U.S. Nuclear Regulatory Commission
Generic Guidance on Preplanned Alternative Method for High Range Noble Gas Monitoring.
HPPOS-039 PDR-9111210178
Title: Generic Guidance on Preplanned Alternative Method
for High Range Noble Gas Monitoring.
See the memorandum from E. L. Jordan to R. A. Scarano dated
October 22, 1985. This memo states that preplanned
alternate methods of determining noble gas releases as
backups to high range noble gas monitors need not be
continuous monitors. Local radiation survey instruments or
meters on the effluent line are an acceptable preplanned
alternate method.
A request was made for generic guidance during a review of
the proposed alternative method (PPAM) for determining
noble gas releases proposed by Palo Verde Nuclear
Generating Station (PVNGS). The PPAM was required by PVNCS
Technical Specifications to be used as a backup for the
High Range Noble Gas (HRNG) monitors required by
NUREG-0737, Item II.F.1. It was Region V's position that a
backup to the HRNG monitors must be a continuous monitor
with a comparable range. However, based on discussions
with cognizant members of NRR's staff, it was found that
the PPAM does not necessarily have to be a continuous
monitor.
NRR also stated that the current form of the Technical
Specifications began with a memorandum from D. G. Eisenhut
to T. E. Murley dated October 20, 1980. This memo proposed
that provisions for monitoring noble gas in Standard
Technical Specifications be relaxed. Prior to this time,
the action statement for an inoperable HRNG monitor
required a plant shutdown. No technical basis could be
found for the shutdown requirements; therefore, the
provision for initiating a PPAM was substituted in the
action statement. The intent of the revised action
statement was to ensure that the licensee devised a
feasible method to monitor noble gases as a backup to the
HRNG monitors, but not to require redundant HRNG monitors.
Prior to the issuance of NUREG-0737, interim requirements
for monitoring high range noble gases were specified in
NUREG-0578. During its review of these interim measures,
NRR accepted a method of HRNG monitoring if the licensee
could demonstrate that it was adequate to characterize the
radioactive release without exceeding the dose limits of
GDC-19. Many licensees found that the simplest method was
to install a local radiation survey instrument or meter on
the effluent line. This method was preferable to grab
sampling since it is less dose intensive and easier to
shield. For many plants, the interim system installed to
meet the requirements of NUREG-0578 now serves as the PPAM.
However, taking the position that this is the only
acceptable proposal is a significant deviation from the
position established by NRR.
Regulatory references: NUREG-0737, Technical Specifications
Subject codes: 7.3, 9.1, 12.16
Applicability: Reactors

