10 CFR 50 Appendix B Notices of Nonconformance (NON) and Violation (NOV) - VII. Control of Purchased Material, Equipment, and Services

The following table lists, in chronological order, the Quality Assurance (QA) Inspection for New Reactor Licensing reports and Vendor QA Inspection reports with a Criterion VII NON/NOV.

This page includes links to files in non-HTML format. See Plugins, Viewers, and Other Tools for more information.

Date Title
07/07/23 Prysmian Group, Willimantic, CT, limited scope inspection to assess compliance with selected portions of their quality assurance (QA) and Part 21 programs, as they pertain to activities conducted at their facility related to the manufacturing of transmission cables for NRC’s regulated facilities.
11/19/21

NTS Huntsville, Huntsville, AL, limited scope inspection to assess compliance with selected portions of their quality assurance (QA) and Part 21 programs, specifically as they pertain to safety-related testing activities conducted at their facility for NRC's regulated facilities.

09/06/19

Curtiss-Wright Enertech, Brea, CA, limited scope inspection to assess compliance with selected portions of their quality assurance (QA) and Part 21 programs, specifically as they pertain to activities conducted at your facility related to the commercial-grade-dedication associated with nuclear-related parts for NRC's regulated facilities.

09/11/18

Hayward-Tyler, Inc., Colchester, VT, limited scope inspection to assess compliance with selected portions of their quality assurance (QA) and Part 21 programs as it pertains to as they pertain to Hayward-Tyler, Inc.'s: design, qualification, commercial grade dedication, and manufacturing of safety related pumps and other equipment for operating nuclear power plants. Also, the inspection will review the activities that address the Notices of Noncompliance (NONs) from the previous NRC inspection.

03/07/18

Flowserve Corporation, Limitorque Valve Operator Manufacturer, Lynchburg, VA, limited scope inspection to assess compliance with selected portions of their quality assurance (QA) and Part 21 programs specifically, as it pertains to Flowserve's supply of Limitorque nuclear safety-related components to the U.S. nuclear industry.

11/16/17

Valcor Engineering Corporation, Springfield Township, NJ, limited scope inspection to assess compliance with selected portions of their quality assurance (QA) and Part 21 programs, specifically as they pertain to activities conducted at their facility related to the design, fabrication, and testing of valves and replacement valve parts for NRC's regulated facilities.

09/13/17

Konecranes Nuclear Equipment & Services (KNES) LLC, New Berlin, WI, limited scope inspection to assess compliance with selected portions of their quality assurance (QA) and Part 21 programs as they pertain to activities conducted at their facility related to the design, fabrication, and testing of several types of cranes and handling equipment for NRC's regulated facilities.

08/22/17

Flowserve Corporation, Raleigh, NC, limited scope inspection to assess compliance with selected portions of their quality assurance (QA) and Part 21 programs as it pertains to activities conducted at your facility related to the design, fabrication, and testing of valves and replacement valve parts for NRC's regulated facilities.

07/31/17

Mirion Technologies (IST) Corporation, Horseheads, NY, limited scope inspection to assess compliance with selected portions of their quality assurance (QA) and Part 21 programs as it pertains to their supply of nuclear safety-related components to the U.S. nuclear industry.

06/05/17

Velan Inc., Montreal, Canada, limited scope inspection to assess compliance with selected portions of their quality assurance (QA) and Part 21 programs as they pertain to activities conducted at their facility related to the design, fabrication, assembly, and testing of valves and replacement parts for NRC's regulated facilities.

05/04/17

L&S Machine Company, Latrobe, PA, limited scope inspection to assess compliance with selected portions of their quality assurance (QA) and 10 CFR Part 21 programs, as they pertain to activities conducted at your Latrobe and Marion Center facilities related to safety-related components for Westinghouse Electric Corporation.

04/24/17

Target Rock, Industrial Division, Curtiss-Wright, Farmingdale, NY, limited scope inspection to assess compliance with selected portions of their quality assurance (QA) and 10 CFR Part 21 programs, as they pertain to activities conducted at their facility related to the design, manufacture, and testing of valves for nuclear power plants.

