IP | Inspection Procedures | ||||||
IP | 35007 | Quality Assurance Program Implementation During Construction and Pre-Construction Activities | 02/09/22 | 22-003 | .docx | ||
IP | 35017 | Quality Assurance Implementation Inspection | 12/10/20 | 20-070 | .docx | ||
IP | 35034 | Design Certification Testing Inspection | 03/23/20 | 20-017 | .doc | ||
IP | 35101 | QA Program Implementation Inspection for Operational Programs | 12/29/21 | 21-041 | .docx | ||
IP | 35710 | Quality Assurance Inspection of Safety-Related Software Used in for Digital Instrumentation and Control Nuclear Applications | 04/18/24 | 24-011 | .docx | ||
IP | 36100 | Inspection of 10 CFR Part 21 and Programs for Reporting Defects and Noncompliance | 02/10/23 | 23-003 | .docx | ||
IP | 36100.01 | Inspection of 10 CFR 50.55(e) Programs for Reporting Defects and Noncompliance During Construction | 03/08/23 | 23-007 | .docx | ||
IP | 36302 | Part 52, Operational Staffing | 08/19/08 | 08-024 | .doc | ||
IP | 37060 | 10 CFR 50.69 Risk–Informed Categorization and Treatment of Structures, Systems, and Components Inspection | 10/18/22 | 22-023 | .docx | FY2023-02 | |
IP | 37700 | Design Changes and Modifications | 09/17/90 | R | 90-010 | ||
IP | 37801 | Decommissioning Safety Reviews, Design Changes, And Modifications | 06/27/25 | 25-022 | .docx | ||
IP | 37804 | Aircraft Impact Assessment | 03/23/20 | 20-017 | .docx | ||
IP | 37805 | Engineering Design Verification Inspections | 04/08/20 | 20-020 | .docx | ||
IP | 40002 | Inspections to Review Allegations | 06/28/02 | 02-024 | .doc | ||
IP | 40100 | Independent Safety Culture Assessment Follow-up | 02/12/25 | 25-002 | .docx | ||
IP | 40600 | Licensee Program for Managing Inspections, Tests, Analyses, and Acceptance Criteria (ITAAC) Closure | 05/29/20 | 20-025 | .docx | ||
IP | 40801 | Problem Identification and Resolution at Permanently Shutdown Reactors | 10/05/20 | 20-046 | .docx | ||
IP | 40802 | Financial Assurance at Decommissioning Power Reactors | 06/27/25 | 25-022 | .docx | ||
IP | 41500 | Training and Qualification Effectiveness | 06/13/95 | R | 95-007 | ||
IP | 41501 | Part 52, Review of Training and Qualification Programs | 06/04/19 | 19-018 | .docx | ||
IP | 41502 | Nuclear Power Plant Simulation Facilities | 10/16/12 | 12-024 | .docx | ||
IP | 42001 | Emergency Operating Procedures | 06/28/91 | R | 91-009 | ||
IP | 42401 | Part 52, Plant Procedures | 10/27/10 | 10-022 | .doc | ||
IP | 42453 | Part 52, Operating Procedures Inspection | 08/19/08 | 08-024 | .doc | ||
IP | 42454 | Part 52, Emergency Operating Procedures | 09/09/13 | 13-020 | .docx | ||
IP | 42700 | Plant Procedures | 11/15/95 | R | 95-015 | ||
IP | 43002 | Routine Inspections of Nuclear Vendors | 02/10/23 | 23-003 | .docx | ||
IP | 43003 | Reactive Inspections of Nuclear Vendors | 04/08/20 | 20-020 | .docx | ||
IP | 43004 | Inspection of Commercial-Grade Dedication Programs | 02/10/23 | 23-003 | .docx | ||
IP | 43005 | NRC Oversight of Third-Party Organizations Implementing Quality Assurance Requirements | 10/07/24 | 24-026 | .docx | ||
IP | 43006 | Inspection of the Implementation of Mitigation Strategies Order Regulating the Use of National SAFER Response Centers | 06/16/22 | 22-013 | .docx | ||
IP | 45052 | Review of Geotechnical and Site Characterization Activities | 04/05/22 | 22-006 | .docx | ||
IP | 49001 | Inspection of Erosion/Corrosion Monitoring Programs | 12/11/98 | R | 98-019 | ||
IP | 50001 | Steam Generator Replacement Inspection | 02/04/25 | 25-001 | .docx | ||
IP | 50002 | Steam Generators | 12/31/96 | R | 96-024 | ||
IP | 50003 | Pressurizer Replacement Inspection | 02/04/25 | 25-001 | .docx | ||
IP | 50054 | Reactor Vessel Material Surveillance Program | 12/04/08 | 08-034 | .doc | ||
IP | 51080 | Part 52 Environmental Qualification (EQ) Program for Electrical and Mechanical Equipment | 06/26/17 | 17-013 | .docx | ||
IP | 52003 | Digital Instrumentation And Control Modification Inspection | 07/09/21 | 21-023 | .docx | ||
IP | 55050 | Nuclear Welding General Inspection Procedure | 06/20/83 | R | 83-006 | ||
IP | 55100 | Structural Welding General Inspection Procedure | 06/20/83 | R | 83-006 | ||
IP | 56700 | Calibration | 03/23/05 | R | 05-008 | .doc | |
IP | 57050 | Visual Testing Examination | 03/09/99 | R | 99-003 | ||
IP | 57060 | Liquid Penetrant Testing Examination | 03/09/99 | R | 99-003 | ||
IP | 57070 | Magnetic Particle Testing Examination | 03/09/99 | R | 99-003 | ||
IP | 57080 | Ultrasonic Testing Examination | 03/09/99 | R | 99-003 | ||
IP | 57090 | Nondestructive Examination Procedure Radiographic Examination Procedure Review/Work Observation/Record Review | 06/14/93 | R | 93-005 | ||
IP | 60705 | Preparation for Refueling | 07/27/95 | R | 95-009 | ||
IP | 60710 | Refueling Activities | 07/27/95 | R | 95-009 | ||
IP | 60715 | Spent Fuel Pool Safety at Operating Reactors | 09/16/20 | 20-043 | .docx | ||
IP | 60801 | Decommissioning Spent Fuel Pool Maintenance, Surveillance, and Safety | 06/27/25 | 25-022 | .docx | ||
IP | 60845 | Operation of Inter-Unit Fuel Transfer Canister and Cask System | 05/16/19 | 19-015 | .docx | ||
IP | 60851 | Design Control of ISFSI Components | 05/27/25 | 25-013 | .docx | ||
IP | 60852 | ISFSI Component Fabrication by Outside Fabricators | 05/27/25 | 25-013 | .docx | ||
IP | 60853 | Onsite Fabrication of Components and Construction of an Independent Spent Fuel Storage Installation | 05/27/25 | 25-013 | .docx | ||
IP | 60854 | Preoperational Testing of an Independent Spent Fuel Storage Installation | 05/27/25 | 25-013 | .docx | ||
IP | 60855 | Operation of An Independent Spent Fuel Storage Installation | 05/27/25 | 25-013 | .docx | ||
IP | 60856 | Review of 10 CFR 72.212(b) Evaluations | 05/27/25 | 25-013 | .docx | ||
IP | 60857 | Review of 10 CFR 72.48 Evaluations | 10/20/20 | 20-052 | .docx | ||
IP | 60858 | Away-From-Reactor Independent Spent Fuel Storage Installation Inspection Guidance | 05/27/25 | 25-013 | .docx | ||
IP | 60859 | Independent Spent Fuel Storage Installation (ISFSI) License Renewal Inspection | 09/11/24 | 24-025 | .docx | ||
IP | 61705 | Calibration of Nuclear Instrumentation Systems | 05/12/86 | R | 86-025 | ||
IP | 61706 | Core Thermal PowerEvaluation | 07/14/86 | R | 86-036 | ||
IP | 61707 | Determination of Reactor Shutdown Margin | 10/11/85 | R | 85-031 | ||
IP | 61708 | Isothermal and ModeratorTemperature CoefficientDeterminations | 10/11/85 | R | 85-031 | ||
IP | 61709 | Total Power Coefficient of Reactivity at Pressurized Water Reactors | 07/14/86 | R | 86-036 | ||
IP | 61710 | Control Rod Worth Measurements | 10/11/85 | R | 85-031 | ||
IP | 61715 | Verification of Containment Integrity | 12/23/86 | R | 86-060 | ||
IP | 61720 | Containment Local Leak Rate Testing | 10/03/85 | R | 85-030 | ||
IP | 61726 | Surveillance Observations | 06/24/98 | R | 98-010 | ||
IP | 61728 | Independent Measurement of RCS Leak Rates for a PWR | 01/01/84 | R | 84-002 | ||
