FOIA/PA-2003-0018 - Resp 4 - Partial.
Accession Number: ML031120702
Date Released: Wednesday, April 16, 2003
Package Contents
The following links on this page are to Adobe Portable Document Format (PDF) files. To obtain a free viewer for displaying this format, see our Plugins, Viewers, and Other Tools.
- ML031110088 - FOIA/PA-2003-0018 - Resp 4 - Partial. (10 page(s), 4/8/2003)
- ML031110097 - Nuclear & Environmental Operations, Davis Besse Reactor Vessel Head Examination. (42 page(s), 4/8/2003)
- ML031110101 - E-mail From Wilkowski to D. Jackson, regarding additional thoughts on DB head crack testing. (6 page(s), 9/12/2002)
- ML031110102 - E-mail from J. Hixon to C. Fairbanks, regarding draft SOW to Davis Besse Crack. (1 page(s), 9/12/2002)
- ML031110106 - E-mail from W. Cullen to C. Fairbanks, regarding draft SOW for Davis Besse Crack. (1 page(s), 9/12/2002)
- ML031110119 - E-mail from M. Kirk to C. Santos, regarding SOW for Davis Besse Crack. (12 page(s), 9/12/2002)
- ML031110146 - E-mail from J. Hixon to DH. Dawes, regarding Davis Besse B&W contract. (2 page(s), 9/13/2002)
- ML031110153 - E-mail from C. Santos to B. Shack, regarding Davis Besse Cladding Cracks. (5 page(s), 9/13/2002)
- ML031110196 - Memo to M. Kirk from P. Willians and B. Bass, regarding status report on Davis Besse Analyses. (6 page(s), 9/27/2002)
- ML031110212 - Memo to M. Kirk from P. T. Williams and B. Bass, regarding status report on Davis Besse Analyses. (9 page(s), 10/4/2002)
- ML031110218 - E-mail from M. Kirk to G. Demoss, regarding Davis besse Reports and Letters. (1 page(s), 10/7/2002)
- ML031110226 - E-mail from N. Chokshi to G. Demoss, regarding Davis Besse. (1 page(s), 10/8/2002)
- ML031110228 - E-mail from J. Hixon to D. H. Dawes, regarding Davis Besse Head Cladding. (1 page(s), 11/11/2002)
- ML031110258 - E-mail from R. Tregoing to BXB, regarding Davis Besse Results. (34 page(s), 10/11/2002)
- ML031110266 - E-mail from W. Cullen to D. Jackson, regarding Boric Acid Corrosion Report. (23 page(s), 10/15/2002)
- ML031110349 - E-mail from MK Leisure to CAL, regarding Serial 2816. (7 page(s), 10/17/2002)
- ML031110351 - Memo to M. Kirk from P. Williams and B. Bass, regarding status report on Davis Besse Analyses. (10 page(s), 10/18/2002)
- ML031120661 - E-mail from P. Williams to RLT, regarding DB Analysis Status Report for October 18, 2002. (15 page(s), 10/18/2002)
- ML031110363 - E-mail from N. Chokshi to D. Jackson, regarding Davis Besse Head Disposal/Additional Samples. (1 page(s), 10/18/2002)
- ML031110370 - E-mail from R. Tregoning to N. Chokshi, regarding DB Head Needs. (1 page(s), 10/21/2002)
- ML031110136 - E-mail from W. Cullen to R. Tregoning. (2 page(s), 10/21/2002)
- ML031110142 - E-mail from R. Tregoning to N. Chokshi, regarding DB Head Needs. (2 page(s), 10/21/2002)
- ML031110150 - E-mail from N. Chokshi to R. Tregoning, regarding DB Head Needs. (2 page(s), 10/21/2002)
- ML031110157 - E-mail from N. Chokshi to W. Dean, regarding DB Material. (3 page(s), 10/21/2002)
- ML031110161 - E-mail from W. Cullen to N. Chokshi, regarding DB Head Needs. (2 page(s), 10/21/2002)
