Date Description
08/26/2015

Public Meeting Regarding Watts Bar Nuclear Plant Dual Unit Fire Protection Report Audit Closure

06/27/2015

Operational Readiness Assessment Team (ORAT) Inspection Exit

05/21/2015

04/01/2015, Summary of Category 1 Public Meeting with Tennessee Valley Authority on the Fire Protection Report for Watts Bar Nuclear Plant, Unit 2.

05/21/2015

05/21/2015, Summary of Meeting with Tennessee Valley Authority Regarding the Watts Bar Nuclear Plant, Unit 2 Operating License Application (Open Item Related to General Design Criterion 5 and Reactor Oversight Process Transition).

03/26/2015

Public Meeting with TVA on WBN 2 Senior Management Meeting 

03/26/2015

Public Meeting with TVA on WBN 2 End of Cycle Assessment

03/11/2015

March 11, 2015, Summary of Meeting with Tennessee Valley Authority Regarding the Watts Bar Nuclear Plant, Unit 2 Operating License Application (Emergency Preparedness and Environmental Protection Plan).

03/04/2015

March 4 Public Meeting with TVA on the ROP Transition Plan

01/14/2015

January 14, 2015 WRAG meeting with  TVA and WRAG

12/18/2014

December 18, 2014, Meeting with Tennessee Valley Authority Regarding the Watts Bar Nuclear Plant, Unit 2 Operating License Application (Licensing Milestones).

11/12/2014

November 12, 2014, Summary of Meeting with Tennessee Valley Authority Regarding the Watts Bar Nuclear Plant, Unit 2 Operating License Application (Fire Protection).

10/01/2014

Summary of October 1 2014 Watts Bar 2 Public Meeting

09/24/2014

September 24, 2014, Summary of Meeting with Tennessee Valley Authority Regarding the Watts Bar Nuclear Plant, Unit 2, Response to Order EA 12-049 on Mitigating Strategies.

09/24/2014

Summary of September 24, 2014, Teleconference with TVA Regarding the License Amendment Request on Hydrology for Watts Bar Nuclear Plant Unit 2

08/28/2014

08/28/2014 Summary of Meeting With Tennessee Valley Authority Regarding The Watts Bar Nuclear Plant, Unit 2 Operating License Application.

08/18/2014

Summary of the Public Meeting to Disuss Aspects of TVA's Response to the 2009 Confirmatory Order

07/22/2014

Summary of Meeting with TVA Regarding the Watts Bar Nuclear Plant, Unit 2, Operating License Application

07/16/2014

Summary of Meeting with TVA Regarding the Watts Bar Nuclear Plant, Unit 2, Operating License Application

07/1/2014

Summary of July 1 Category 1 Public Meeting with TVA to Discuss Seismic Hazard Reevaluations Associated with Implementation of Japan Lessons-Learned Near-Term Task Force Recommendation 2.1

06/26/2014

Summary of Meeting with TVA Regarding the Watts Bar Nuclear Plant, Unit 2, Operating License

06/16/2014

Summary of Meeting with TVA Regarding Watts Bar Nuclear Plant, Unit 2, Operating License Application

04/24/2014

Summary of 04/24/2014 Meeting with TVA Regarding Watts Bar Nuclear Plant, Unit 2, Open Items for Licensing

04/09/2014

Summary of Category 3 Public Meeting with TVA to Discuss Annual Assessment of the Watts Bar Nuclear Plant Unit 2 Construction Project

04/09/2014

Summary of Category 1 Public Meeting with TVA to Discuss the Status of the  Watts Bar Nuclear Plant, Unit 2, Construction Project

01/28/2014

Summary of Meeting with TVA Regarding Watts Bar Nuclear Plant, Unit 2, Open Items for Licensing

01/28/2014

Summary of Public Meeting with TVA to Discuss Fire Protection Program at Watts Bar

01/08/2014

Summary of Public Meeting with TVA to Discuss Status of Construction and Licensing of Watts Bar Nuclear Plant, Unit 2

08/20/2013

Summary of Public Meeting Re. Hydrology License Amendment Requests

06/28/2013

Summary of Meeting with TVA Regarding Watts Bar Nuclear Plant, Unit 2

04/17/2013

Summary of Meeting to Discuss the Annual Assessment of the Watts Bar Nuclear Construction Project

04/02/2013

Summary of Meeting with TVA to Discuss Commercial Grade Dedication Program

05/22/2012

Summary of Meeting with TVA Regarding Construction Project Status

04/12/2012

End of Cycle Meeting Summary

02/02/2012

Summary of Meeting with TVA Regarding Review of FSAR Submittals

12/21/2011

Summary of Meeting with TVA Regarding Review of FSAR Section 9.5.1 Fire Protection