IP | 62002 | Inspection of Structures, Passive Components, and Civil Engineering Features at Nuclear Power Plants | 12/31/96 | R | 96-024 | ||
IP | 62003 | Inspection of Steel and Concrete Containment Structures at Nuclear Power Plants | 06/11/97 | R | 97-008 | ||
IP | 62700 | Maintenance Implementation | 04/04/00 | R | 00-005 | ||
IP | 62706 | Maintenance Rule | 12/13/00 | R | 00-028 | .doc | |
IP | 62708 | Motor-Operated Valve Capability | 07/16/20 | 20-033 | .docx | ||
IP | 62709 | Configuration Risk Assessment and Risk Management Process | 12/28/00 | R | 00-029 | .doc | |
IP | 62710 | Power-Operated Gate Valve Pressure Locking and Thermal Binding | 04/30/10 | R | 10-013 | .doc | |
IP | 62712 | Part 52, Maintenance Rule | 08/13/13 | R | 13-017 | .docx | |
IP | 64704 | Decommissioning Fire Protection Program | 06/27/25 | 25-022 | .docx | ||
IP | 64705 | Part 52, Fire Protection Operational Program | 06/04/19 | 19-018 | .docx | ||
IP | 65001 | Inspections of Inspections, Tests, Analyses, and Acceptance Criteria (ITAAC) Related Work | 08/13/13 | 13-017 | .docx | ||
IP | 65001.01 | Inspection of ITAAC-Related Foundations & Buildings | 04/18/14 | 14-010 | .docx | ||
IP | 65001.02 | Inspection of ITAAC-Related Installation of Structural Concrete | 11/22/11 | 11-037 | .docx | ||
IP | 65001.03 | Inspection of ITAAC-Related Installation of Piping | 08/19/08 | 08-024 | .doc | ||
IP | 65001.04 | Inspection of ITAAC-Related Installation of Pipe Supports and Restraints | 08/13/14 | 14-018 | .docx | ||
IP | 65001.05 | Inspection of ITAAC-Related Installation of Reactor Pressure Vessel and Internals | 08/19/08 | 08-024 | .doc | ||
IP | 65001.06 | Inspection of ITAAC-Related Installation of Mechanical Components | 01/27/15 | 15-001 | .docx | ||
IP | 65001.07 | Inspection of ITAAC-Related Installation of Valves | 07/29/08 | 08-021 | .doc | ||
IP | 65001.08 | Inspection of ITAAC-Related Installation of Electric Components and Systems | 08/19/08 | 08-024 | .doc | ||
IP | 65001.09 | Inspection of ITAAC-Related Installation of Electric and Fiber Optic Cable | 08/05/09 | 09-019 | .doc | ||
IP | 65001.10 | Inspection of ITAAC-Related Installation of Instrument Components and Systems | 10/20/08 | 08-029 | .doc | ||
IP | 65001.11 | Construction Inspection Program Inspection of ITAAC-Related Containment Integrity and Containment Penetrations | 08/19/08 | 08-024 | .doc | ||
IP | 65001.11A | Part 52, Containment Structural Integrity Test | 12/20/19 | 19-041 | .docx | ||
IP | 65001.12 | Inspection of ITAAC-Related Installation of Heating, Ventilating, and Air Conditioning Systems | 07/29/08 | 08-021 | .doc | ||
IP | 65001.13 | Inspection of ITAAC-Related Installation of Load Handling Equipment and Fuel Racks | 08/05/09 | 09-019 | .doc | ||
IP | 65001.14 | Inspection of ITAAC-Related Installation of Complex Systems with Multiple Components | 06/24/15 | 15-012 | .docx | ||
IP | 65001.15 |
Inspection of ITAAC-Related Installation of Fire Protection Equipment |
07/01/08 | 08-019 | .doc | ||
IP | 65001.16 | Inspection of ITAAC-Related Engineering | 06/20/14 | 14-013 | .docx | ||
IP | 65001.17 OUO-SRI |
Inspection of ITAAC-Related Security Structures, Systems, and Components | 09/30/16 | 16-024 | |||
IP | 65001.18 | Inspection of Emergency Planning ITAAC | 10/30/08 | 08-030 | .doc | ||
IP | 65001.19 | Inspection Of Installation of ITAAC-Related Radiation Monitoring Components And Systems | 10/20/08 | 08-029 | .doc | ||
IP | 65001.20 | Inspection of Safety-Related Piping Deisgn Acceptance Criteria (DAC)-Related ITAAC | 06/02/11 | 11-009 | .docx | ||
IP | 65001.21 | Inspection of Pipe Rupture Hazards Analyses (Inside and Outside Containment) Design Acceptance Criteria (DAC) – Related ITAAC | 11/07/11 | 11-029 | .docx | ||
IP | 65001.22 | Inspection of Digital Instrumentation and Control (DI&C) System/Software Design Acceptance Criteria (DAC) – Related to ITAAC | 12/19/11 | 11-041 | .docx | ||
IP | 65001.23 | Inspection of Human Factors Engineering Verification and Validation ITAAC | 12/22/14 | 14-031 | .docx | ||
IP | 65001.A | Inspection of the As-Built Attributes for Structures, Systems, and Components (SSCs) Associated with ITAAC | 09/25/13 | 13-023 | .docx | ||
IP | 65001.B | Inspection of the ITAAC-Related Welding and Nondestructive Examination Programs | 11/04/19 | 19-034 | .docx | ||
IP | 65001.C | Inspection of the ITAAC-Related Construction Test Program | 04/18/14 | 14-010 | .docx | ||
IP | 65001.D | Inspection of the ITAAC-Related Operational Testing Program | 05/09/14 | 14-011 | .docx | ||
IP | 65001.E | Inspection of the ITAAC-Related Qualification Program | 06/20/14 | 14-013 | .docx | ||
IP | 65001.F | Inspection of the ITAAC-Related Design and Fabrication Requirements | 09/20/13 | 13-022 | .docx | ||
IP | 69001 | Class II Research and Test Reactors | 02/03/04 | 04-004 | .doc | ||
IP | 69002 | Class III Research and Test Reactors | 02/03/04 | 04-004 | .doc | ||
IP | 69003 | Class I Research and Test Reactor Operator Licenses, Requalification, and Medical Examinations | 02/03/04 | 04-004 | .doc | ||
IP | 69004 | Class I Research and Test Reactor Effluent and Environmental Monitoring | 02/03/04 | 04-004 | .doc | ||
IP | 69005 | Class I Research and Test Reactor Experiments | 02/03/04 | 04-004 | .doc | ||
IP | 69006 | Class I Research and Test Reactors Organization and Operations and Maintenance Activities | 02/03/04 | 04-004 | .doc | ||
IP | 69007 | Class I Research and Test Reactor Review and Audit and Design Change Functions | 02/03/04 | 04-004 | .doc | ||
IP | 69008 | Class I Research and Test Reactor Procedures | 02/03/04 | 04-004 | .doc | ||
IP | 69009 | Class I Research and Test Reactor Fuel Movement | 02/03/04 | 04-004 | .doc | ||
IP | 69010 | Class I Research and Test Reactor Surveillance | 02/03/04 | 04-004 | .doc | ||
IP | 69011 | Class I Research and Test Reactor Emergency Preparedness | 02/03/04 | 04-004 | .doc | ||
IP | 69012 | Class I Research and Test Reactors Radiation Protection | 02/03/04 | 04-004 | .doc | ||
IP | 69013 | Research and Test Reactor Decommissioning | 02/03/04 | 04-004 | .doc | ||
IP | 69020 | Inspections of Safety-Related Items (and Services) During Construction of Non-Power Production and Utilization Facilities | 03/25/25 | 25-005 | .docx | ||
IP | 69020.A | Inspection of Foundations and Buildings at Non-Power Production and Utilization Facilities | 03/25/25 | 25-005 | .docx | ||
IP | 69020.B | Inspection of Structural Concrete at Non-Power Production and Utilization Facilities | 03/25/25 | 25-005 | .docx | ||
IP | 69020.C | Inspection of Structural Steel and Supports at Non-Power Production and Utilization Facilities | 03/25/25 | 25-005 | .docx | ||
IP | 69020.D | Inspection of Piping at Non-Power Production and Utilization Facilities | 03/25/25 | 25-005 | .docx | ||
IP | 69020.E | Inspection of Piping Supports and Restraints at Non-Power Production and Utilization Facilities | 03/25/25 | 25-005 | .docx | ||
IP | 69020.F | Inspection of Mechanical Components at Non-Power Production and Utilization Facilities | 03/25/25 | 25-005 | .docx | ||
