Clinch River Nuclear Site Application

Graphic provided by Tennessee Valley Authority
On this page:
Project Overview
The U.S. Nuclear Regulatory Commission (NRC) is currently engaged in review activities for Tennessee Valley Authority’s (TVA) construction permit application for the Clinch River Nuclear Site in Oak Ridge, Tennessee. This comes after the NRC’s issuance of the site’s Early Site Permit (ESP) in 2019.
Additional information on pre-application activities can be obtained from ADAMS using a search by docket number 99902056.
Additional information regarding the ESP can be found at Clinch River Nuclear Site Early Site Permit webpage.

Topical Reports

Public Meeting Materials and Meeting Summaries

Audits and Audit Reports

Exemption Requests

Key Milestones
Milestones |
Completion Date
Actual - A
Target - T |
Environmental Report Submitted (Part One) |
April 28, 2025 – A |
Preliminary Safety Analysis Report Submitted (Part Two) |
May 20, 2025 – A |
Environmental Report Acceptance Review Completion (Decision Letter Issued) |
June 12, 2025 – A |
Preliminary Safety Analysis Report Acceptance Review Completion |
July 11, 2025 – T |
Docketing Decision Letter
Issued/Acceptance Review Complete |
July 11, 2025 – T |
Review Schedule Established/Schedule Letter Issued to Applicant |
TBD |
Safety Review* |
TBD |
Environmental Review* |
TBD |
Hearing |
TBD |
Construction Permit Decision |
TBD |