12/08/2011

Summary of Meeting to Obtain Comments Regarding Draft Supplement to the Final Environmental Statement

11/18/2011

Summary of Teleconference Meeting with TVA Regarding Review of FSAR Section 7 I&C

11/16/2011

Summary of Meeting with TVA Regarding Review of FSAR Section 9.5.1 Fire Protection

11/08/2011

Summary of Meeting with TVA Regarding Construction Project Status

08/31/2011

Summary of Meeting with TVA Regarding Review of FSAR Section 9.5.1 Fire Protection and Open Items in the Safety Evaluation Report

08/24/2011

Summary of Meeting with TVA Regarding Construction Project Status

06/30/2011,
07/12/2011,
07/28/2011

Summary of Meeting with TVA Regarding Construction Project Status

06/20/2011

Summary of Meeting with TVA Regarding Construction Project Status

06/2011

Summary of Teleconference Meetings with TVA During June 2011 Regarding Review of FSAR Section 7 I&C

05/10/2011

Summary of Meeting with TVA from May 10, 2011 through May 12, 2011, Regarding Review of FSAR Submittals

05/2011

Summary of Teleconference Meetings with TVA During May 2011 Regarding Review of FSAR Section 7 I&C

04/28/2011

End of Cycle Meeting Summary

04/2011

Summary of Teleconference Meetings with TVA During April 2011 Regarding Review of FSAR Section 7 I&C

03/29/2011

Summary of Meeting with TVA Regarding Review of FSAR Section 9.5.1 Fire Protection

03/2011

Summary of Teleconference Meetings with TVA During March 2011 Regarding Review of FSAR Section 7 I&C

02/14/2011

Summary of Meeting with TVA Regarding Project Schedule

02/2011

Summary of Teleconference Meetings with TVA During February 2011 Regarding Review of FSAR Section 7 I&C

01/24/2011,
02/03/2011,
02/15/2011

Summary of Meetings with TVA Regarding Review of FSAR Section 9.5.1 Fire Protection

01/2011

Summary of Teleconference Meetings with TVA During January 2011 Regarding Review of FSAR Section 7 I&C

12/2010

Summary of Teleconference Meetings with TVA During December 2010 Regarding Review of FSAR Section 7 I&C

11/29/2010

Summary of Meeting with TVA Regarding Emergency Action Level Plans for TVA Nuclear Plants

11/16/2010

Summary of Meeting with TVA Regarding Integrated Safeguards Testing

11/10/2010

Summary of Teleconference Meeting with TVA Regarding Review of FSAR Section 7 I&C

11/04/2010

Summary of Meeting with TVA Regarding Review of FSAR Section 7 I&C

11/03/2010

Summary of Meeting with TVA Regarding Review of FSAR Section 9.5.1 Fire Protection

10/12/2010

Summary of Meeting with TVA Regarding Review of FSAR Section 9.5.1 Fire Protection

10/12/2010

Summary of Meeting with TVA Regarding Review of FSAR Section 7 I&C

09/15/2010

Summary of Meeting with TVA Regarding Review of FSAR Section 7 I&C

08/03/2010 Summary of Meeting with TVA Regarding FSAR Review
07/27/2010 Summary of Teleconference with TVA Regarding Status of I&C Review
05/11/2010

Summary of Teleconference with TVA Regarding Status of I&C Review

04/20/2010

End of Cycle Meeting Summary

10/06/2009

Summary of the Public Meeting to Obtain Comments Regarding Environmental Scoping

08/06/2009

Summary of the Public Meeting with TVA Regarding the Construction Refurbishment Plan

07/09/2009

Summary of the Public Meeting with TVA Regarding the Scope of Future Submittals in the Balance of Plant Area

06/25/2009

Summary of the Public Meeting with TVA Regarding the Scope of Future Submittals in the Mechanical Area

04/02/2009

Summary of 03/17/2009, Meeting With Tennessee Valley Authority (TVA), Regarding Corrective Action Program (CAP) For Cable Issues at Watts Bar Unit 2

02/23/2009

Summary of December 11, 2008, Meeting with Tennessee Valley Authority on Status of Construction and Licensing Activities

03/12/2007

Meeting with the Tennessee Valley Authority Regarding the Possible Resumption of Construction and Licensing for the Watts Bar Nuclear Plant Unit 2

12/04/2007

Public outreach meeting in site vicinity

To top of page