The following table summarizes the key milestones in the schedule that the U.S. Nuclear Regulatory Commission (NRC) has established for its review of the application that Uranium One submitted to obtain a license for its Ludeman In Situ Recovery site.
| Key Milestones | Completion Date Actual - A Target - T |
|---|---|
| Application Received | 12/06/11 |
| License Application in ADAMS | 01/03/12 – A |
| Acknowledgement email Sent (11 days from receipt) | 12/19/11 – A |
| Acceptance Review | |
Application accepted for review | 05/06/12 – A |
Acceptance Review Complete (60 days from Acceptance Review Begins) | 05/16/12 – A |
| Safety Review | |
Safety RAIs issued | 01/15/13 – A |
Licensee submits major "change of design" request deferring amended application submission for RAI response revisions | 04/10/13 – A |
RAIs responses received in full | 03/13/14 – A |
Second round of Targeted RAIs submitted sent | 12/01/14 – A |
Targeted RAI responses received | 06/08/15 – A |
Schedule letter issued | 03/28/17 – A |
Revised Application (Technical Report) including "Change of Design" modification received | 06/30/17 – A |
Schedule letter issued | 08/25/17 – A |
Final SER Complete | 03/01/18 – A |
| Environmental Review | |
Requests for RAIs to Applicant | 01/19/13 – A |
RAI responses received in full | 03/13/14 – A |
Revised Application (Environmental Report) including "Change of Design" modification received | 08/25/17 – A |
Draft Environmental Assessment (EA) issued | 02/27/18* – A |
Final EA Issued | 08/02/18** – A |
| Issue License Amendment and SER Rev 1 | 08/24/18 – A |
*Based on August 31, 2017 submittal of revised Environmental Report that contained a change of design
**Issuance of the Final EA is contingent upon completion of the National Historic Preservation Act (NHPA) Section 106 consultation
Information on Federal Register notices for receipt of the application and opportunity to request a hearing or petition to intervene can be found on the Hearing Opportunities page.