IP | 69020.G | Inspection of Electrical Cable at Non-Power Production and Utilization Facilities | 03/25/25 | 25-005 | .docx | ||
IP | 69020.H | Inspection of Electrical Components and Systems at Non-Power Production and Utilization Facilities | 03/25/25 | 25-005 | .docx | ||
IP | 69020.I | Inspection of Ventilation and Confinement Systems at Non-Power Production and Utilization Facilities | 03/25/25 | 25-005 | .docx | ||
IP | 69020.J | Inspection of Instrumentation and Control Systems at Non-Power Production and Utilization Facilities | 03/25/25 | 25-005 | .docx | ||
IP | 69020.K | Inspection of Safety Significant Welding at Non-Power Production and Utilization Facilities | 03/25/25 | 25-005 | .docx | ||
IP | 69020.L | Inspection of Fire Protection Systems Under Construction at Non-Power Production and Utilization Facilities | 03/25/25 | 25-005 | .docx | ||
IP | 69020.M | Inspection of Digital Instrumentation and Control (DI&C) System/Software Design at Non-Power Production and Utilization Facilities | 03/25/25 | 25-005 | .docx | ||
IP | 69021 | Inspection of Quality Assurance Program Implementation During Construction of Non-Power Production and Utilization Facilities | 03/25/25 | 25-005 | .docx | ||
IP | 69022 | Inspections of Operational Readiness During Construction of Non-Power Production and Utilization Facilities | 03/25/25 | 25-005 | .docx | ||
IP | 70307 | Containment Integrated Leak Rate Test Procedure Review | 03/07/86 | R | 86-013 | ||
IP | 70313 | Containment Integrated Leak Rate Test Surveillance | 10/03/85 | R | 85-036 | ||
IP | 70323 | Containment Leak Rate Test Results Evaluation | 10/03/85 | R | 85-030 | ||
IP | 70367 | Part 52, Inspection of Preoperational Test Program | 10/20/20 | 20-052 | .docx | ||
IP | 70368 | Part 52, Containment Leak Rate Testing Program (Programmatic) | 06/26/17 | 17-013 | .docx | ||
IP | 70702 | Part 52, Inspection of Preoperational Test Performance | 12/06/17 | 17-028 | .docx | ||
IP | 71002 | License Renewal Inspection | 06/26/23 | 23-018 | .docx | ||
IP | 71003 | Post-Approval Site Inspection For License Renewal | 08/11/23 | 23-023 | .docx | ||
IP | 71004 | Power Uprate | 02/09/22 | 22-003 | .docx | ||
IP | 71007 | Reactor Vessel Head Replacement Inspection | 02/04/25 | 25-001 | .docx | ||
IP | 71013 | Site Inspection for Plants with a Timely Renewal Application | 06/26/23 | 23-018 | .docx | ||
IP | 71111 | Reactor Safety-Initiating Events, Mitigating Systems, Barrier Integrity | 10/13/22 | 22-022 | .docx | ||
IP | 71111.01 | Adverse Weather Protection | 08/01/22 | 22-015 | .docx | ||
IP | 71111.04 | Equipment Alignment | 09/19/23 | 23-028 | .docx | FY2009-02 FY2008-01 |
|
IP | 71111.05 | Fire Protection | 08/01/22 | 22-015 | .docx | ||
IP | 71111.06 | Flood Protection Measures | 08/01/22 | 22-015 | .docx | FY2023-02 FY2007-02, Rev. 3 |
|
IP | 71111.07 | Heat Exchanger/Sink Performance | 08/18/23 | 23-025 | .docx | ||
IP | 71111.08 | Inservice Inspection Activities | 10/16/23 | 23-030 | .docx | ||
IP | 71111.11 | Licensed Operator Requalification Program and Licensed Operator Performance | 12/06/24 | 24-039 | .docx | ||
IP | 71111.12 | Maintenance Effectiveness | 03/31/21 | 21-016 | .docx | FY2020-01 FY2019-01 FY2009-01 |
|
IP | 71111.13 | Maintenance Risk Assessments and Emergent Work Control | 08/01/22 | 22-015 | .docx | FY2023-02 | |
IP | 71111.15 | Operability Determinations and Functionality Assessments | 10/05/20 | 20-046 | .docx | FY2012-02, Rev 1 FY2009-02 FY2008-01 FY2007-02, Rev. 3 FY2007-01 |
|
IP | 71111.15 | Operability Determinations and Functionality Assessments – Effective January 1, 2026 | 04/09/25 | 25-006 | .docx | FY2012-02, Rev 1 FY2009-02 FY2008-01 FY2007-02, Rev. 3 FY2007-01 |
|
IP | 71111.17T | Evaluations of Changes, Tests and Experiments | 12/08/16 | R | 16-032 | .docx | |
IP | 71111.18 | Plant Modifications – Effective Date January 1, 2025 | 11/21/24 | 24-036 | .docx | FY2023-02 FY2023-01 FY2020-01 FY2019-01 |
|
IP | 71111.19 | Post-Maintenance Testing | 10/06/20 | R | 20-047 | .docx | FY2020-01 FY2009-02 FY2009-01 FY2008-01 |
IP | 71111.20 | Refueling and Other Outage Activities | 04/06/22 | 22-007 | .docx | FY2007-03 Rev 3 FY2007-01 |
|
IP | 71111.21M | Comprehensive Engineering Team Inspection | 06/27/25 | 25-024 | .docx | FY2023-02 FY2023-01 FY2020-01 FY2019-01 FY2007-02, Rev. 3 FY2007-01 |
|
IP | 71111.21N | Design Bases Assurance Inspection (Programs) | 02/05/19 | 19-005 | .docx | FY2019-01 | |
IP | 71111.21N.02 | Design-Basis Capability of Power-Operated Valves Under 10 CFR 50.55a Requirements | 10/09/20 | 20-050 | .docx | ||
IP | 71111.21N.03 | Commercial Grade Dedication | 02/16/23 | 23-004 | .docx | FY2023-01 | |
IP | 71111.21N.04 | Age-Related Degradation | 04/09/25 | 25-006 | .docx | FY2023-01 | |
IP | 71111.21N.05 | Fire Protection Team Inspection (FPTI) | 06/12/19 | 19-019 | .docx | FY2023-02 | |
IP | 71111.22 | Surveillance Testing | 03/29/21 | R | 21-015 | .docx | FY2020-01 FY2009-02 FY2009-01 FY2008-01 |
IP | 71111.24 | Testing and Maintenance of Equipment Important to Risk | 03/07/23 | 23-006 | .docx | FY2023-02 FY2023-01 FY2020-01 FY2009-02 FY2009-01 FY2008-01 |
|
IP | 71114 | Reactor Safety – Emergency Preparedness | 04/02/21 | 21-018 | .docx | ||
IP | 71114.01 | Exercise Evaluation | 07/21/16 | 16-017 | .docx | ||
IP | 71114.02 | Alert and Notification System Evaluation – Effective Date 01/01/2025 | 12/12/24 | 24-042 | .docx | ||
IP | 71114.03 | Emergency Response Organization Staffing and Augmentation System | 07/21/16 | 16-017 | .docx | ||
IP | 71114.04 | Emergency Action Level and Emergency Plan Changes | 07/21/16 | 16-017 | .docx | ||
IP | 71114.05 | Maintenance of Emergency Preparedness | 07/21/16 | 16-017 | .docx | ||
IP | 71114.06 | Drill Evaluation | 07/21/16 | 16-017 | .docx | ||
IP | 71114.07 | Exercise Evaluation - Hostile Action (HA) Event | 07/21/16 | 16-017 | .docx | ||
IP | 71114.08 | Exercise Evaluation – Scenario Review | 07/21/16 | 16-017 | .docx | ||
IP | 71124 | Radiation Safety—Public and Occupational | 12/21/17 | 17-031 | .docx | ||
IP | 71124.01 | Radiological Hazard Assessment and Exposure Controls | 12/29/21 | 21-041 | .docx | ||
IP | 71124.03 | In-Plant Airborne Radioactivity Control and Mitigation | 12/23/19 | 19-042 | .docx | ||
IP | 71124.04 | Occupational Dose Assessment | 12/23/19 | 19-042 | .docx | ||
IP | 71124.05 | Radiation Monitoring Instrumentation | 03/04/20 | 20-014 | .docx | ||
IP | 71124.06 | Radioactive Gaseous and Liquid Effluent Treatment | 03/04/20 | 20-014 | .docx | ||
IP | 71124.07 | Radiological Environmental Monitoring Program | 03/04/20 | 20-014 | .docx | ||
IP | 71124.08 | Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation | 03/04/20 | 20-014 | .docx | ||
IP | 71130 | Security | 12/06/23 | 23-035 | .docx | ||
IP | 71130.01 | Access Authorization | 12/21/23 | 23-039 | .docx | ||
IP | 71130.02 OUO-SRI |
Access Control | 12/18/23 | 23-038 | |||
IP | 71130.03 OUO-SRI |
