Home > NRC Library > ADAMS Public Documents
Further response to FOIA request for records generated in connection w/any rept or study of basemat cracking & water leakage & seepage problems at facility.Forwards App C documents.App D documents available in PDR.
Accession Number: ML17198A241
Date Released: Wednesday, May 20, 2020
Package Contents
The following links on this page are to Adobe Portable Document Format (PDF) files. To obtain a free viewer for displaying this format, see our Plugins, Viewers, and Other Tools.
- ML20127B594 - Further response to FOIA request for records generated in connection w/any rept or study of basemat cracking & water leakage & seepage problems at facility.Forwards App C documents.App D documents available in PDR. (44 page(s), 2/22/1985)
- ML20127B878 - Issue D to Procedure QCIP-4, "Control of Concrete Matls & Mixes." (12 page(s), 11/29/1975)
- ML20127B788 - Responds to encl City Council Resolution 84-193 adopted on 840517.NRC recently established coordinating team to gather necessary info to make remaining licensing decisions on facility.Press release dtd 840404 encl. (5 page(s), 5/31/1984)
- ML20127B745 - Rev 4 to Special Process Procedure W-SP-6, "Bending & Straightening of Reinforcing Bars Partially Embedded in Concrete & Placing of Bars in Hardened Concrete." (4 page(s), 10/11/1977)
- ML20127B921 - Rev 5 to Site Insp & Test Procedure W-SITP-12, "Backfill & Compaction Insp." (7 page(s), 7/9/1976)
- ML17198A250 - Rev 5 to Site Insp & Test Procedure W-SITP-4, "Reinforcing Steel - Handling,Storage,Installing,Cadwelding & Mod Insp." (10 page(s), 12/3/1976)
- ML20127C180 - Rev 0 to Nuclear Project Operating Procedure POP-N-713, "Use of Insp Cleanup Repts." (17 page(s), 12/8/1975)
- ML20127B723 - Issue A to Procedure QCIP-2, "Soils Control." (25 page(s), 9/17/1975)
- ML17198A245 - Rev 0 to Special Process Procedure W-SP-3, "Disposal of Unused Cadweld Powder." (3 page(s), 11/6/1975)
- ML20127C189 - Rev 1 to Nuclear Project Operating Procedure POP-N-713, "Use of Discrepancy Repts." (9 page(s), 3/24/1976)
- ML20127C148 - Rev 0 to Nuclear Project Operating Procedure POP-N-702, "Personnel Training,Qualification & Certification." (6 page(s), 10/15/1975)
- ML20127C019 - Rev 1 to Special Process Procedure W-SP-17, "Addl Grouting of 499S02-10B." (11 page(s), 4/19/1977)
- ML20127C206 - Rev 3 to Nuclear Project Operating Procedure POP-N-713, "Use of Discrepancy Repts." Related info encl. (68 page(s), 2/3/1978)
- ML17198A249 - Issue F to Procedure QCIP-9, "Insp of Concrete Reinforcing Steel Mechanical Splices (Cadwelds)." (10 page(s), 9/3/1976)
- ML20127C039 - Rev 1 to Special Process Procedure W-SP-20, "Concrete Core Drilling." (5 page(s), 8/28/1978)
- ML20127B665 - Issue B to Procedure CP-703, "Batch Plant Activities & Operations." (22 page(s), 2/24/1983)
- ML17198A240 - Issue B to Procedure CP-699, "Handling,Storing,Installing, Cadwelding & Mod of Reinforcing Steel." (5 page(s), 3/30/1982)
- ML20127B854 - Issue H to Procedure QCIP-2, "Soils Control." (14 page(s), 12/6/1977)
