement, not to propose a civil penalty for this violation.
However, similar violations in the future could result in a civil penalty.
The second violation involves FP&L's failure to install a one-hour
rated fire barrier for charging pump (CP) 1A. Operating License Condition
2.C(3) requires that FP&L implement the fire protection program as
described in the Updated Final Safety Analysis Report (UFSAR). The UFSAR,
Volume 9.5, Section 4N, Exemption N1 states that conduits carrying cables
for CP 1A in Fire Zone 38 will be provided with a minimum one-hour rated
protection. However, due to FP&L's inadequate implementation of the
original fire protection exemption, the required one-hour fire barrier
was not installed in Fire Zone 38 as required by FP&L's Operating
License, Condition 2.C(3). If an all-consuming fire occurred in Fire Area
N (which consists of Fire Zones 36A, 38, 75, 76) affecting cables above
the fire partitions that separate the charging pumps, all charging pumps
could have been rendered inoperable. As FP&L presented at the conference,
EOPs were available to place in service the high pressure safety injection
pumps to provide an alternate reactor coolant system makeup source, should
the charging pumps have become unavailable due to a fire in the area.
Regarding the third violation, the NRC initially determined that FP&L
was unable to limit fire damage so that one train of a system (in this
case, the Train A shutdown cooling equipment, including the low pressure
safety injection (LPSI) 1A pump) was free from fire damage as required
by Section III.G.1 of Appendix R to 10 CFR 50, because Train A equipment
contained unprotected cables. However, FP&L provided information at
the conference indicating that Train B components, being protected from
fire, could easily be placed in service to satisfy Appendix R requirements
to achieve and maintain hot or cold shutdown. As FP&L stated at the
conference, the procedure to be used to respond to fires in this fire
area, Off-normal Operating Procedure 1-ONOP-100.01, "Response to Fire,"
incorrectly identified that Train A shutdown cooling equipment was protected
from fire instead of Train B equipment. This error occurred during FP&L's
original SSA reviews. Based upon an additional review of this issue, including
the information FP&L provided at the conference, the NRC has concluded
that Procedure 1-ONOP-100.01 was inadequate, in that it referenced the
use of Train A of shutdown cooling equipment rather than Train B equipment.
As FP&L stated at the conference, the use of Train B LPSI pumps to
achieve cold shutdown was maintained at all times and could have been
accomplished in accordance with EOPs, and this task was well within the
capability of plant operators.
The NRC has determined that these two violations did not pose a significant
challenge to the ability to achieve safe shutdown. Therefore, the NRC
has concluded that the two violations should be classified separately
as Severity Level IV violations. Your corrective actions for the two violations
were determined to be prompt and comprehensive. Corrective actions for
first of these violations included the completion of a modification to
reroute the control circuit for CP 1A, a modification for CP 1A power
cable protection (to be completed by March 1999), and the installation
of cameras to serve as a continuous fire watch for this fire area. Your
corrective actions for the second of these violations included a prompt
procedural revision to reflect that Train B LPSI is the protected train.
Therefore, these Severity Level IV violations are being treated as two
separate Non-Cited Violations, consistent with Appendix C of the NRC Enforcement
Policy.
An additional apparent violation was discussed at the conference and documented
in NRC Inspection Report Nos. 50-335/98-14, 50-389/98-14, involving the
analysis methodology and evaluations for circuits of equipment whose spurious
actuation could adversely affect post-fire safe-shutdown capability. Specifically,
this issue involved three separate but related areas: (1) an FP&L
analysis methodology, which assumed only one spurious operation to occur
as a result of fire in any area, without any further consideration of
the number, type, or specific location of potentially affected cables
and circuits; (2) the potential for fire to cause a breach of pressurizer
power operated relief valve (PORV) and reactor coolant system gas vent
system (RCSGVS) high/low pressure interface boundaries; and (3) an inadequate
evaluation of the potential for fire to cause damage to motor operated
valves (MOVs) relied on to accomplish post-fire safe-shutdown functions.