Contingency Response – Force-on-Force Testing | 11/15/23 | 23-034 | |||
IP | 71130.04 OUO-SRI |
Equipment Performance, Testing, and Maintenance | 03/08/24 | 24-009 | |||
IP | 71130.05 OUO-SRI |
Protective Strategy Evaluation and Performance Evaluation Program | 11/15/23 | 23-034 | |||
IP | 71130.07 | Security Training | 01/02/24 | 24-001 | .docx | ||
IP | 71130.07EW | Enhanced Weapons and Preemption of Firearms Laws | 01/02/24 | 24-001 | .docx | ||
IP | 71130.08 | Fitness-for-Duty Program | 01/23/24 | 24-003 | .docx | ||
IP | 71130.09 | Security Plan Changes | 07/09/24 | 24-020 | .docx | ||
IP | 71130.10 | Cybersecurity | 12/14/21 | 21-040 | .docx | FY2023-01 | |
IP | 71130.11 OUO-SRI |
Material Control & Accounting (MC&A) | 01/07/20 | 20-003 | |||
IP | 71130.14 OUO-SRI |
Review of Power Reactor Target Sets | 03/09/23 | 23-008 | |||
IP | 71150 | Discrepant or Unreported Performance Indicator Data | 04/30/19 | 19-013 | .docx | ||
IP | 71151 | Performance Indicator Verification – Effective Date 01/01/2025 | 12/12/24 | 24-042 | .docx | FY2023-02 | |
IP | 71152 | Problem Identification and Resolution (PI&R) | 10/31/23 | 23-032 | .docx | FY2023-02 FY2023-01 FY2020-01 FY2018-01 FY2009-02 FY2009-01 FY2008-01 FY2007-04 FY2007-02, Rev. 3 FY2007-01 |
|
IP | 71153 | Follow-up of Events and Notices of Enforcement Discretion | 09/03/25 | 25-029 | .docx | ||
IP | 71303 | Part 52, Technical Specifications Review | 07/08/20 | 20-031 | .docx | ||
IP | 71715 | Sustained Control Room and Plant Observation | 04/14/92 | R | 92-004 | ||
IP | 71801 | Decommissioning Implementation and Status | 06/27/25 | 25-022 | .docx | ||
IP | 71841 | Human Performance | 12/12/00 | R | 00-027 | .doc | |
IP | 72303 | Startup Testing for ABWR: Test Procedure Review, Test Witnessing, and Test Results Evaluation | 09/05/06 | 06-021 | .doc | ||
IP | 72304 | AP 1000 Startup Test Inspections | 02/28/19 | 19-009 | .doc | ||
IP | 72401 | Part 52, Inspection of Startup Test Program | 12/07/20 | 20-069 | .docx | ||
IP | 72701 | Modification Testing | 04/14/92 | R | 92-004 | ||
IP | 73051 | Inservice Inspection Review of Program | 01/14/86 | R | 86-003 | ||
IP | 73052 | Inservice Inspection Review of Procedures | 01/14/86 | R | 86-003 | ||
IP | 73054 | Part 52, Preservice and Inservice Inspection - Review of Program | 03/04/20 | 20-013 | .docx | ||
IP | 73753 | Inservice Inspection | 06/04/98 | R | 98-010 | ||
IP | 73754 | Part 52 - Preservice Inspection - Non-Destructive Exam | 09/23/19 | 19-029 | .docx | ||
IP | 73755 | Inservice Inspection Data Review and Evaluation | 01/14/86 | R | 86-003 | ||
IP | 73756 | Inservice Testing of Pumps and Valves | 07/27/95 | R | 95-009 | ||
IP | 73757 | Part 52, Preservice Inspection - Data Review and Evaluation | 09/23/19 | 19-029 | .doc | ||
IP | 73758 | Part 52, Functional Design and Qualification, and Preservice and Inservice Testing Programs for Pumps, Valves and Dynamic Restraints | 02/06/20 | 20-007 | .docx | ||
IP | 78010 | 10 CFR Part 21 Program | 09/11/08 | 08-026 | .doc | ||
IP | 79702 | Control and Monitoring of Radiological Source Term | 04/17/00 | R | 00-006 | .doc | |
IP | 80522 | Part 52, Radiological Environmental Monitoring Program (REMP) | 05/07/20 | 20-024 | .docx | ||
IP | 81000 | Security | 10/29/24 | 24-033 | .docx | ||
IP | 81000.01 | Access Authorization | 07/24/24 | 24-021 | .docx | ||
IP | 81000.02 OUO-SRI |
Access Control | 11/04/24 | 24-035 | |||
IP | 81000.03 | Performance Evaluation Program | 12/10/24 | 24-041 | .docx | ||
IP | 81000.04 OUO-SRI |
Equipment Performance, Testing, and Maintenance | 11/04/24 | 24-035 | |||
IP | 81000.05 OUO-SRI |
Protective Strategy Evaluation | 11/04/24 | 24-035 | |||
IP | 81000.06 | Protection of Safeguards Information | 12/13/24 | 24-043 | .docx | ||
IP | 81000.07 | Security Training | 08/06/25 | 25-027 | .docx | ||
IP | 81000.08 | Fitness-For-Duty Program | 10/29/24 | 24-033 | .docx | ||
IP | 81000.09 OUO-SRI |
Cyber Security Inspection for Construction | 09/30/16 | 16-025 | |||
IP | 81000.10 | Security Organization, Management Effectiveness, Program Reviews and Audits | 12/10/24 | 24-041 | .docx | ||
IP | 81000.11 OUO-SRI |
Material Control and Accounting (MC&A) | 09/07/12 | 12-020 | |||
IP | 81000.11 | Material Control and Accounting (MC&A) | 11/22/24 | 24-037 | .docx | ||
IP | 81000.12 | Cybersecurity Restart Inspection--Pre-Fuel Load | 05/13/25 | 25-011 | .docx | ||
IP | 81000.14 OUO-SRI |
Review of New Power Reactor Target Sets | 11/04/24 | 24-035 | |||
IP | 81072 OUO-SRI |
Review of New Power Reactor Target Sets | 01/29/19 | 84-015 | |||
IP | 81120 OUO-SRI |
Inspection Requirements and Guidance for Additional Security Measures for the Physical Protection in Transit for Radioactive Material Quantities of Concern | 04/01/10 | 10-010 | |||
IP | 81200 | Security | 07/28/20 | 20-035 | .doc | ||
IP | 81200.01 | Access Authorization for Decommissioning Nuclear Power Reactors | 05/07/20 | 20-024 | .doc | ||
IP | 81200.02 OUO-SRI |
Access Control for Decommissioning Nuclear Power Reactors | 10/16/20 | 20-051 |
|||
IP | 81200.04 OUO-SRI |
Equipment Performance, Testing, and Maintenance for Decommissioning Nuclear Power Reactors | 01/05/21 | 21-001 |
|||
IP | 81200.05 OUO-SRI |
Protective Strategy Evaluation and Performance Evaluation Program for Decommissioning Nuclear Power Reactors | 01/05/21 | 21-001 | |||
IP | 81200.06 | Protection of Safeguards Information for Decommissioning Nuclear Power Reactors | 01/05/21 | 21-001 | .docx | ||
IP | 81200.07 | Security Training for Decommissioning Nuclear Power Reactors | 04/01/21 | 21-017 | .docx | ||
IP | 81200.09 | Security Plan Changes for Decommissioning Power Reactors | 02/18/21 | 21-009 | .docx | ||
IP | 81200.14 OUO-SRI |
Review of Decommissioning Reactor Target Sets | 01/05/21 | 21-001 |
|||
IP | 81310 OUO-SRI |
Physical Protection of Shipments of Irradiated Fuel | 12/22/08 | 08-037 | |||
IP | 81311 | Physical Security Requirements for Independent Spent Fuel Storage Installations | 06/28/22 | 22-014 | .docx | ||
IP | 81335 | Physical Protection of Shipments of Special Nuclear Material of Moderate Strategic Significance | 02/07/24 | 24-006 | .docx | ||
IP | 81340 OUO-SRI |
Physical Protection of Shipments of Special Nuclear Material of Low Strategic Significance (SNM-LSS) | 11/23/09 | 09-028 | |||
IP | 81360 OUO-SRI |
General Requirements for Physical Protection of Formula Quantities of Special Nuclear Material in Transit | 12/02/09 | 09-029 | |||
IP | 81365 OUO-SRI |
Records, Reports, and Planning for Physical Protection of Formula Quantities of Special Nuclear Material in Transit | 11/23/09 | 09-028 | |||
IP | 81370 OUO-SRI |
Specific Requirements for Physical Protection of Shipments of Formula Quantities of Special Nuclear Material in Transit | 12/22/08 | 08-037 | |||
IP | 81402 OUO-SRI |
Reporting of Safeguards Events | 11/23/09 | 09-028 | |||
IP | 81421 | Fixed Site Physical Protection of Special Nuclear Material of Moderate Strategic Significance | 02/07/24 | 24-006 | .docx | ||