- ML031110167 - E-mail from N. Chokshi to R. Tregoning, regarding DB Head. (1 page(s), 10/22/2002)
- ML031110173 - E-mail from R. Tregoning to N. Chokshi, regarding DB Head. (1 page(s), 10/22/2002)
- ML031110177 - E-mail from J. Strosnider to A. Thadani, regarding decision on Davis Besse RPV Head. (1 page(s), 10/22/2002)
- ML031110189 - E-mail to M. Kirk from M. Leisure, regarding four photos requested of Davis Besse reactor head cavity mold. (3 page(s), 10/23/2002)
- ML031110192 - E-mail from N. Chokshi to W. Cullen, requesting meeting with Bill Dean and Projects. (1 page(s), 10/23/2002)
- ML031110201 - E-mail from M. Kirk to R. Bass, regarding Dimensioned Photos of the DB Cavity Dental Mold. (4 page(s), 10/24/2002)
- ML031110205 - E-mail from R. Tregoning to Bass, regarding Initial Plan - rough draft. (8 page(s), 10/24/2002)
- ML031110213 - E-mail from Tregoning to W. Cullen, regarding Mosaic. (1 page(s), 10/24/2002)
- ML031110220 - E-mail from R. Tregoning to M. Kirk, regarding dimensioned photos of the DB cavity dental mold. (1 page(s), 10/24/2002)
- ML031110225 - E-mail from D. Wuokko to jbh1, regarding NRC Request for Weld Data Sheets for RVCH. (1 page(s), 10/25/2002)
- ML031110229 - E-mail from R.Tregoning to W. Cullen, regarding latest version of ORNL clad burst SOW. (12 page(s), 10/25/2002)
- ML031110232 - Memo to M. Kirk and R. Tregoning from P. Williams and B. Bass, regarding Status Report on Davis Besse Analyses. (11 page(s), 10/25/2002)
- ML031110235 - E-mail from M. Kirk to R. Bass, regarding permanent set measured in DB clad. (1 page(s), 10/29/2002)
- ML031110241 - E-mail from G. Demoss to M. Kirk, regarding Davis Besse. (1 page(s), 10/29/2002)
- ML031110247 - E-mail from W. Cullen to koc, regarding industry cooperation phone call. (9 page(s), 10/30/2002)
- ML031110283 - E-mail from W. Cullen to R, Tregoning, regarding BAC Data. (9 page(s), 10/31/2002)
- ML031110290 - E-mail for R. Tregoning to W. Cullen, regarding cladding corrosion. (1 page(s), 10/31/2002)
- ML031110297 - E-mail from R. Tregoning to R. Bass, regarding DB uncertainty analysis. (19 page(s), 11/4/2002)
- ML031110302 - E-mail from H. Nieh to R. Blough regarding emerging issue at Davis Besse. (1 page(s), 3/8/2002)
- ML031110309 - Memo to R. Tregoning from P. Williams, regarding status report on Davis Besse Analyses. (17 page(s), 11/8/2002)
- ML031110242 - E-mail from P. Williams to RLT, regarding DB Analysis Status report for November 8, 2002. (21 page(s), 11/8/2002)
- ML031120666 - E-mail from R. Tregoning to J. Torres, regarding permanent set measured in DB Clad. (19 page(s), 11/27/2002)
- ML031110250 - E-mail from D. Nelson to S. Long, regarding meeting summary concerning Davis Besse CRDM nozzle leakage expectations. (3 page(s), 4/26/2002)
- ML031110253 - Responses to comments raised by Ellis Merschoff via e-mail on 08/30/02, regarding ORNL stress analysis of Davis Besse Corrosion Wastage. (3 page(s), 4/8/2003)
- ML031110254 - E-mail from M. Mayfield to E. Merschoff, regarding response to comments on Davis Besse Head Analysis. (4 page(s), 9/6/2002)