You informed the NRC at the conference that FP&L disagreed with the
NRC's position that 10 CFR 50, Appendix R required licensees to consider
multiple spurious equipment operation in facility SSAs. FP&L stated
that the facility's original SSA assumed any and all spurious equipment
operation, one at a time, in accordance with NRC Generic Letter 86-10,
Implementation of Fire Protection Requirements, dated April 24, 1986.
In addition, FP&L concluded that issues (1) and (2) were not risk
significant, based on the following: the results of the recently completed
Unit 1 and 2 SSA Revalidation effort, which considered multiple concurrent
spurious equipment operation and concluded that this condition would have
minimal impact on the overall results of the SSA; the small portion of
the PORV circuitry that was not protected; and the reactor coolant system
inventory loss due to spurious operation of the RCSGVS high/low pressure
interface boundary valves could be accommodated by the makeup capacity
of one charging pump. However, the NRC has concluded that multiple spurious
operation of equipment in the event of a fire is within the licensing
basis of the facility and our position is consistent with previously issued
NRC guidance for implementation of fire protection requirements.
Accordingly, we have determined that issues (1) and (2) above constitute
violations of 10 CFR 50, Appendix R, Section III.L.7. However, after consultation
with the Director, Office of Enforcement, the NRC is exercising discretion
to not issue a Notice of Violation for these Severity Level III violations.
For issue (1), discretion is being exercised pursuant to Section VII.B.6
of the Policy because of: (i) the apparent widespread industry misunderstanding
of the requirement; (ii) the low risk significance; and (iii) your actions
to promptly perform the required analysis, evaluate the effect of this
condition on the facility, and complete the required corrective actions.
For issue (2), discretion is being exercised pursuant to Section VII.B.3
of the NRC Enforcement Policy because: (i) these circuit vulnerabilities
were independently identified by your staff prior to the FPFI; (ii) they
were caused by inadequate original implementation of the SSA and not reflective
of current performance; and (iii) the corrective actions taken and planned
are appropriate.
Based on the information FP&L provided at the conference, the NRC
considers it appropriate to hold in abeyance the final disposition of
issue (3) above regarding the potential for fire to cause damage to MOVs,
pending the completion of FP&L's MOV evaluation and NRC's additional
review of the results of that evaluation. This issue will continue to
be identified as EEI 50-335, 389/98-14-07.
The NRC has concluded that information regarding the reason for the violation
cited in the enclosed Notice, the corrective actions taken and planned
to correct the violation and prevent recurrence, and the date when full
compliance was achieved is already adequately addressed on the docket
as documented in Inspection Report No. 50-335/98-14, 50-389/98-14 and
this letter. Therefore, you are not required to respond to this letter
unless the description therein does not accurately reflect your corrective
actions or your position. In that case, or if you choose to provide additional
information, you should follow the instructions specified in the enclosed
Notice.
In accordance with 10 CFR 2.790 of the NRC's "Rules of Practice," a copy
of this letter and its enclosures will be placed in the NRC Public Document
Room.