12/21/16

Curtiss Wright - Electro-Mechanical Division, Cheswick, PA, limited scope inspection to assess compliance with selected portions of their quality assurance (QA) and 10 CFR Part 21 programs specifically, as they pertain to activities conducted at your facility related to the design, manufacture, and qualification testing of the reactor coolant pumps for the AP1000 reactor design.

11/29/16

General Atomics Electromagnetic Systems (GA-EMS), San Diego, CA, limited scope inspection to assess compliance with selected portions of their quality assurance (QA) and 10 CFR Part 21 programs specifically, as it pertains to GA-EMS's design and manufacturing of radiation monitoring systems supplied for the U.S. AP1000 reactor design and to operating nuclear power plants.

08/29/16

Namco Controls Corporation, Elizabethtown, NC, limited scope inspection to assess compliance with selected portions of their quality assurance (QA) and 10 CFR Part 21 programs specifically, as it pertains to Namco's design, qualification, fabrication, testing, commercial-grade-dedication, and manufacturing of safety-related limit switches for operating nuclear plants and AP1000 plants.

06/09/16

Equipos Nucleares, S.A (ENSA), Cantabria, Spain, limited scope inspection to assess compliance with selected portions of their quality assurance (QA) and 10 CFR Part 21 programs as they pertain to the design, fabrication, assembly, and testing of components for NRC regulated facilities.

04/15/16

ASCO Valve, Inc., Aiken, SC, limited scope inspection to assess compliance with selected portions of their quality assurance (QA) and 10 CFR Part 21 programs as they pertain to ASCO design, fabrication, and commercial-grade dedication of safety-related solenoid valves to operating nuclear power plants. In addition, the staff will review the environmental qualifications performed for AP1000 safety-related solenoid valves.

01/15/16

Nova, Nuclear Division, Middleburg Heights, limited scope inspection to assess compliance with selected portions of their quality assurance (QA) and 10 CFR Part 21 programs as they pertain to safety-related components supplied to nuclear power plants.