- ML20127B989 - Addendum 1 to Rev 3 to Special Process Procedure W-SP-16, "Repair,Insp,Documentation & Verification of Placement 499S03-19." (5 page(s), 4/13/1977)
- ML20127B687 - Amend 1 to Issue A to Procedure CP-803, "Excavation & Backfill." (8 page(s), 4/1/1984)
- ML20127C030 - Rev 0 to Site Insp & Test Procedure W-SITP-7, "Insp of Concrete Placing,Curing,Finishing & Repair." (9 page(s), 11/24/1975)
- ML20127C080 - Rev 5 to Nuclear Project Operating Procedure POP-N-300, "Control of Engineering Documents." (17 page(s), 3/19/1980)
- ML20127B658 - Issue C to Procedure QCIP-7, "Insp of Concrete Placement, Curing & Finishing." (7 page(s), 12/19/1975)
- ML20127B608 - "Clam Shell Filter Blanket Test Rept." (244 page(s), 11/30/1975)
- ML20127C119 - Rev 5 to Site Insp & Test Procedure W-SITP-7, "Insp of Concrete Placing,Curing,Finishing & Repair." (10 page(s), 2/4/1977)
- ML20127B825 - Issue F to Procedure QCIP-2, "Soils Control." (16 page(s), 10/15/1976)
- ML20127B967 - Addendum 1 to Rev 1 to Special Process Procedure W-SP-16, "Repair,Insp,Documentation & Verification of Placement 499S03-19." (4 page(s), 3/18/1977)
- ML20127C174 - Rev 2 to Site Insp & Test Procedure W-SITP-8, "Waterstop Insp." (5 page(s), 11/13/1975)
- ML20127C027 - Rev 2 to Special Process Procedure W-SP-17, "Addl Grouting of 499S02-10B." (12 page(s), 4/22/1977)
- ML20127B925 - Issue F to Procedure QCIP-4, "Control of Concrete Matls & Mixes." (11 page(s), 3/19/1976)
- ML20127B844 - Rev 4 to Site Insp & Test Procedure W-SITP-8, "Waterstop Insp." (6 page(s), 10/24/1978)
- ML20127C032 - Issue F to Procedure QCIP-6, "Concrete Preplacement Insp." (11 page(s), 11/5/1976)
- ML20127B883 - Rev 0 to Special Process Procedure W-SP-8, "Backfill Test Fill." (7 page(s), 5/27/1976)
- ML17198A264 - Rev 3 to Const Work Procedure W-WP-4, "Handling,Storing, Installing,Cadwelding & Mod of Reinforcing Steel." (4 page(s), 11/6/1975)
- ML20127C316 - Rev 5 to Const Work Procedure W-WP-7, "Concrete Placing, Curing,Finishing & Repairs." (13 page(s), 5/7/1976)
- ML20127C096 - Rev 4 to Nuclear Project Operating Procedure POP-N-301, "Const Engineering." (22 page(s), 5/17/1978)
- ML20127C222 - Discusses availability of info on shear that is applicable to facility basemat.No excuse found for departing radically from code provisions,but advantage should be taken of provisions in code allowing increase in shear strength. (16 page(s), 5/14/1984)
- ML17198A257 - Rev 0 to Site Insp & Test Procedure W-SITP-4, "Reinforcing Steel - Handling,Storage,Installing,Cadwelding & Mod Insp." (10 page(s), 10/13/1975)
- ML20127B802 - Rev 2 to Special Process Procedure W-SP-7, "Repair & Curing of Concrete Repair for Placement 499S02-10B." (24 page(s), 7/28/1976)
- ML17198A243 - Rev 2 to Special Process Procedure W-SP-3, "Disposal of Unused Cadweld Powder." (2 page(s), 3/29/1976)
- ML20127C023 - Rev 0 to Site Insp & Test Procedure W-SITP-16, "Insp of Concrete Mud Slab Placing,Curing,Finishing & Repair." (4 page(s), 10/14/1975)
- ML20127B715 - Rev 1 to Special Process Procedure W-SP-6, "Bending & Straightening of Reinforcing Bars Partially Embedded in Concrete & Placing of Bars in Hardened Concrete." (4 page(s), 5/13/1976)
