U.S. Nuclear Regulatory Commission
Technical Assistance Request, Yuma Proving Ground, Department of the Army, Statement of Intent for a Government Licensee
HPPOS-269 PDR-9306090321
Title: Technical Assistance Request, Yuma Proving Ground,
Department of the Army, Statement of Intent for a
Government Licensee
See the memorandum from J. E. Glenn to R. J. Pate dated
August 12, 1991, and the memorandum from J. H. Austin to J.
E. Glenn dated August 6, 1992. These memos respond to the
TAR from Region V, dated July 15, 1991, regarding the
Department of the Army Statement of Intent related to the
YUMA Proving Ground. NMSS has reviewed the financial
assurance and revised cost estimate documents in a
Statement of Intent as cited in NUREG-1337, Rev. 1, page
A-6. The cost estimate and the assumptions used in the
cost details are reasonable. As a matter of information to
the Regional licensing staff, we are enclosing a November
21, 1990 memorandum sent to the Regions which included
recommended wording for a statement of intent for a
government licensee which may be used by Regions in future
cases.
Government licensees required to submit financial assurance
under the decommissioning rule may use a statement of
intent as their financial assurance mechanism. Most
government licensees required to make submittals are
expected to use this option. However, no recommended
wording for a statement of intent was provided in the
standard format and content guidance originally published
as NUREG-1336 and later issued as Regulatory Guide 3.66. We
are enclosing recommended wording to provide an example of
an acceptable statement of intent. This recommended
wording will be incorporated into the standard review plan
for license applications (FC 90-2) until it can be added to
Regulatory Guide 3.66.
In addition to the wording for a statement of intent,
questions have been raised concerning what financial
assurance is required from the Navy and Air Force master
materials licensees. The Navy and Air Force have made
preliminary financial assurance submittals to comply with
the July 27, 1990 submittal deadline. However, the
decommissioning regulations also require that the Navy and
Air Force each submit a decommissioning funding plan with
site-specific cost estimates at renewal. However, the lack
of a renewal date leaves the due date for submittal of a
complete funding plan in question.
The intent of the rule is that the Navy and Air Force
should submit plans within the next five years which assure
a specified level of funding for decommissioning their
facilities. A reasonable approach would be for them to
systematically review the activities authorized at each
site, and perform a site-specific cost estimate for each
site which would require decommissioning financial
assurance if licensed separately. For the other activities
and sites which do not reach this threshold, a general
combined cost estimate would be acceptable. A total cost
should be determined and a statement of intent or other
mechanism for that dollar amount should be provided.
This is an especially opportune time for the military to be
considering decommissioning plans because they recently
received the GAO report issued in March 1990 entitled, "The
Military Would Benefit From a Comprehensive Waste Disposal
Program," which was circulated to the regions in May 1990.
We request that Regions II and IV approach the Navy and the
Air Force, respectively, to discuss our expectations that
they submit decommissioning funding plans with
site-specific cost estimates within the next five years.
Regulatory references: 10 CFR 30.35, 10 CFR 40.36, 10 CFR
70.25, Regulatory Guide 3.66
Subject codes: 5.8, 11.2, 12.13
Applicability: Byproduct, Source, and Special Nuclear
Materials