- ML031110255 - Note to Ellis from Mike regarding report concerning Davis Besse. (2 page(s), 4/8/2003)
- ML031110256 - 7/24 - 25/2002 Davis Besse Lessons Learned Task Force Meeting. (14 page(s), 7/25/2002)
- ML031110257 - E-mail from R. Haag to J. Starefos, regarding inspection/review plan. (17 page(s), 6/20/2002)
- ML031110265 - 07/24-25/2002 Davis Besse Lessons Learned Task Force Meeting. (14 page(s), 7/24/2002)
- ML031110269 - E-mail from J. Starefos to H. Hackett, regarding DB LLRT List. (12 page(s), 7/25/2002)
- ML031110277 - E-mail from J. Starefos to A. Howell, regarding DB LLRT List. (11 page(s), 7/25/2002)
- ML031110282 - E-mail from A. Howell to LLTF, regarding DB LLRT List. (12 page(s), 7/29/2002)
- ML031110289 - 08/05-08/2002, Davis Besse Lessons Learned Task Force Meeting. (22 page(s), 8/5/2002)
- ML031110293 - E-mail from J. Starefos to R. Bywater, regarding info from last weeks meeting. (35 page(s), 8/12/2002)
- ML031110307 - 3.4.2 The NRC Failed to Provide Adequate Reactor Oversight Process Guidance. (5 page(s), 4/8/2003)
- ML031110328 - 3.4.2 The NRC Failed to Provide Adequate Reactor Oversight Process Guidance. (5 page(s), 4/8/2003)
- ML031110330 - E-mail from J. Donoghue to R. Bywater, regarding Appendix A. (9 page(s), 8/29/2002)
- ML031110333 - E-mail for J. Donoghue to R. Bywater, regarding APP A Update. (9 page(s), 9/3/2002)
- ML031110294 - E-mail from E. Raphael to J. Starefos, regarding draft document concerning Davis Besse lessons learned. (156 page(s), 8/20/2002)
- ML031120686 - E-mail from E. Raphael to J. Starefos, regarding draft report. (175 page(s), 8/29/2002)
- ML031110329 - 08/05-08/2002 Davis Besse Lessons Learned Task Force Meeting. (22 page(s), 8/8/2002)
- ML031110335 - Davis Besse Lessons Learned Task Force Meeting. (22 page(s), 8/7/2002)
- ML031110304 - To Steve from Mark. (1 page(s), 5/28/2002)
- ML031110315 - Outline of RES Activities to be Undertaken in Support of NRR Significance Determination Process Davis Besse Head Wastage Issue. (3 page(s), 6/5/2002)
- ML031110321 - E-mail from M. Kirk to S. Long, regarding failure model for DB. (1 page(s), 7/3/2002)
- ML031110322 - E-mail from M. Kirk to S. Long, regarding schedule for DB cavity growth analyses. (1 page(s), 7/8/2002)
- ML031110325 - E-mail from M. Kirk to S. Long, regarding DB cavity growth analysis - preliminary results. (1 page(s), 7/26/2002)
- ML031110344 - Memo from M. Kirk to N. Chokshi/S. Long, regarding status of ORNL Calculation of Burst Pressured for cavities that are larger than the cavity found at Davis Besse. (4 page(s), 8/5/2002)
- ML031110353 - E-mail from M. Kirk to S. Long, regarding Reference 3 to your draft RSD document for Davis Besse. (1 page(s), 8/12/2002)
- ML031110355 - E-mail from W. Cullen to S. Long, regarding SDP thought. (1 page(s), 8/14/2002)
- ML031110357 - E-mail from M. Kirk to S. Long, regarding clarification of focus of RSD. (1 page(s), 8/16/2002)
- ML031110358 - E-mail from W. Cullen to S. Long, regarding origin of ANL Results. (1 page(s), 8/16/2002)