IP | 81431 OUO-SRI |
Fixed Site Physical Protection of Special Nuclear Material of Low Strategic Significance | 10/24/12 | 12-025 | |||
IP | 81501 OUO-SRI |
Personnel Training and Qualification - General Requirements | 12/02/09 | 09-029 | |||
IP | 81502 OUO-SRI |
Fitness for Duty Program | 12/22/08 | 08-037 | |||
IP | 81504 OUO-SRI |
Fitness for Duty Program for Construction | 10/15/09 | 09-024 | |||
IP | 81505 | Protection of Safeguards Information for Construction | 02/13/19 | 19-007 | .docx | ||
IP | 81601 | Fixed Site Physical Protection of Formula Quantities of Strategic Special Nuclear Material – Non-Power Reactors | 03/13/20 | 20-015 | .docx | ||
IP | 81602 | Fixed Site Physical Protection of Special Nuclear Material of Moderate Strategic Significance – Non-Power Reactors | 03/13/20 | 20-015 | .docx | ||
IP | 81603 | Fixed Site Physical Protection of Special Nuclear Material of Low Strategic Significance – Non-Power Reactors | 03/13/20 | 20-015 | .docx | ||
IP | 81606 | Material Control and Accounting – Non-Power Reactors | 03/13/20 | 20-015 | .docx | ||
IP | 81607 | Protection of Safeguards Information and Safeguards Information Modified Handling – Non-Power Reactors | 03/13/20 | 20-015 | .docx | ||
IP | 81608 | Reporting of Safeguards Events – Non-Power Reactors | 05/01/25 | 25-010 | .docx | ||
IP | 81612 | In Transit Physical Protection of Special Nuclear Material of Moderate Strategic Significance and Receipt of New Reactor Fuel – Non-Power Reactors | 03/13/20 | 20-015 | .docx | ||
IP | 81613 | In Transit Physical Protection of Special Nuclear Material of Low Strategic Significance and Receipt of New Reactor Fuel – Non-Power Reactors | 03/13/20 | 20-015 | .docx | ||
IP | 81614 | In Transit Physical Protection of Irradiated Reactor Fuel – Non-Power Reactors | 03/13/20 | 20-015 | .docx | ||
IP | 81621 | Fixed Site Physical Protection of Category 1 and Category 2 Quantities of Radioactive Material – Non-Power Reactors | 03/13/20 | 20-015 | .docx | ||
IP | 81622 | In Transit Physical Protection of Category 1 and Category 2 Quantities of Radioactive Material and 100 Grams or Less of Irradiated Reactor Fuel – Non-Power Reactors | 03/13/20 | 20-015 | .docx | ||
IP | 81700.01 OUO-SRI |
Category I Fuel Cycle Facility Strategic Special Nuclear Material Security Controls | 05/15/17 | 17-010 | |||
IP | 81700.02 OUO-SRI |
Category I Fuel Cycle Facility Access Control Measures | 05/15/17 | 17-010 | |||
IP | 81700.04 OUO-SRI |
Category I Fuel Cycle Facility Security Equipment Performance, Testing and Maintenance | 05/15/17 | 17-010 | |||
IP | 81700.05 OUO-SRI |
Category I Fuel Cycle Facility Physical Protection Program and Protective Strategy | 05/15/17 | 17-010 | |||
IP | 81700.06 | Licensee Conducted Force-on-Force Exercises at Category I Fuel Cycle Facilities | 10/27/17 | 17-023 | .docx | ||
IP | 81700.07 OUO-SRI |
Category I Fuel Cycle Facility Security Training | 05/15/17 | 17-010 | |||
IP | 81700.08 OUO-SRI |
Category I Fuel Cycle Facility Fitness-for-Duty Programs | 05/15/17 | 17-010 | |||
IP | 81700.09 OUO-SRI |
Security Measures for Licensed Facilities | 03/02/20 | 20-012 | |||
IP | 81700.10 OUO-SRI |
Protection of Safeguards Information at Category I Fuel Cycle Facilities | 05/15/17 | 17-010 | |||
IP | 81700.11 | Annual Observation of Licensee Conducted Force-on-Force Exercises at Category I Fuel Cycle Facilities | 10/27/17 | 17-023 | .docx | ||
IP | 81810 OUO-SRI |
Protection of Safeguards Information | 09/10/07 | 07-027 | |||
IP | 81811 | Protection of Safeguards Information by Design Certification Applicants and Vendors | 04/08/20 | 20-020 | .docx | ||
IP | 81815 OUO-SRI |
Authorization for Access to National Security Information (NSI) & Restricted Data (RD) | 06/27/14 | 14-014 |
|||
IP | 81820 OUO-SRI |
Physical Protection Facility Approval and Safeguarding of National Security Information and Restricted Data | 11/26/24 | 24-038 | |||
IP | 81822 | Protection of Safeguards Information | 10/31/24 | 24-034 | .docx | ||
IP | 82001 | Evaluation of Emergency Preparedness | 05/22/00 | R | 00-010 | .doc | |
IP | 82001.01 | ERO Performance Drills | 05/22/00 | R | 00-010 | .doc | |
IP | 82001.02 | ERO Performance Drills Dose Assessment | 05/22/00 | R | 00-010 | .doc | |
IP | 82001.03 | ERO Augmentation Drill | 05/22/00 | R | 00-010 | .doc | |
IP | 82001.04 | Facilities and EquIPment | 05/22/00 | R | 00-010 | .doc | |
IP | 82001.05 | Procedure Quality | 05/22/00 | R | 00-010 | .doc | |
IP | 82001.06 | Remedial Exercises | 05/22/00 | R | 00-010 | .doc | |
IP | 82002 | Part 52 Emergency Preparedness Program | 03/04/20 | 20-014 | .docx | ||
IP | 82002.01 | Facilities and Equipment | 11/08/11 | 11-030 | .doc | ||
IP | 82002.02 | Procedure Quality | 11/08/11 | 11-030 | .doc | ||
IP | 82002.03 | Review of Exercise Objectives and Exercise Scenario for Power Reactors | 11/08/11 | 11-030 | .doc | ||
IP | 82002.04 | Emergency Preparedness Exercises | 11/08/11 | 11-030 | .doc | ||
IP | 82002.05 | Emergency Response Organization On-Shift Staffing and Augmentation Drills | 11/08/11 | 11-030 | .doc | ||
IP | 82002.06 | Emergency Response Organization, Dose Assessment Drills | 11/08/11 | 11-030 | .doc | ||
IP | 82002.07 | Operational Status of the Emergency Preparedness Program | 11/08/11 | 11-030 | .doc | ||
IP | 82201 | Emergency Detection and Classification | 03/23/05 | R | 05-008 | .doc | |
IP | 82202 | Protective Action Decision Making | 03/23/05 | R | 05-008 | .doc | |
IP | 82301 | Evaluation of Exercises for Power Plants | 04/24/13 | R | 13-012 | ||
IP | 82302 | Review of Exercise Objectives and Scenarios for Power Reactors | 04/24/13 | R | 13-012 | ||
IP | 82401 | Decommissioning Emergency Preparedness Scenario Review and Exercise Evaluation | 09/04/14 | 14-020 | .docx | ||
IP | 82501 | Decommissioning Emergency Preparedness Program Evaluation | 09/04/14 | 14-020 | .docx | ||
IP | 82701 | Operational Status of the Emergency Preparedness Program | 04/24/13 | R | 13-012 | ||
IP | 83501 | Significant Uncontrolled Radiation Exposure | 04/17/00 | R | 00-006 | .doc | |
IP | 83502 | Evaluation of Public Radiation Safety | 04/17/00 | R | 00-006 | .doc | |
IP | 83502.01 | Radioactive Gaseous and Liquid Effluent Treatment and Monitoring Systems | 04/17/00 | R | 00-006 | .doc | |
IP | 83502.02 | Radioactive Material Processing and Transportation | 04/17/00 | R | 00-006 | .doc | |
IP | 83502.03 | Radiological Environment Monitoring Program (REMP) and Radioactive Material Control Program | 04/17/00 | R | 00-006 | .doc | |
IP | 83523 | Radiation Protection, Plant Chemistry, Radwaste, Transportation and Environmental: Training and Qualifications | 11/13/08 | R | 08-032 | .doc | |
IP | 83531 | Part 52, Life Cycle Minimization of Contamination and Groundwater Protection Program | 03/04/20 | 20-013 | .docx | ||
IP | 83533 | Part 52, External Occupational Exposure Control and Personal Dosimetry | 03/04/20 | 20-013 | .docx | ||
IP | 83534 | Part 52, Internal Exposure Control and Assessment | 03/04/20 | 20-013 | .docx | ||
