Application Review Schedule for the Combined License Application for Levy County, Units 1 and 2
The following table summarizes the key milestones in the schedule that the U.S. Nuclear Regulatory Commission (NRC) has established for its review of the application that Progress Energy Florida, Inc. (PEF) submitted to obtain a combined license (COL) for two Westinghouse Advanced Passive 1000 (AP1000) pressurized-water reactors (PWRs) designated as Levy County, Units 1 and 2.
Detailed Review Schedule for COL Application: The schedule for the Westinghouse design certification amendment is currently under review. The design certification amendment schedule will affect the Levy County SCOL combined license schedule for dependent sections such as Advanced SER with No Open Items, ACRS Review and Final SER Issuance. The posted Levy County SCOL schedule does not currently reflect the necessary changes and will be updated after the Westinghouse schedule is revised.
| Key Milestones | Completion Date Actual - A Target - T |
|---|---|
| Application Tendered | 07/30/08 - A |
| Acceptance Review | |
Acceptance Review Start |
08/04/08 - A |
Docketing Decision Letter Issued/Acceptance Review Complete |
10/06/08 - A |
Review Schedule Established/Schedule Letter Issued to Applicant |
02/18/09 - A |
| Safety Review | |
Phase A - Requests for Additional
Information (RAIs) and Supplemental RAIs (Formerly Phase 1) |
03/29/10 - A |
Phase B - Advanced Final safety evaluation
report (SER) without Open Items (Formerly Phase 2) |
09/15/11 - A |
Phase C - ACRS Review of Advanced
Final SER (Formerly Phase 3) |
01/24/12 - A |
Phase D - Final SER (Formerly Phase 4) |
04/12 - T |
| Environmental Review | |
Phase 1 - Environmental impact statement (EIS) scoping summary report issued |
05/28/09 - A |
Phase 2 - Draft EIS issued to EPA |
08/06/10 - A |
Phase 3 - Responses to public comments on draft EIS completed** |
04/27/12 - A |
Phase 4 - Final EIS issued to EPA |
04/27/12 - A |
| Hearing | |
Commission or ASLB hold mandatory hearing |
|
| License | |
Commission decision on issuance of COL application |
|
** NRC staff responses to public comments on the Draft EIS are included in Appendix E of the Final EIS
Information on Federal Register notices for receipt of the application and opportunity to request a hearing or petition to intervene can be found on the Hearing Opportunities page.

