March 13, 2003
The Honorable Richard A. Meserve
Chairman
U.
S. Nuclear Regulatory Commission
Washington, DC 20555-0001
| SUBJECT: |
REACTOR OVERSIGHT PROCESS |
Dear Chairman Meserve:
The Advisory Committee on Reactor Safeguards (ACRS) and its Plant Operations Subcommittee have had a number of interactions with the U.S. Nuclear Regulatory Commission (NRC) staff on the Reactor Oversight Process (ROP). In reports dated October 12, 2001, and February 13, 2002, the ACRS raised several issues that included:
- the appropriateness of the threshold values for the yellow-red performance indicator (PI) levels, and
- inconsistencies between the performance assessment and the significance determination process (SDP).
The ACRS met with the staff at its 500th meeting on March 6, 2003, to discuss these issues. At the conclusion of this meeting, it was evident that there are still significant disagreements between the staff and the Committee. This report, then, is intended to clarify the ACRS views on this matter and to serve as a basis for further discussion.
The ACRS views on the ROP are as follows:
- The purpose of the ROP is to assess safety performance so that the agency can take appropriate action.
- The ROP is risk-informed because it focuses on performance areas and indicators that affect safety.
- It is incorrect to base thresholds for PIs
on risk metrics such as
CDF
(changes in core damage frequency) and
LERF
(changes in large, early release frequency). - The thresholds separating all the performance levels (colors) should be performance-based and determined by expert judgement similar to the selection of the current green/white thresholds.
- The principal role for the SDP is to assign risk characterization to inspection findings not to be an evaluation of performance.
- PIs are needed for the cross-cutting issues and their development should be pursued by the staff.
- The Action Matrix should reflect the complementary results of the performance assessment and the SDP.
- Lack of parity
among thresholds may result in suboptimal allocation of NRC and licensee resources.
DISCUSSION
Our
view is that the purpose of the ROP is to assess changes in performance, not changes
in risk. We believe that the ROP is risk-informed because it focuses attention
on performance areas that are known to be cornerstones of safety. As we have noted
previously, however, it is misleading to assess the importance of changes even
in a risk-informed PI in terms of
CDF.
Clearly, degraded performance can translate into an increase in the risk
posed by a given plant. However, a realistic estimate of
CDF
cannot be determined from changes in a single isolated parameter with the assumption
that all other factors that can affect CDF remain constant. Thus, the selection
of thresholds based on
CDF,
as was done for the "number-of-scrams" PI, is misleading with respect
to indicating the extent of degraded performance. Our view is that such thresholds
should be selected on a performance basis and chosen through expert judgment and
not be based on such risk considerations.
The SDP process should continue to evaluate the risk significance of events and findings. This information complements the performance assessment findings from the PIs. The two sets of information are complementary, and it is appropriate that both be addressed in the Action Matrix.
We continue to doubt the validity of the assumption that degraded performance in the cross-cutting areas will be revealed by the current PIs and inspections. Efforts to develop new PIs should be focused on licensees' corrective action programs, human performance, and safety conscious work environment.
The staff and the Committee agree that the significance of the thresholds for the various PIs should be examined. In addition to improving the coherence of the Action Matrix, parity in significance will yield another benefit. NRC and licensee resources are naturally biased toward performance areas that are rated other than green. If the thresholds are chosen inappropriately, then resources may be misallocated.
Sincerely,
/RA/
Mario V. Bonaca
Chairman