IP | 83535 | Part 52, Control of Radioactive Materials and Contamination, Surveys, and Monitoring | 03/04/20 | 20-013 | .docx | ||
IP | 83536 | Part 52, Facilities and Equipment | 03/04/20 | 20-013 | .docx | ||
IP | 83537 | Part 52, Maintaining Occupational Exposures ALARA | 03/04/20 | 20-013 | .docx | ||
IP | 83723 | General Employee, Radiation Safety, Plant Chemistry, Radwaste, and Transportation Training | 12/16/03 | R | 03-041 | .doc | |
IP | 83724 | External Occupational Exposure Control and Personal Dosimetry | 04/17/00 | 00-006 | .doc | ||
IP | 83725 | Internal Exposure Control and Assessment | 04/17/00 | 00-006 | .doc | ||
IP | 83726 | Control of Radioactive Materials and Contamination, Surveys, and Monitoring | 11/13/14 | 14-027 | .docx | ||
IP | 83728 | Maintaining Occupational Exposures ALARA | 04/17/00 | R | 00-006 | .doc | |
IP | 83729 | Occupational Exposure During Extended Outages | 12/31/91 | R | 91-021 | ||
IP | 83746 | Part 52, Offsite Dose Calculation Manual (ODCM) | 05/07/20 | 20-024 | .doc | ||
IP | 83750 | Decommissioning Occupational Radiation Control | 06/27/25 | 25-022 | .docx | ||
IP | 83801 | Inspection of Remedial and Final Surveys at Permanently Shutdown Reactors | 01/06/21 | 21-002 | .docx | ||
IP | 83822 | Radiation Protection | 12/15/22 | 22-026 | .docx | ||
IP | 83890 | Closeout Inspection and Survey | 12/15/22 | 22-026 | .docx | ||
IP | 84100 | Special Nuclear Material Inspections At Near Surface Low-Level Waste Disposal Facilities in Agreement States | 11/27/01 | 01-028 | .doc | ||
IP | 84101 | Radioactive Waste Management | 12/30/91 | 91-022 | |||
IP | 84522 | Solid Wastes (Preoperational and Supplemental) | 11/13/08 | R | 08-032 | .doc | |
IP | 84525 | Quality Assurance and Confirmatory Measurements for In-Plant Radiochemical Analysis (Preoperational And Supplemental) | 11/13/08 | 08-032 | .doc | ||
IP | 84527 | Part 52, Solid Waste Management Program | 04/30/20 | 20-022 | .doc | ||
IP | 84528 | Part 52, Liquid Waste Management Program | 04/30/20 | 20-022 | .docx | ||
IP | 84529 | Part 52, Gaseous Waste Management Program | 05/07/20 | 20-024 | .docx | ||
IP | 84750 | Decommissioning Radioactive Waste Treatment, and Effluent and Environmental Monitoring | 06/27/25 | 25-022 | .docx | ||
IP | 84850 | Radioactive Waste Management - Inspection of Waste Generator Requirements of 10 CFR Part 20 and 10 CFR Part 61. | 12/22/08 | 08-037 | .doc | ||
IP | 84900 | Low-Level Radioactive Waste Storage | 12/15/22 | 22-026 | .docx | ||
IP | 85102 OUO-SRI |
Material Control and Accounting - Reactors | 03/29/85 | 85-010 | |||
IP | 85103 OUO-SRI |
Material Control and Accounting at Decommissioning Nuclear Power Reactors | 07/03/18 | 18-019 | |||
IP | 85200 OUO-SRI |
MC&A for Licensees Possessing Less Than or Equal to One Effective Kilogram of SNM |
04/10/85 | 85-010 | |||
IP | 85203 OUO-SRI |
Management Structure and Controls | 05/30/24 | 24-016 | |||
IP | 85205 OUO-SRI |
Item Control Program | 05/30/24 | 24-016 | |||
IP | 85207 OUO-SRI |
Measurement Program | 05/30/24 | 24-016 | |||
IP | 85209 OUO-SRI |
Measurement Control Program | 05/30/24 | 24-016 | |||
IP | 85211 OUO-SRI |
Physical Inventory Program |
05/30/24 | 24-016 | |||
IP | 85213 OUO-SRI |
Resolution Program for Category II Facilities | 05/30/24 | 24-016 | |||
IP | 85303 OUO-SRI |
Material Control and Accounting Management Structure and Personnel Training and Qualification | 12/17/20 | 20-074 | |||
IP | 85305 OUO-SRI |
Item Monitoring |
12/16/20 | 20-073 | |||
IP | 85307 OUO-SRI |
Process Monitoring |
12/16/20 | 20-073 | |||
IP | 85309 OUO-SRI |
Measurement Systems and Control | 11/06/20 | 20-060 | |||
IP | 85311 OUO-SRI |
Physical Inventory Program |
11/06/20 | 20-060 | |||
IP | 85313 OUO-SRI |
Alarm Resolution Program |
11/06/20 | 20-060 | |||
IP | 85315 OUO-SRI |
Internal Control | 12/16/20 | 20-073 | |||
IP | 85401 OUO-SRI |
Management Structure |
11/06/20 | 20-060 | |||
IP | 85402 OUO-SRI |
Measurement Program |
12/22/20 | 20-075 | |||
IP | 85403 OUO-SRI |
Measurement Control Program |
12/22/20 | 20-075 | |||
IP | 85404 OUO-SRI |
Physical Inventory Program for Low Enriched Uranium Fuel Facilities | 01/13/21 | 21-004 | |||
IP | 85405 OUO-SRI |
Item Control |
01/13/21 | 21-004 | |||
IP | 85406 OUO-SRI |
Resolution Program for Low Enriched Uranium Fuel Facilities | 01/13/21 | 21-004 | |||
IP | 85407 OUO-SRI |
Assessment Program |
12/17/20 | 20-074 | |||
IP | 85408 OUO-SRI |
Recordkeeping Program |
12/17/20 | 20-074 | |||
IP | 85420 OUO-SRI |
Inspection of IAEA Safeguards for Inspectors at Power Reactors | 06/22/88 | R | 88-007 | ||
IP | 85501 OUO-SRI |
Physical Inventory Program for Uranium Enrichment Facilities - |
12/22/20 | 20-075 | |||
IP | 85502 OUO-SRI |
Detection Program for Uranium Enrichment Facilities | 12/22/20 | 20-075 | |||
IP | 85503 OUO-SRI |
Resolution Program for Uranium Enrichment Facilities | 01/13/21 | 21-004 | |||
IP | 86001 | Design, Fabrication, Testing, and Maintenance of Transportation Packagings | 05/21/25 | 25-012 | .docx | ||
IP | 86730 | Transportation of Radioactive Materials (49 CFR Parts 100-179 and 10 CFR Part 71) | 04/17/00 | 00-006 | .doc | ||
IP | 86740 | Inspection of Transportation Activities | 12/14/20 | 20-071 | .docx | ||
IP | 86750 | Decommissioning Solid Radioactive Waste Management, Demolition and Transportation of Radioactive Materials | 06/27/25 | 25-022 | .docx | ||
IP | 87102 | Maintaining Effluents from Materials Facilities As Low As Is Reasonably Achievable (ALARA) | 04/04/00 | 00-005 | |||
IP | 87103 | Inspection of Materials Licensees Involved in an Incident or Bankruptcy Filing | 11/03/00 | 00-023 | .doc | ||
IP | 87104 | Decommissioning Inspection Procedure for Materials Licensees | 12/15/22 | 22-026 | .docx | ||
IP | 87121 | Industrial Radiography Programs | 05/16/24 | 24-015 | .docx | ||
IP | 87122 | 10 CFR Part 36 Panoramic Dry-Source-Storage, Panoramic Wet-Source-Storage, and Underwater Irradiator Programs | 12/21/23 | 23-039 | .docx | ||
IP | 87123 | Well Logging and Tracer Study Programs | 04/26/22 | 22-008 | .docx | ||
IP | 87124 | Fixed Nuclear Gauge Programs | 04/26/22 | 22-008 | .docx | ||
IP | 87125 | Materials Processor/Manufacturer Programs | 12/21/23 | 23-039 | .docx | ||
IP | 87126 | Broad Scope Academic and Research & Development Programs | 04/26/22 | 22-008 | .docx | ||
IP | 87127 | Radiopharmacy Programs | 07/01/08 | 08-018 | .doc | ||
IP | 87128 | Manufacturing and Distribution of Exempt Products | 08/07/19 | 19-026 | .docx | ||
IP | 87129 | Master Materials Program | 10/29/21 | 21-036 | .docx | ||
IP | 87130 | Nuclear Medicine Programs | 04/26/22 | 22-008 | .docx | ||
IP | 87131 | Nuclear Medicine Programs, Written Directive Required | 08/24/11 | 11-014 | .doc | ||
IP | 87132 | Brachytherapy Programs | 02/26/15 | 15-003 | .docx | ||
IP | 87133 | Medical Gamma Sterotactic Radiosurgery and Teletherapy Programs | 08/24/11 | 11-014 | .doc | ||
IP | 87134 | Medical Broad-Scope Programs | 08/24/11 | 11-014 | .doc | ||