07/09/15 ABB, Incorporated, Coral Springs, FL, limited scope inspection to assess compliance with selected portions of their quality assurance (QA) and 10 CFR Part 21 programs as they pertain associated with safety-related components supplied to operating nuclear power plants.
07/06/15 Engine Systems Inc. (ESI), Rocky Mount, NC, limited scope inspection to assess compliance with selected portions of their quality assurance (QA) and 10 CFR Part 21 programs specifically as they pertain to ESI's qualification and dedication activities associated with safety-related components supplied to operating nuclear power plants
06/25/15 National Technical Systems, Huntsville, AL, limited scope inspection to assess compliance with selected portions of their quality assurance (QA) and 10 CFR Part 21 programs specifically as they pertain to the ASME QME-1-2007 functional and flow qualification testing of the 8-inch squib valves for the Westinghouse AP1000 design.
05/22/15 Chicago Bridge & Iron Power, Laurens, SC, limited scope inspection to assess compliance with selected portions of their quality assurance (QA) and 10 CFR Part 21 programs, specifically as they pertain to activities related to the fabrication of piping spools for the Westinghouse Electric Company AP1000 reactor design.
05/01/15 Crane Nuclear, Inc., Bolingbrook, IL, limited scope inspection to assess compliance with selected portions of their quality assurance (QA) and 10 CFR Part 21 programs specifically as they pertain to safety-related components supplied to operating nuclear power plants.
04/24/15 Westinghouse Electric Company, Cranberry Township, PA, limited scope inspection to assess compliance with selected portions of their quality assurance (QA) and 10 CFR Part 21 programs as they pertain to the implementation of safety-related activities for U.S. regulated facilities.
11/21/14 Specialty Maintenance and Construction, Inc. (SMCI), Lakeland, FL, limited scope inspection to assess compliance with selected portions of their quality assurance (QA) and 10 CFR Part 21 programs, as they pertain SMCI's implementation of quality activities associated with the fabrication of the remain-in-place steel formwork modules for concrete, in-containment refueling water storage tank wall and reactor vessel cavity modules for the Westinghouse Electric Company's AP1000 reactor design.
11/18/14 Oregon Iron Works, Inc., Clackamas, OR and Vancouver, WA, limited scope inspection to assess compliance with selected portions of their quality assurance (QA) and 10 CFR Part 21 programs, as they pertain to the implementation of safety-related activities for U.S. regulated facilities.
10/24/14 Chicago Bridge & Iron Power, Charlotte, NC, limited scope inspection to assess compliance with selected portions of their quality assurance (QA) and 10 CFR Part 21 programs.
09/09/14 Curtiss Wright Qualtech NP, Huntsville, AL, limited scope inspection to assess compliance with selected portions of their quality assurance (QA) and 10 CFR Part 21 programs
11/08/13 Newport News Industrial (NNI), Newport News, Virginia, limited scope inspection to assess NNIs' compliance with selected portions of their quality assurance (QA) and 10 CFR Part 21 programs as they pertain to activities conducted at their facility related to the design, manufacture, and qualification testing of safety-related components.
10/02/13 Ametek Solidstate Controls, Inc., Columbus, Ohio, limited scope inspection to assess Ametek Solidstate Controls, Inc.'s compliance with selected portions of their quality assurance (QA) and 10 CFR Part 21 programs as they pertain to activities conducted at their facility related to the design, fabrication, assembly, and testing of components for NRC regulated facilities.
10/02/13 Chicago Bridge & Iron (CB&I) (formerly known as B.F. Shaw), Laurens, South Carolina., limited scope inspection to assess CB&I's compliance with selected portions of their quality assurance (QA) and 10 CFR Part 21 programs specifically related to the fabrication of piping for the US AP1000 plants.
08/20/13 Pentair Valves and Controls, Mansfield, MA, limited scope inspection to assess Pentair Valves and Controls' compliance with selected portions of their quality assurance (QA) and 10 CFR Part 21 programs as they pertain to activities conducted at their facility related to the design, manufacture, and qualification testing of safety-related valves.
07/31/13 IBF S.p.A., Piacenza, Italy, limited scope inspection to assess IBF S.p.A.'s compliance with selected portions of their quality assurance (QA) and 10 CFR Part 21 programs as they pertain to activities conducted at their facility related to the fabrication of seamless piping for the reactor coolant loop of the AP1000 plants at the Vogtle, V.C. Summer, and Levy sites.
07/16/13 Babcock & Wilcox Canada Ltd. (BWC), Cambridge, Ontario Canada, limited scope inspection to assess BWC's compliance with selected portions of their quality assurance (QA) and 10 CFR Part 21 programs as they pertain to the design, fabrication, assembly, and testing activities of the Once Through Replacement Steam Generators for the Davis Besse Nuclear Power Station.