- ML031110360 - E-mail from M. Kirk to S. Long, regarding more comments. (1 page(s), 8/20/2002)
- ML031110361 - E-mail from M. Kirk to S. Long, regarding clad flaw distribution for Davis Besse. (4 page(s), 9/10/2002)
- ML031110366 - E-mail from N. Chokshi to C. Santos, regarding proposed work scope for DB analyses. (13 page(s), 9/12/2002)
- ML031110371 - E-mail from M. Kirk to S. Long, regarding Deputy EDO briefing. (1 page(s), 9/13/2002)
- ML031110373 - E-mail from D. Jackson to C. Santos, regarding additional thoughts on DB Head Crack Testing. (2 page(s), 9/13/2002)
- ML031110377 - E-mail from J. Hixon to W. Cullen, regarding Ian Barnes Contact info. (1 page(s), 10/8/2002)
- ML031110381 - E-mail from J. Hixon to D. Dawes, regarding Besse head cladding. (1 page(s), 10/11/2002)
- ML031110383 - E-mail from J. Hixon to D. Jackson, regarding Davis Besse Cladding Update. (1 page(s), 10/12/2002)
- ML031110384 - E-mail from J. Hixon to GFD, Regarding Another Weld Data Sheet for the Davis Besse Reactor Head. (2 page(s), 10/12/2002)
- ML031110390 - E-mail from J. Hixon to A. Mendiola, Regarding Another Weld Data Sheet for the Davis Besse Reactor Head. (1 page(s), 10/12/2002)
- ML031110393 - E-mail from M. Leisure to MTK, regarding photos of cavity mold. (4 page(s), 10/23/2002)
- ML031110399 - E-mail from J. Hixon to J. Hopkins, regarding NRC request for weld data sheets for RVCH. (1 page(s), 10/29/2002)
- ML031110404 - E-mail from XU Hongqing to W. Cullen, regarding clad thickness. (3 page(s), 11/1/2002)
- ML031110405 - E-mail from N. Chokshi to S. Long, regarding SDP. (1 page(s), 11/4/2002)
- ML031110409 - E-mail from R. Tregoning to W. Cullen, regarding DB cracked clad, J-weld sectioning plan. (1 page(s), 11/7/2002)
- ML031110492 - Failure Criterion Development and Parametric Finite Element Analyses to Assess Margins for the Davis Besse RPV Head Corrosion. (57 page(s), 4/30/2002)
- ML031120692 - Advisory Committee on Reactor Safeguards Update of the Davis Besse Nuclear Power Station Reactor Pressure Vessel Closure Head Activities. (28 page(s), 6/6/2002)
- ML031110424 - E-mail from P. Baranowsky to D. Marksberry, after-thought regarding SECY on Industry Trends. (1 page(s), 3/18/2002)
- ML031110427 - E-mail from P. Baranowsky to D. Marksberry, regarding Davis Besse Risk Assessment Telecon. (1 page(s), 4/22/2002)
- ML031110430 - E-mail from G. Lanik to D. Marksberry, regarding ASP Insights. (5 page(s), 4/30/2002)
- ML031110432 - E-mail from D. Marksberry to P. Baranowsky, regarding definition of SDP Risk Question for Davis Besse Head Cavity. (1 page(s), 5/3/2002)
- ML031110434 - E-mail from E. Marksberry to P. Baranowsky, regarding definition of SDP Risk Question for the Davis Besse Head Cavity. (1 page(s), 5/6/2002)
- ML031110439 - E-mail from D. Marksberry to P. Baranowsky, regarding Davis Besse Mid Year Funding. (1 page(s), 6/4/2002)
- ML031110441 - E-mail from D. Marksberry to M. Harper, regarding BWR PWR FY 1996-2001. (1 page(s), 7/8/2002)
- ML031110445 - E-mail from D. Marksberry to G. Demoss, regarding Davis Besse Status. (1 page(s), 7/29/2002)