IP | 87137 | 10 CFR Part 37 Materials Security Programs | 12/03/20 | 20-068 | .docx | ||
IP | 87139 | Portable Nuclear Gauge Programs | 04/26/22 | 22-008 | .docx | ||
IP | 87140 | Source, Special Nuclear Material, and Other Alpha Emitter Use Programs | 04/26/22 | 22-008 | .docx | ||
IP | 87141 | Limited Scope Academic and Research & Development Programs Including Animal Use | 04/26/22 | 22-008 | .docx | ||
IP | 87142 | Sealed Sources and Devices (Other) Used in Measuring Systems, Analytical Instruments, Calibration and Checking of Instruments, and Similar Purposes | 04/26/22 | 22-008 | .docx | ||
IP | 87143 | Self-Shielded Irradiator and Calibrator Devices | 04/26/22 | 22-008 | .docx | ||
IP | 87144 | Veterinary Use Programs | 04/26/22 | 22-008 | .docx | ||
IP | 87250 | Locating Missing Materials Licensees | 10/29/01 | 01-022 | |||
IP | 87300 | Groundwater Monitoring and Remediation at Decommissioning Fuel Cycle and Complex Materials Facilities | 12/15/22 | 22-026 | .docx | ||
IP | 87305 | Decommissioning Management Organization and Controls | 12/15/22 | 22-026 | .docx | ||
IP | 87654 | Uranium Mill, In-Situ Recovery, and 11e.(2) Byproduct Material Disposal Site Decommissioning Inspection | 12/15/22 | 22-026 | .docx | ||
IP | 88003 | Reactive Inspection for Events at Fuel Cycle Facilities | 03/19/15 | 15-004 | .docx | ||
IP | 88005 | Management Organization and Controls | 09/05/06 | 06-020 | .doc | ||
IP | 88010 | Training | 02/07/14 | 14-005 | .docx | ||
IP | 88015 | Nuclear Criticality Safety | 10/20/20 | 20-052 | .docx | ||
IP | 88020 | Operational Safety | 12/14/20 | 20-071 | .docx | ||
IP | 88025 | Maintenance and Surveillance of Safety Controls | 01/23/14 | 14-003 | .docx | ||
IP | 88030 | Radiation Protection | 01/29/21 | 21-007 | .docx | ||
IP | 88045 | Effluent Control and Environmental Protection | 03/12/21 | 21-013 | .docx | ||
IP | 88050 | Emergency Preparedness | 12/17/20 | 20-074 | .docx | ||
IP | 88051 | Evaluation of Exercises and Drills | 11/12/20 | 20-062 | .docx | ||
IP | 88055 | Fire Protection | 11/09/20 | 20-061 | .docx | ||
IP | 88070 | Plant Modifications (Annual) | 12/14/20 | 20-071 | .docx | ||
IP | 88071 | Configuration Management Program | 03/06/14 | 14-007 | .docx | ||
IP | 88072 | Plant Modifications (Triennial) | 08/21/18 | 18-027 | .docx | ||
IP | 88075 | Event Follow-up | 03/19/15 | 15-004 | .docx | ||
IP | 88100 | Plant Operations | 12/30/96 | 96-026 | |||
IP | 88101 | Configuration Control | 12/30/96 | 96-026 | |||
IP | 88102 | Surveillance Observations | 12/30/96 | 96-026 | |||
IP | 88103 | Maintenance Observations | 12/30/96 | 96-026 | |||
IP | 88104 | Decommissioning Inspection Procedure For Fuel Cycle Facilities | 12/15/22 | 22-026 | .docx | ||
IP | 88106 | Quality Assurance: Program Development and Implementation(Pre-licensing and Construction) | 02/07/07 | 07-006 | .doc | ||
IP | 88107 | Quality Assurance: Design and Documentation Control (Pre-licensing and Construction) | 05/18/05 | 05-013 | .doc | ||
IP | 88108 | Quality Assurance: Control of Materials, Equipment, and Services (Pre-licensing and Construction) | 02/07/07 | 07-006 | .doc | ||
IP | 88109 | Quality Assurance: Inspection, Test Control, and Control of Measuring and Test Equipment (Pre-licensing and Construction) | 06/20/07 | 07-020 | .doc | ||
IP | 88110 | Quality Assurance: Problem Identification, Resolution and Corrective Action (PIRCA) (Construction, Pre-Operation and Operation) | 05/18/05 | 05-013 | .doc | ||
IP | 88111 | 10 CFR, Part 21, Inspection-Facility Construction | 02/07/07 | 07-006 | .doc | ||
IP | 88113 | Control of the Electronic Management of Data | 02/07/07 | 07-006 | .doc | ||
IP | 88114 | Quality Affecting Item Procurement (10 CFR Part 21) and Commercial Grade Item Dedication Process (Reactive) | 10/25/06 | 06-031 | .doc | ||
IP | 88115 | Supplier/Vendor Inspection (Construction Phase) | 10/25/06 | 06-031 | .doc | ||
IP | 88117 | Facility Changes (License Application) and Change Process (10 CFR 70.72) (Pre-Licensing and Construction) | 09/20/16 | 16-023 | .docx | ||
IP | 88130 OUO-SRI |
Resident Inspection Program for On-Site Construction Activities at the Mixed-Oxide Fuel Fabrication Facility | 03/02/16 | 16-009 | |||
IP | 88131 | Geotechnical/Foundation Activities | 10/25/06 | 06-031 | .doc | ||
IP | 88132 | Structural Concrete Activities | 10/25/06 | 06-031 | .doc | ||
IP | 88133 | Structural Steel and Supports Activities | 07/25/07 | 07-023 | .doc | ||
IP | 88134 | Piping Systems Relied on for Safety | 05/18/05 | 05-013 | .doc | ||
IP | 88135 | Resident Inspection Program for Category I Fuel Cycle Facilities | 12/02/20 | 20-067 | .docx | ||
IP | 88135.02 | Resident Inspection Program Plant Status Activities | 12/02/20 | 20-067 | .docx | ||
IP | 88135.04 | Resident Inspection Program Operational Safety | 12/02/20 | 20-067 | .docx | ||
IP | 88135.05 | Resident Inspection Program Fire Protection (Annual/Quarterly) | 12/02/20 | 20-067 | .docx | ||
IP | 88135.17 | Resident Inspection Program Plant Modifications | 12/02/20 | 20-067 | .docx | ||
IP | 88135.19 | Resident Inspection Program Post-Maintenance Testing | 12/02/20 | 20-067 | .docx | ||
IP | 88135.22 | Resident Inspection Program Surveillance Testing | 12/02/20 | 20-067 | .docx | ||
IP | 88136 | Mechanical Components | 07/25/07 | 07-023 | .doc | ||
IP | 88137 | Electrical Cable | 04/01/10 | 10-010 | .doc | ||
IP | 88138 | Electrical Components and Systems | 08/08/07 | 07-024 | .doc | ||
IP | 88139 | Ventilation and Confinement Systems | 08/08/07 | 07-024 | .doc | ||
IP | 88140 | Instrumentation and Control Systems | 04/01/10 | 10-010 | .doc | ||
IP | 88141 | Fire Prevention and Protection | 08/08/07 | 07-024 | .doc | ||
IP | 88142 | Underground Fire Water Loop and Equipment Installation | 08/08/07 | 07-024 | .doc | ||
IP | 88143 | Pipe Supports and Restrains | 07/25/07 | 07-023 | .doc | ||
IP | 88161 | Corrective Action Program (CAP) Implementation at Fuel Cycle Facilities | 07/28/14 | 14-017 | .docx | ||
IP | 88200 | Inspections of Safety Significant Items and Services during Construction of Fuel Cycle Facilities | 05/28/25 | 25-014 | .docx | ||
IP | 88200.A | Inspection of Foundations and Buildings at Fuel Cycle Facilities | 05/28/25 | 25-014 | .docx | ||
IP | 88200.B | Inspection of Structural Concrete at Fuel Cycle Facilities | 05/28/25 | 25-014 | .docx | ||
IP | 88200.C | Inspection of Structural Steel and Supports at Fuel Cycle Facilities | 05/28/25 | 25-014 | .docx | ||
IP | 88200.D | Inspection of Piping at Fuel Cycle Facilities | 05/28/25 | 25-014 | .docx | ||
IP | 88200.E | Inspection of Piping Supports and Restraints at Fuel Cycle Facilities | 05/28/25 | 25-014 | .docx | ||
IP | 88200.F | Inspection of Mechanical Components at Fuel Cycle Facilities | 05/28/25 | 25-014 | .docx | ||
IP | 88200.G | Inspection of Electrical Cable at Fuel Cycle Facilities | 05/28/25 | 25-014 | .docx | ||
IP | 88200.H | Inspection of Electrical Components and Systems at Fuel Cycle Facilities | 05/28/25 | 25-014 | .docx | ||