04/22/13 Dresser Masoneilan facility in Avon, Massachusetts, limited scope inspection to assess Dresser Masoneilan's compliance with selected portions of their quality assurance (QA) and 10 CFR Part 21 programs specifically related to quality assurance activities associated with the design, fabrication, assembly, and testing of safety-related valves and valve parts for U.S. nuclear power plants.
04/18/13 NuScale Power LLC, Corvallis, Oregon, design certification inspection as it pertains to testing activities conducted at Stern Laboratories, Inc.
03/21/13 Weir Valves & Controls USA Inc., Ipswich, MA, limited scope inspection to assess Weir Valves and Controls' compliance with selected portions of their quality assurance (QA) and 10 CFR Part 21 programs specifically related to the design, fabrication, assembly, and testing activities of components for NRC regulated facilities.
12/07/12 Mangiarotti S.p.A, Monfalcone, Italy, limited scope inspection to assess Mangiarotti's compliance with selected portions of their quality assurance (QA) and 10 CFR Part 21 programs specifically associated with the design, fabrication, assembly, and testing of the accumulators, core make-up tanks, passive residual heat removal heat exchangers, and the pressurizers for the Westinghouse Electric Company AP1000 reactor design.
11/30/12 Mitsubishi Heavy Industries, Ltd. (MHI), Kobe, Japan, limited scope inspection to assess MHI's compliance with selected portions of their quality assurance (QA) and 10 CFR Part 21 programs specifically, the quality assurance program will be reviewed to determine if the preparation and testing of the Full-Scale Mock-up and testing of re-designed anti-vibration bars are adequate and correct and meet the applicable requirements of Appendix B to 10 CFR Part 50, 10 CFR Part 21, and American Society of Mechanical Engineers Code Section III, "Rules for Construction of Nuclear Facility Components."
10/23/12 Curtiss-Wright Flow Control Company, Target Rock Division, Farmingdale, NY, routine limited-scope inspection to assess Curtiss-Wright's compliance with selected portions of their quality assurance (QA) and 10 CFR Part 21 programs.
09/07/12 Wyle Laboratories, Huntsville, Alabama, limited-scope routine inspection to assess Wyle Laboratories' compliance with selected portions of their quality assurance (QA) and 10 CFR Part 21 programs specifically associated with testing services to support environmental qualification of components being supplied as part of the Westinghouse AP1000 reactor design.
07/27/12 National Technical Systems (NTS) facility in Acton, MA, limited-scope routine inspection to assess NTS's compliance with selected portions of their quality assurance (QA) and 10 CFR Part 21 programs specifically associated with the seismic qualification testing of the tension bolt and position switch of the AP1000 design squib valves.
07/02/12 Kinectrics facility in Toronto, Ontario, limited-scope routine inspection to review implementation of Kinectric’s quality assurance (QA) program and 10 CFR Part 21 program, specifically as it pertains to Kinectrics supply of testing services to support environmental qualification of components being supplied as part of the Westinghouse AP1000 reactor design as well as reviewing selected activities in support of testing and dedication of safety related components to the U.S. nuclear operating fleet.
05/17/12 Westinghouse Electric Company (WEC), Cranberry Township, PA., technically-focused, limited scope inspection was to assess WEC's compliance with selected portions of their quality assurance (QA) program and 10 CFR Part 21 program.
09/20/11 Shaw Nuclear Services (SNS), Charlotte, NC, limited-scope inspection of selected portions of SNS's quality assurance (QA) program
09/13/11 Emerson Process Management, Fisher Controls International LLC (Fisher Controls), Marshalltown, IA, inspection of selected portions of Fisher Control's quality assurance (QA) program and 10 CFR Part 21 program
09/01/11 Mitsubishi Heavy Industries, LTD., US-APWR Design Certification Application - Inspection of the implementation of the quality assurance processes and procedures for testing activities performed in support of the US-APWR DC application in accordance with the requirements of Appendix B to 10 CFR Part 50 and 10 CFR Part 21 at the Takasago Research and Development Center in Takasago, Japan.
07/29/11 Continuum Dynamics, INC, (CDI), Ewing, NJ, inspection of selected portions of CDI's quality assurance (QA) program and 10 CFR Part 21 program
07/20/11 CS Innovations, INC, (CSI), Scottsdale, AZ, inspection of selected portions of CSI's quality assurance (QA) program and 10 CFR Part 21 program
07/05/11 Areva NP, INC, Lynchburg, VA, limited-scope inspection of Areva NP's quality assurance (QA) program
04/22/11