| Sincerely, |
||
| Original Signed by Luis A. Reyes |
||
| Luis A. Reyes Regional Administrator |
Docket Nos. 50-335, 50-389
License Nos. DPR-67, NPF-16
Enclosure: Notice of Violation
cc w/encls:
J. A. Stall
Vice President
St. Lucie Nuclear Plant
6351 South Ocean Drive
Jensen Beach, FL 34957
R. G. West
Plant General Manager
St. Lucie Nuclear Plant
6351 South Ocean Drive
Jensen Beach, FL 34957
E. J. Weinkam
Licensing Manager
St. Lucie Nuclear Plant
6351 South Ocean Drive
Jensen Beach, FL 34957
John Gianfrancesco, Manager
Administrative Support & Special Projects
Florida Power & Light Company
P. O. Box 14000
Juno Beach, FL 33408-0420
Rajiv S. Kundalkar
Vice President - Nuclear Engineering
Florida Power & Light Company
P. O. Box 14000
Juno Beach, FL 33408-0420
M. S. Ross, Attorney
Florida Power & Light Company
P. O. Box 14000
Juno Beach, FL 33408-0420
William A. Passetti
Bureau of Radiation Control
Department of Health and
Rehabilitative Services
2020 Capital Circle SE, Bin #C21
Tallahassee, FL 32399-1741
Joe Myers, Director
Division of Emergency Preparedness
Department of Community Affairs
2740 Centerview Drive
Tallahassee, FL 32399-2100
J. Kammel
Radiological Emergency
Planning Administrator
Department of Public Safety
6000 SE Tower Drive
Stuart, FL 34997
Douglas Anderson
County Administrator
St. Lucie County
2300 Virginia Avenue
Ft. Pierce, FL 34982
|
NOTICE OF VIOLATION |
||
| Florida Power & Light Company St. Lucie Nuclear Plant |
Docket No. 50-335 License No. DPR-67 EA 98-513 |
During an NRC inspection conducted on October 10-23 and November 2-6, 1998, a violation of NRC requirements was identified. In accordance with the "General Statement of Policy and Procedures for NRC Enforcement Actions," NUREG-1600, the violation is listed below:
Operating License DPR-67 (Unit 1) Condition 2.C (3) specifies that the licensee implement and maintain in effect all provisions of the approved fire protection program as described in the Updated Final Safety Analysis Report (UFSAR) for the facilities and as approved by various NRC Safety Evaluation Reports. Unit 1, which was licensed to operate prior to January 1, 1979, is required by 10 CFR 50.48(b) to meet the requirements of Sections III.L of Appendix R to 10 CFR Part 50.
Section III.L.3 of Appendix R to 10 CFR Part 50 requires that the alternative shutdown capability be independent of the specific fire areas(s) and shall accommodate post-fire conditions where offsite power is available and where offsite power is not available for 72 hours. Procedures shall be in effect to implement this capability.
Procedure 1-ONOP-100.02, "Control Room Inaccessibility," Revision 1, is the procedure that implemented the licensee's alternative shutdown capability.
Contrary to the above, as of April 3, 1998, Procedure 1-ONOP-100.02 was inadequate to implement the alternative shutdown capability. Specifically, the procedure failed to provide adequate guidance to ensure that heating, ventilation and air conditioning equipment to the 1B Electrical Equipment Room and the Hot Shutdown Control Panel Room would be properly operated in the event of a fire in the Control Room or in the Cable Spreading Room. (01013)
This is a Severity Level III violation (Supplement I).
The NRC has concluded that information regarding the reasons for the violation,
the corrective actions taken and planned to correct the violation and
prevent recurrence, and the date when full compliance was achieved has
been adequately addressed on the docket as discussed in the letter transmitting
this Notice of Violation (Notice), and in Inspection Report Nos. 50-335/98-14,
50-389/98-14. However, you are required to submit a written statement
or explanation pursuant to 10 CFR 2.201 if the description therein does
not accurately reflect your corrective actions or your position. In that
case, or if you choose to respond, submit a written statement or explanation
to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk,
Washington, D.C. 20555-0001 with a copy to the Regional Administrator,
Region II, U.S. Nuclear Regulatory Commission, Atlanta Federal Center,
23T85, 61 Forsyth Street S.W., Atlanta, Georgia, 30303-3415 and a copy
to the NRC Resident Inspector at the St. Lucie facility, within 30 days
of the date of the letter transmitting this Notice.
If you contest this enforcement action, you should also provide a copy
of your response, with the basis for your denial, to the Director, Office
of Enforcement, United States Nuclear Regulatory Commission, Washington,
DC 20555-0001.
If you chose to respond, your response will be placed in the NRC Public
Document Room (PDR). Therefore, to the extent possible, the response should
not include any personal privacy, proprietary, or safeguards information
so that it can be placed in the PDR without redaction.
In accordance with 10 CFR 19.11, you may be required to post this Notice
within two working days after receipt.
Dated this 31st day of March 1999
1. A Notice of Violation and Proposed Imposition of Civil Penalty in the amount of $88,000 was issued on March 25, 1998, for a Severity Level II problem involving an incorrect Refueling Water Tank setpoint (EA 98-009).