IP | 88200.I | Inspection of Ventilation and Confinement Systems at Fuel Cycle Facilities | 05/28/25 | 25-014 | .docx | ||
IP | 88200.J | Inspection of Instrumentation and Control Systems at Fuel Cycle Facilities | 05/28/25 | 25-014 | .docx | ||
IP | 88200.K | Inspection of Safety-Significant Welding at Fuel Cycle Facilities | 05/28/25 | 25-014 | .docx | ||
IP | 88200.L | Inspection of Fire Protection Systems Under Construction at Fuel Cycle Facilities | 05/28/25 | 25-014 | .docx | ||
IP | 88200.M | Inspection of Digital Instrumentation and Control (DI&C) System/Software Design at Fuel Cycle Facilities | 05/28/25 | 25-014 | .docx | ||
IP | 88201 | Inspection of Management Measures during Construction of Fuel Cycle Facilities | 06/20/25 | 25-018 | .docx | ||
IP | 88201.A | Configuration Management | 06/20/25 | 25-018 | .docx | ||
IP | 88201.B | Maintenance | 06/20/25 | 25-018 | .docx | ||
IP | 88201.C | Training and Qualifications | 06/20/25 | 25-018 | .docx | ||
IP | 88201.D | Procedures | 06/20/25 | 25-018 | .docx | ||
IP | 88201.E | Audits and Assessments | 06/20/25 | 25-018 | .docx | ||
IP | 88201.F | Incident Investigations | 06/20/25 | 25-018 | .docx | ||
IP | 88201.G | Records Management | 06/20/25 | 25-018 | .docx | ||
IP | 88201.H | Other Quality Assurance (QA) Elements | 06/20/25 | 25-018 | .docx | ||
IP | 89005 | Management Organization and Controls at Uranium Recovery and 11e.(2) Byproduct Material Facilities | 10/08/21 | 21-034 | .docx | ||
IP | 89010 | Disposal Cell Construction at Uranium Recovery and 11e.(2) Byproduct Material Facilities | 10/08/21 | 21-034 | .docx | ||
IP | 89015 | Construction and Preoperational Inspection Program at Uranium Recovery and 11e.(2) Byproduct Material Facilities | 10/08/21 | 21-034 | .docx | ||
IP | 89020 | Groundwater and Water Management at Uranium Recovery and 11e.(2) Byproduct Material Facilities | 10/08/21 | 21-034 | .docx | ||
IP | 89025 | Assessment of Dryer and Yellowcake Packaging Operations | 07/26/24 | 24-022 | .docx | ||
IP | 89030 | Radiation Protection at Uranium Recovery and 11e.(2) Byproduct Material Facilities | 10/08/21 | 21-034 | .docx | ||
IP | 89035 | Radioactive Waste Management and Transportation at Uranium Recovery and 11e.(2) Byproduct Material Facilities | 10/08/21 | 21-034 | .docx | ||
IP | 89045 | Effluent Control and Environmental Protection at Uranium Recovery and 11e.(2) Byproduct Material Facilities | 10/08/21 | 21-034 | .docx | ||
IP | 89050 | Emergency Preparedness and Fire Protection at Uranium Recovery and 11e.(2) Byproduct Material Facilities | 10/08/21 | 21-034 | .docx | ||
IP | 89060 | Department of Energy Observational Site Visits | 12/15/22 | 22-026 | .docx | ||
IP | 90001 | Construction Regulatory Response Column Inspections | 10/27/10 | 10-022 | .doc | ||
IP | 90002 | Construction Degraded Performance Column Inspections | 10/28/14 | 14-026 | .docx | ||
IP | 90003 | Construction Supplemental Inspection for Repetitive Degraded Cornerstones, Multiple Degraded Cornerstones, Multiple Yellow Inputs or One Red Input | 10/28/14 | 14-026 | .docx | ||
IP | 90700 | Feedback of Operational Experience Information at Operating Power Reactors | 03/23/05 | R | 05-008 | .doc | |
IP | 90712 | In-office Review of Written Reports of Nonroutine Events at Power Reactor Facilities | 12/31/98 | R | 98-020 | ||
IP | 92050 | Review of Quality Assurance for Extended Construction Delay | 04/04/00 | 00-005 | |||
IP | 92700 | Onsite Followup of Written Reports of Nonroutine Events at Power Reactor Facilities | 12/31/98 | R | 98-020 | ||
IP | 92701 | Followup | 03/13/07 | 07-010 | .doc | ||
IP | 92702 | Follow-Up on Traditional Enforcement Actions Including Violations, Deviations, Confirmatory Action Letters, and Orders | 10/26/20 | 20-055 | .doc | ||
IP | 92703 | Followup of Confirmatory Action Letters or Orders | 05/13/09 | 09-012 | .doc | ||
IP | 92707 OUO-SRI |
Security Inspection of Facilities Impacted by a Local, State, or Federal Emergency Where the U.S. Nuclear Regulatory Commission's Ability to Conduct Triennial Force On-Force Exercises is Limited | 03/14/24 | 24-010 | |||
IP | 92709 | Contingency Plans for Licensee Strikes or Lockouts | 05/16/19 | 19-015 | .docx | ||
IP | 92711 | Implementation of Licensee Contingency Plans During a Strike/Lockout | 05/16/19 | 19-015 | .docx | ||
IP | 92712 | Resumption of Normal Operations After a Strike/Lockout | 05/16/19 | 19-015 | .docx | ||
IP | 92720 | Corrective Action | 11/01/07 | 07-034 | |||
IP | 92722 | Follow-Up Inspection for Any Severity Level I or II Traditional Enforcement Violation or for Two or More Severity Level III Traditional Enforcement Violations in a 12-Month Period | 09/16/21 | 21-031 | .docx | ||
IP | 92723 | Follow-Up Inspection for One Severity Level III and Two Severity Level IV Traditional Enforcement Violations or for Three or More Severity Level IV Traditional Enforcement Violations in the Same Area in a 12-Month Period | 09/16/21 | 21-031 | .docx | ||
IP | 93002 | Managing Fatigue | 11/21/24 | 24-036 | .docx | ||
IP | 93100 | Safety-Conscious Work Environment Issue of Concern Followup | 07/14/21 | 21-024 | .docx | ||
IP | 93800 | Augmented Inspection Team | 06/07/22 | 22-012 | .docx | ||
IP | 93801 | Safety System Functional Inspection (SSFI) | 07/15/96 | R | 96-016 | .doc | |
IP | 93802 | Operational Safety Team Inspection (OSTI) | 11/27/89 | R | 89-015 | ||
IP | 93803 | Safety Systems Outage Modifications Inspection | 04/27/89 | R | 89-008 | ||
IP | 93804 | Risk-Based Operational Safety and Performance Inspection | 01/15/92 | R | 92-001 | ||
IP | 93805 | Maintenance Program | 08/06/93 | R | 93-007 | ||
IP | 93806 | Operational Readiness Assessment Team Inspections | 09/29/98 | R | 98-015 | ||
IP | 93807 | Systems Based Instrumentation and Control Inspection | 01/29/93 | R | 93-001 | ||
IP | 93810 | Service Water System Operational Performance Inspection (SWSOPI) | 09/14/98 | R | 98-013 | ||
IP | 93811 | Electrical Distribution System Functional Inspection (EDSFI) | 02/03/99 | R | 99-002 | ||
IP | 93812 | Special Inspection | 06/07/22 | 22-012 | .docx | ||
IP | 95001 | Supplemental Inspection Response to Action Matrix Column 2 (Regulatory Response) Inputs | 08/19/21 | 21-028 | .docx | ||
IP | 95002 | Supplemental Inspection Response to Action Matrix Column 3 (Degraded Performance) Inputs | 03/19/21 | 21-014 | .docx | ||
IP | 95003 | Supplemental Inspection Response to Action Matrix Column 4 (Multiple/Repetitive Degraded Cornerstone) Inputs | 06/07/22 | 22-012 | .docx | ||
IP | 95003.01 | Emergency Preparedness | 01/15/09 | 09-002 | .doc | ||
IP | 95003.02 | Guidance for Conducting an Independent NRC Safety Culture Assessment | 04/16/25 | 25-008 | .docx | ||
IP | 96001 OUO-SRI |
NRC Force-on-Force Inspections at Category 1 Fuel Cycle Facilities | 03/11/19 | 19-010 |
Page Last Reviewed/Updated Thursday, September 04, 2025
Page Last Reviewed/Updated Thursday, September 04, 2025