U.S. Nuclear Regulatory Commission
Monitoring of Radioactive Release Via Storm Drains
HPPOS-007 PDR-9111210092
Title: Monitoring of Radioactive Release Via Storm Drains
See the memorandum from W. J. Dircks to Commissioner
Bradford dated August 28, 1981. This memo states that a
blanket requirement for monitoring storm drains (yard
drains) from every power reactor is unwarranted from a
safety standpoint. The information was also provided to J.
H. Joyner (and others) by L. J. Cunningham in the form of a
memorandum dated September 10, 1981.
Based on an unmonitored release of radioactive water on
July 30, 1981, at the Northern States Power Company's
Monticello Plant and similar occurrences at Millstone, Unit
1 (June 21, 1981) and at the Japanese Tsuruga plant, it was
asked if there were technical reasons for not continuously
monitoring storm drains for radioactivity.
In the Monticello Plant incident, an unreviewed and
improper action by a plant engineer resulted in radioactive
water being used in the cement solidification of
radioactive wastes at a newly-installed portable
solidification system located in the radwaste shipping
building. The building was not designed for this purpose
and did not have floor drains or curbs to prevent spilled
water from escaping. The incident occurred when the
responsible engineer improperly and inadvertently used
slightly radioactive water from the reactor's condensate
storage tank by connecting a rubber hose secured by a hose
clamp to the piping of the concrete mixing system. The
hose came loose and an estimated 2,000 gallons of
radioactive water spilled onto the concrete floor of the
radwaste storage building. The water ran down the sloping
floor, under two closed overhead garage-type doors, and
into the storm drain system.
An estimated 100 gallons of water, contaminated with
4.5x10-7 micro-Ci/ml I-131 and 1.4x10-6 micro-Ci/ml I-133,
entered the Mississippi River at the storm drain outfall.
At the point of release, the isotope concentrations were
approximately 300% of the "maximum permissible
concentration" described in 10 CFR 20 (§§20.1-20.601),
Appendix B, Table II, Column 2, but dilution and dispersion
by the Mississippi River was assumed to have resulted in
essentially instantaneous reduction to non-detectable
concentrations with essentially zero environmental
radiation-dose impact. The remainder of the water entered
the soil or was trapped in the storm drain ditches.
NRR replied that no insurmountable technical reasons
existed with regard to the monitoring of storm drains for
radioactivity. However, practical difficulties in the
automatic sampling or extraction of material for
radioactivity analysis, as well as practical problems of
volumetric measurements from the highly variable stream
flow rates would need to be resolved if the total release
were to be determined. In addition, if it is assumed that
each nuclear power plant is serviced by a single storm
drain system (also called yard drains), the initial cost of
the installation of monitoring equipment per plant would be
approximately 200 to 500 thousand dollars and that the
annual operation and maintenance costs would be 20 to 50
thousand dollars.
Because of the difficulties in monitoring radioactive
discharge into storm sewer drains, the associated costs for
installation and operation, the general knowledge of past
experiences with this particular type of unmonitored
release from reactor operations, and the small potential
effect on public health, it was the opinion of the EDO that
requirements for monitoring storm sewer drains were
unwarranted.
Regulatory references: 10 CFR 20.201, 10 CFR 20.1501,
Technical Specifications
Subject codes: 7.3, 7.4, 9.2
Applicability: Reactors