- ML031110452 - E-mail from G. Demoss to S. Long, regarding Davis Besse. (1 page(s), 8/12/2002)
- ML031110455 - E-mail from P. Baranowsky to G. Demoss, regarding Davis Besse peer review. (1 page(s), 8/13/2002)
- ML031110456 - E-mail from D. Marksberry to G. Demoss, regarding draft tack plan for RPV Head Penetration LER's. (1 page(s), 8/28/2002)
- ML031110471 - E-mail from M. Kirk to G. Demoss, regarding draft slides for 9-3-02 Ashok Brief on Davis Besse. (14 page(s), 8/30/2002)
- ML031110402 - E-mail from G. Demoss to D. Marksberry, regarding first cut at slides for Ashok. (22 page(s), 9/3/2002)
- ML031110406 - E-mail from G. Demoss to M. Cheok, regarding Ashok briefing on Davis Besse SDP. (2 page(s), 9/4/2002)
- ML031110412 - E-mail from G. Demoss to P. Baranowsky, regarding Davis Besse Meeting Canceled. (1 page(s), 9/11/2002)
- ML031110446 - E-mail from G. Demoss to P. Baranowsky, regarding Davis Besse ASP. (4 page(s), 9/13/2002)
- ML031110453 - E-mail from G. Demoss to P. Baranowsky, regarding nozzle cracking data for risk assessments. (1 page(s), 9/18/2002)
- ML031110457 - E-mail from D. Marksberry to P. O'Reilly, regarding input for Commissioner Periodics. (6 page(s), 9/19/2002)
- ML031110462 - E-mail from G. Demoss to M. kirk, regarding Davis Besse. (1 page(s), 9/19/2002)
- ML031110464 - E-mail from G. Demos to B. Brady, regarding Davis Besse. (1 page(s), 9/23/2002)
- ML031110465 - E-mail from G. Demoss to W. Cullen, regarding Davis Besse. (2 page(s), 9/25/2002)
- ML031110467 - E-mail from G. Demoss to B. Brady, regarding Davis Besse. (1 page(s), 9/25/2002)
- ML031110470 - E-mail from G. Demoss to B. Brady, regarding rough draft of comments. (3 page(s), 9/25/2002)
- ML031110481 - E-mail from G. Demoss to P. Baranowsky, regarding potential conflict on Friday Oct 11. (1 page(s), 9/27/2002)
- ML031110483 - E-mail from G. Demoss to M. Cheok, regarding draft Davis Besse comments. (3 page(s), 10/3/2002)
- ML031110486 - E-mail from G. Demoss to S. Long, regarding comments on the SDP. (3 page(s), 10/3/2002)
- ML031110490 - E-mail from G. Demoss to S. Long, regarding meeting with NRR. (1 page(s), 10/7/2002)
- ML031110493 - E-mail from G. Demoss to N. Chokshi, regarding Davis Besse. (1 page(s), 10/8/2002)
- ML031110495 - Draft memo to Collins from Thadani, regarding comments on draft response to request for Technical Assistance - Risk Assessment of Davis Besse Reactor Head Degradation. (5 page(s), 10/2/2002)
- ML031120695 - E-mail from W. Cullen to G. Demoss, regarding Davis Besse. (14 page(s), 10/8/2002)
- ML031110499 - E-mail from G. Demoss to M. Kirk, regarding Davis Besse. (1 page(s), 10/8/2002)
- ML031110500 - E-mail from M. Cheok to G. Demoss, regarding Davis Besse. (4 page(s), 10/10/2002)
- ML031110505 - E-mail from W. Cullen to G. Demoss, regarding HI All. (1 page(s), 10/10/2002)
- ML031110514 - E-mail from P. Baranowsky to G. Demoss, regarding UCS Letter on Davis Besse. (14 page(s), 10/15/2002)
- ML031110518 - E-mail from M. Kirk to S. Long, regarding MEM Analysis of Davis Besse. (1 page(s), 6/27/2002)