- ML20127B637 - "QA Program for Phase I Concrete Const,Waterford Steam Electric Station Unit 3." Related info encl. (52 page(s), 6/18/1975)
- ML20127C245 - Rev 0 to Const Work Procedure W-WP-7, "Concrete Placing, Curing,Finishing & Repairs." (11 page(s), 11/21/1975)
- ML20127B622 - "Louisiana Power & Light Co,Waterford Steam Electric Station Unit 3,Allowable Bearing Pressure." Related info encl. (2019 page(s), 4/30/1977)
- ML20127B912 - Rev 4 to Site Insp & Test Procedure W-SITP-12, "Backfill & Compaction Insp." (7 page(s), 6/25/1976)
- ML20127B895 - Rev 1 to Special Process Procedure W-SP-8, "Backfill Test Fill." (6 page(s), 6/9/1976)
- ML20127B962 - Rev 8 to Site Insp & Test Procedure W-SITP-12, "Backfill & Compaction Insp." (6 page(s), 3/13/1978)
- ML20127C011 - Issue D to Procedure QCIP-6, "Concrete Preplacement Insp." (10 page(s), 1/21/1976)
- ML20127C310 - Rev 4 to Const Work Procedure W-WP-7, "Concrete Placing, Curing,Finishing & Repairs." (12 page(s), 4/30/1976)
- ML20127B848 - Rev 5 to Special Process Procedure W-SP-7, "Repair & Curing of Concrete Repair for Placement 499S02-10B." (26 page(s), 8/26/1976)
- ML17198A259 - Rev 2 to Site Insp & Test Procedure W-SITP-4, "Reinforcing Steel - Handling,Storage,Installing,Cadwelding & Mod Insp." (10 page(s), 10/24/1975)
- ML20127B695 - Rev 0 to Special Process Procedure W-SP-6, "Bending & Straightening of Reinforcing Bars Partially Embedded in Concrete & Placing of Bars in Hardened Concrete." (3 page(s), 4/26/1976)
- ML20127C327 - Rev 6 to Const Work Procedure W-WP-7, "Concrete Placing, Curing,Finishing & Repairs." (14 page(s), 5/24/1976)
- ML20127C056 - Rev 1 to Site Insp & Test Procedure W-SITP-7, "Insp of Concrete Placing,Curing,Finishing & Repair." (9 page(s), 12/5/1975)
- ML17198A244 - Issue C to Procedure QCIP-9, "Insp of Concrete Reinforcing Steel Mechanical Splices (Cadwelds)." (9 page(s), 9/5/1975)
- ML20127B707 - Issue A to Procedure QCIP-1, "Density Control of Shell." (7 page(s), 9/17/1975)
- ML20127B903 - Issue E to Procedure QCIP-4, "Control of Concrete Matls & Mixes." (11 page(s), 1/14/1976)
- ML20127B972 - Issue C to Procedure QCIP-6, "Concrete Preplacement Insp." (12 page(s), 11/29/1975)
- ML17198A252 - Rev 8 to Site Insp & Test Procedure W-SITP-4, "Reinforcing Steel - Handling,Storage,Installing,Cadwelding & Mod Insp." (13 page(s), 2/28/1978)
- ML20127B916 - Addendum 1 to Rev 1 to Special Process Procedure W-SP-13, "Repair,Insp,Documentation & Verification of Basemat Foundation Beneath Columns H10A & H11A Lying on Placement 19." (11 page(s), 10/7/1976)
- ML20127C199 - Rev 3 to Site Insp & Test Procedure W-SITP-8, "Waterstop Insp." (5 page(s), 2/2/1978)
- ML20127B862 - Rev 6 to Special Process Procedure W-SP-7, "Repair & Curing of Concrete Repair for Placement 499S02-10B." (27 page(s), 9/16/1976)
- ML17198A261 - Rev 4 to Site Insp & Test Procedure W-SITP-4, "Reinforcing Steel - Handling,Storage,Installing,Cadwelding & Mod Insp." (11 page(s), 11/11/1975)
- ML20127C059 - Issue G to Procedure QCIP-6, "Concrete Preplacement Insp." (9 page(s), 4/11/1977)
