The U.S. Nuclear Regulatory Commission is in the process of rescinding or revising guidance and policies posted on this webpage in accordance with Executive Order 14151 Ending Radical and Wasteful Government DEI Programs and Preferencing, and Executive Order 14168 Defending Women From Gender Ideology Extremism and Restoring Biological Truth to the Federal Government. In the interim, any previously issued diversity, equity, inclusion, or gender-related guidance on this webpage should be considered rescinded that is inconsistent with these Executive Orders.

Appalachian Power Company

subscribe to page updates Image of Joshua Falls SMR Project
Who:   Appalachian Power Company (APCo)
What:   Pre-application activities associated with a future early site permit (ESP) application.
When:   December 2024 to Present - in pre-application period with plan for ESP submittal April 2027
Website:   https://appalachianpowersmr.com/

On this page:

Project Overview

The U.S. Nuclear Regulatory Commission (NRC) is currently engaged in pre-application activities with Appalachian Power Company (APCo) regarding a future ESP that would be at the company-owned Joshua Falls property in Campbell County, Virginia, for a small modular reactor (SMR) (gross electrical output (MWe) to be determined later).

Additional information on pre-application activities can be obtained from ADAMS using a search by Project No. 99902129.

To top of page

Regulatory Engagement Plan

On March 5, 2025, APCo submitted a non-proprietary notice of intent, regulatory engagement plan (REP) and response to Regulatory Issue Summary (RIS) 2020-02. The table below will give members of the public an opportunity to stay informed on APCo’s latest licensing plans.
 
Date Title
March 5, 2025 Notice of Intent to Pursue an Early Site Permit for Potential Reactor Siting at the Joshua Falls, Virginia, Site with Associated Regulatory Engagement Plan and Response to Regulatory Issue Summary 2020-02

To top of page

Project Related Documents

Date Title
December 13, 2024 Appalachian Power Company (APCo) Quality Assurance Program Description (QAPD) Pre-Submittal Public Meeting
January 28, 2025 Quality Assurance Program Description for Nuclear Quality Assurance Program, – APCo ESP QAPD, Revision 0
February 28, 2025 NRC Staff’s Completeness Determination for Appalachian Power Tropical Report, "Quality Assurance Program Description for Nuclear Quality Assurance Program APCo ESP QAPD Revision 0"

To top of page

Contacts

Contacts for Appalachian Power Company (APCo) Pre-application Activities
Lead Project Manager
Associate Project Manager
Prosanta Chowdhury
Thomas Hayden