Flowserve Limitorque, Lynchburg, VA, inspection of selected portions of Flowserve Limitorque's quality assurance (QA) program and 10 CFR Part 21 program

02/02/11

Mitsubushi Heavy Industries, LTD., US-APWR Design Certification Application - Inspection of the implementation of the quality assurance program to support the US-APWR DC application in accordance with the requirements of Appendix B to 10 CFR Part 50 and 10 CFR Part 21 at the MHI facilities in Kobe, Japan.

01/20/11

GE Hitachi Nuclear Energy, Wilmington, NC, inspection of selected portions of GE Hitachi's quality assurance (QA) program and 10 CFR Part 21 program

10/06/10

Tyco Electronics, Fairview, NC, inspection of selected portions of Tyco's quality assurance (QA) program and 10 CFR Part 21 program

09/29/10

Mangiarotti S.p.A., Sedegliano (UD), Italy, inspection of selected portions of Mangiarotti's quality assurance (QA) program and 10 CFR Part 21 program

05/03/10

Sulzer Pumps (US) Inc., Chattanooga, TN, inspection of selected portions of Sulzer's quality assurance (QA) program and 10 CFR Part 21 program

04/22/10

Shaw Nuclear Services, Charlotte, NC, inspection of selected portions of Shaw's quality assurance (QA) program and 10 CFR Part 21 program

11/16/09

Sumitomo Metal Industries, Ltd., Higashi-Mukojima Amagasaki, Japan, inspection of selected portions of Sumitomo's quality assurance (QA) program and 10 CFR Part 21 program

11/12/09

General Electric Hitachi ESBWR Design Certification Application - Inspection of the radiation shielding calculations and associated codes used in the development of the ESBWR design certification at the GE Hitachi facility in Wilmington, NC.

10/05/09

Detroit Edison Company (DECo) Fermi Unit 3 Combined License Application - Inspection of the implementation of the quality assurance program to support the Fermi Unit 3 COL application in accordance with the requirements of Appendix B to 10 CFR Part 50 and 10 CFR Part 21 at the DECo facilities in Detroit, MI.

06/03/09

Nova Machine Products Inc., Middleburg Heights, OH, inspection of selected portions of Nova's quality assurance (QA) program, and 10 CFR Part 21 program

04/27/09

Dresser Industries Incorporated, Alexandria, LA, inspection of selected portions of Dresser's quality assurance (QA) program, and 10 CFR Part 21 program

03/31/09

CoreStar International Corporation, Irwin, PA, inspection of selected portions of CoreStar's quality assurance (QA) program, and 10 CFR Part 21 program

12/24/08

Westinghouse AP1000 Design Certification Amendment Application - Inspection of the implementation of the quality assurance and Part 21 programs governing the amendment to the AP1000 Design Certification the Westinghouse facility in Monroeville, PA.

12/17/08 Weir Valves & Controls (WVC) USA, Incorporated, Ipswich, MA, inspection of selected portions of WVC's quality assurance (QA) program, and 10 CFR Part 21 program
12/04/08

Enertech, Brea, CA, inspection of selected portions of Enertech's quality assurance (QA) program, and 10 CFR Part 21 program

11/18/08

Energy Steel & Supply Company (ESSC), Lapeer, MI, inspection of selected portions of ESSC's quality assurance (QA) program, and 10 CFR Part 21 program

10/15/08

Babcock and Wilcox (B&W) Nuclear Operations Group Mount Vernon Facility, Mount Vernon, IN, inspection of selected portions of B&W's quality assurance (QA) program, and 10 CFR Part 21 program

10/09/08

Fairbanks Morse Engine, Beloit, WI, inspection of selected portions of Fairbanks Morse's quality assurance (QA) program, and 10 CFR Part 21 program

09/17/08

Spectrum Technologies Utilities Service Division, Schenectady, NY, inspection of selected portions of Spectrum's quality assurance (QA) program, and 10 CFR Part 21 program

07/18/08

Doosan Heavy Industries, Changwon, Korea, inspection of selected portions of Doosan's quality assurance (QA) program, and 10 CFR Part 21 program

  • Vendor Response Letters 1 | 2
  • NRC Closeout Letters 1 | 2
05/27/08

Namco Controls, Inc., Lancaster, SC, inspection of selected portions of Namco's quality assurance (QA) program, and 10 CFR Part 21 program

05/07/08

Areva NP GmbH, Erlangen, Germany, inspection of selected portions of Areva NP GmbH's quality assurance (QA) program, and 10 CFR Part 21 program

12/18/07

Velan Inc., Montreal, Canada, inspection of selected portions of Velan's quality assurance (QA) program, and 10 CFR Part 21 program

08/31/07

Target Rock, Inc., Division of Curtiss-Wright Flow Control Corporation, East Farmingdale, NY, inspection of selected portions of Target Rock's quality assurance (QA) program, and 10 CFR Part 21 program.

  • No Vendor Response Required
05/25/06

Crane Nuclear, Incorporated, Kennesaw, GA, inspection of selected portions of Crane Nuclear's quality assurance (QA) program, and Crane Nuclear's 10 CFR Part 21 program.

01/11/06

General Electric Nuclear Energy, Wilmington, NC, ESBWR quality assurance inspection

To top of page