- ML20127B998 - Rev 4 to Special Process Procedure W-SP-16, "Repair,Insp, Documentation & Verification of Placement 499S03-19." (10 page(s), 7/1/1977)
- ML17198A248 - Issue D to Procedure QCIP-9, "Insp of Concrete Reinforcing Steel Mechanical Splices (Cadwelds)." (10 page(s), 2/19/1976)
- ML20127C304 - Rev 3 to Const Work Procedure W-WP-7, "Concrete Placing, Curing,Finishing & Repairs." (12 page(s), 3/5/1976)
- ML20127B761 - Issue C to QCIP-2, "Soils Control." (14 page(s), 6/29/1976)
- ML20127C084 - Rev 3 to Site Insp & Test Procedure W-SITP-7, "Insp of Concrete Placing,Curing,Finishing & Repair." (9 page(s), 9/20/1976)
- ML20127B792 - Rev 1 to Special Process Procedure W-SP-7, "Repair & Curing of Concrete Repair for Placement 499S02-10B." (11 page(s), 5/31/1976)
- ML17198A247 - Amend 1 to Issue G to Procedure QCIP-9, "Insp of Concrete Reinforcing Steel,Mechanical Splices (Cadwelds)." Amend deletes procedure in entirety. (9 page(s), 3/16/1984)
- ML20127B736 - Rev 3 to Special Process Procedure W-SP-6, "Bending & Straightening of Reinforcing Bars Partially Embedded in Concrete & Placing of Bars in Hardened Concrete." (4 page(s), 6/7/1977)
- ML20127C047 - Rev 1 to Site Insp & Test Procedure W-SITP-16, "Insp of Concrete Mud Slab Placing,Curing,Finishing & Repair." (4 page(s), 10/20/1975)
- ML20127B741 - Issue B to Procedure QCIP-2, "Soils Control." (26 page(s), 10/14/1975)
- ML20127C087 - Rev 0 to Nuclear Project Operating Procedure POP-N-301, "Const Engineering." (21 page(s), 10/15/1975)
- ML17198A256 - Rev 11 to Site Insp & Test Procedure W-SITP-4, "Reinforcing Steel - Handling,Storage,Installing,Cadwelding & Mod Insp." (17 page(s), 1/9/1979)
- ML20127C360 - Rev 2 to Const Work Procedure W-WP-8, "Handling,Installation & Field Repair of Waterstops." (7 page(s), 5/3/1977)
- ML20127C386 - Rev 0 to Const Work Procedure W-WP-12, "Backfilling & Compaction." (7 page(s), 4/7/1976)
- ML20127B604 - Issue A to Procedure CP-203, "Clam Shell Filter Blanket Test Fill." (27 page(s), 9/22/1975)
- ML17198A262 - Rev 2 to Const Work Procedure W-WP-4, "Handling,Storage, Installing,Cadwelding & Mod of Reinforcing Steel." (8 page(s), 10/24/1975)
- ML20127B615 - "Mat 10B Placement Rept." Related info encl. (214 page(s), 5/31/1976)
- ML20127B828 - Rev 3 to Special Process Procedure W-SP-7, "Repair & Curing of Concrete Repair for Placement 499S02-10B." (24 page(s), 8/9/1976)
- ML20127B645 - Discusses insp of dewatering & excavation activities & const of common foundation mat for facility.Site preparation & placement of mat performed in accordance w/approved specs, procedures & regulations. (2 page(s), 11/16/1983)
- ML20127B939 - Rev 6 to Site Insp & Test Procedure W-SITP-12, "Backfill & Compaction Insp." (7 page(s), 8/3/1976)
- ML17198A260 - Rev 3 to Site Insp & Test Procedure W-SITP-4, "Reinforcing Steel - Handling,Storage,Installing,Cadwelding & Mod Insp." (11 page(s), 11/6/1975)
- ML20127C269 - Rev 2 to Const Work Procedure W-WP-7, "Concrete Placing, Curing,Finishing & Repairs." (11 page(s), 12/18/1975)
