The documents listed below document the NRC staff's assessment of the NGNP white papers and related key licensing issues.
This page includes links to files in non-HTML format. See Plugins, Viewers, and Other Tools for more information.
| Date | Description |
|---|---|
| 07/17/14 | NRC Letter to DOE on Assessment of NGNP Key Licensing Issues |
| 06/20/13 | NRC Staff Response to ACRS Letter on NGNP Key Licensing Issues |
| 05/15/13 | ACRS Letter to NRC Staff on NGNP Key Licensing Issues |
| 05/09/13 | ACRS Full Committee Meeting on NGNP, Transcripts |
| 04/09/13 | ACRS Subcommittee Meeting on NGNP, Transcripts |
| 03/11/13 | NGNP Draft Updated FQ-MST Assessment Report (Rev. 1) |
| 03/08/13 | NGNP Draft Updated DID-LBE-SSC Assessment Report (Rev. 1) |
| 03/08/13 | NGNP Draft Summary Feedback on Four Key Licensing Issues |
| 03/07/13 | Next Generation Nuclear Plant - Preapplication Assessment of Key Licensing Issues |
| 05/09/12 | High Temperature Materials Assessment Report |
| 02/15/12 | Assessment of White Papers on Fuel Qualification, Mechanistic Source Terms, Defense-In-Depth Approach, Licensing Basis Event Selection, and Safety Classification of Systems, Structures, and Components |
| 02/15/12 | NRC Letter to DOE on Key Issues for NGNP Licensing |