- ML20127B985 - Addendum 1 to Rev 2 to Special Process Procedure W-SP-16, "Repair,Insp,Documentation & Verification of Placement 499S03-19." (4 page(s), 4/13/1977)
- ML20127C016 - Rev 3 to Site Insp & Test Procedure W-SITP-5, "Embedded Items - Handling,Storage & Installation Insp." (6 page(s), 10/19/1976)
- ML20127C160 - Rev 1 to Site Insp & Test Procedure W-SITP-8, "Waterstop Insp." (6 page(s), 10/27/1975)
- ML17198A246 - Issue G to Procedure QCIP-9, "Insp of Concrete Reinforcing Steel Mechanical Splices (Cadwelds)." (10 page(s), 12/8/1976)
- ML20127C050 - Rev 0 to Site Insp & Test Procedure W-SITP-2, "Clam Shell Filter Blanket Insp." (5 page(s), 10/13/1975)
- ML20127B952 - Rev 7 to Site Insp & Test Procedure W-SITP-12, "Backfill & Compaction Insp." (6 page(s), 1/25/1977)
- ML20127C003 - Issue B to Procedure QCIP-6, "Concrete Preplacement Insp." (9 page(s), 9/12/1975)
- ML20127B947 - Issue C to Procedure QCIP-5, "Control of Concrete Mixing & Transporting." (11 page(s), 2/27/1976)
- ML20127C366 - Rev 4 to Const Work Procedure W-WP-8, "Handling, Installation & Field Repair of Waterstops." (6 page(s), 2/2/1978)
- ML20127C355 - Rev 1 to Const Work Procedure W-WP-8, "Handling & Installation of Waterstops." (7 page(s), 10/27/1975)
- ML20127B908 - Rev 1 to Special Process Procedure W-SP-9, "Testing Reinforcing Steel Subjected to Cold Rebending." (6 page(s), 6/18/1976)
- ML17198A242 - Issue A to Procedure CP-699, "Handling,Storing,Installing, Cadwelding & Mod of Reinforcing Steel." (2 page(s), 2/22/1985)
- ML20127B866 - Rev 0 to Site Insp & Test Procedure W-SITP-12, "Backfill & Compaction Insp." (7 page(s), 12/15/1975)
- ML20127B671 - Amend 1 to Issue C to Procedure QCIP-8, "Receiving,Insp, Storage & Testing of Concrete Reinforcing Steel." (11 page(s), 3/16/1984)
- ML20127C391 - Rev 1 to Const Work Procedure W-WP-17, "Housekeeping." (5 page(s), 6/8/1976)
- ML20127B777 - Rev 0 to Special Process Procedure W-SP-7, "Repair & Curing of Concrete Repair for Placement 499S02-10B." (11 page(s), 5/12/1976)
- ML20127C102 - Issue D to Procedure QCIP-7, "Insp of Concrete Placement, Curing & Finishing." (12 page(s), 1/12/1976)
- ML17198A254 - Rev 9 to Site Insp & Test Procedure W-SITP-4, "Reinforcing Steel - Handling,Storage,Installing,Cadwelding & Mod Insp." (15 page(s), 10/4/1978)
- ML20127B839 - Issue G to Procedure QCIP-2, "Soils Control." (16 page(s), 1/3/1977)
- ML20127B719 - Rev 2 to Special Process Procedure W-SP-6, "Bending & Straightening of Reinforcing Bars Partially Embedded in Concrete & Placing of Bars in Hardened Concrete." (4 page(s), 10/13/1976)
- ML17198A258 - Rev 1 to Site Insp & Test Procedure W-SITP-4, "Reinforcing Steel - Handling,Storage,Installing,Cadwelding & Mod Insp." (10 page(s), 10/21/1975)
- ML20127C075 - Rev 4 to Nuclear Project Operating Procedure POP-N-300, "Control of Engineering Documents." (13 page(s), 1/19/1979)
- ML20127B992 - Rev 4 to Site Insp & Test Procedure W-SITP-14, "Welding Insp." (14 page(s), 2/20/1980)
- ML20127C145 - Rev 0 to Site Insp Procedure W-SITP-8, "Waterstop Insp." (6 page(s), 10/13/1975)
- ML17198A265 - Rev 4 to Const Work Procedure W-WP-4, "Handling,Storing, Installing,Cadwelding & Mod of Reinforcing Steel." (5 page(s), 11/14/1975)
- ML20127B900 - Rev 3 to Site Insp & Test Procedure W-SITP-12, "Backfill & Compaction Insp." (7 page(s), 4/19/1976)
- ML17198A251 - Rev 6 to Site Insp & Test Procedure W-SITP-4, "Reinforcing Steel - Handling,Storage,Installing,Cadwelding & Mod Insp." (11 page(s), 12/22/1976)
- ML20127C111 - Rev 5 to Nuclear Project Operating Procedure POP-N-301, "Const Engineering." (21 page(s), 7/14/1978)
- ML20127C140 - Rev 1 to Nuclear Project Operating Procedure POP-N-702, "Personnel Training,Qualification & Certification." (6 page(s), 1/15/1976)
- ML20127B755 - Rev 5 to Special Process Procedure W-SP-6, "Bending & Straightening of Reinforcing Bars Partially Embedded in Concrete & Placing of Bars in Hardened Concrete." (4 page(s), 5/23/1979)
- ML20127C093 - Rev 4 to Site Insp & Test Procedure W-SITP-7, "Insp of Concrete Placing,Curing,Finishing & Repair." (10 page(s), 1/13/1977)
- ML20127B887 - Rev 1 to Site Insp & Test Procedure W-SITP-12, "Backfill & Compaction Insp." (6 page(s), 3/16/1976)
- ML20127B782 - Issue D to Procedure QCIP-2, "Soils Control." (14 page(s), 8/20/1976)
- ML20127C008 - Rev 0 to Special Process Procedure W-SP-17, "Addl Grouting of 499S02-10B." (8 page(s), 3/21/1977)
- ML20127C123 - Rev 0 to Nuclear Project Operating Procedure POP-N-605, "Introduction & Training." (6 page(s), 10/15/1975)
- ML20127C261 - Rev 1 to Const Work Procedure W-WP-7, "Concrete Placing, Curing,Finishing & Repairs." (10 page(s), 11/26/1975)
- ML20127C129 - Issue B to Procedure QCIP-7, "Insp of Concrete Placement, Curing & Finishing." (16 page(s), 9/12/1975)
- ML20127C064 - Rev 1 to Site Insp & Test Procedure W-SITP-2, "Clam Shell Filter Blanket Insp." (5 page(s), 10/15/1975)
- ML20127B943 - Addendum 3 to Rev 0 to Special Process Procedure W-SP-13, "Repair,Insp & Documentation of Basemat Foundation Beneath Columns H10A & H11A Lying on Placement 19." (9 page(s), 10/25/1976)
- ML20127C135 - Rev 1 to Const Work Procedure W-WP-2, "Clam Shell Filter Blanket Placement." (5 page(s), 10/15/1975)
- ML17198A255 - Rev 10 to Site Insp & Test Procedure W-SITP-4, "Reinforcing Steel - Handling,Storage,Installing,Cadwelding & Mod Insp." (15 page(s), 12/11/1978)
- ML20127B930 - Rev 2 to Special Process Procedure W-SP-13, "Repair,Insp, Documentation & Verification of Basemat Foundation Beneath Columns H10A & H11A Lying on Placement 19." (14 page(s), 9/30/1976)
- ML20127B871 - Rev 7 to Special Process Procedure W-SP-7, "Repair & Curing of Concrete Repair for Placement 499S02-10B." (27 page(s), 7/1/1977)
- ML20127B960 - Rev 0 to Special Process Procedure W-SP-16, "Repair,Insp, Documentation & Verification of Placement 499S03-19." (10 page(s), 12/31/1976)
- ML20127C156 - Rev 2 to Nuclear Project Operating Procedure POP-N-702, "Personnel Training,Qualification & Certification." (7 page(s), 3/5/1976)
- ML20127C107 - Rev 0 to Const Work Procedure W-WP-2, "Clam Shell Filter Blanket Placement." (5 page(s), 10/13/1975)
- ML20127B771 - Issue A to Procedure QC 4.0-4, "Concrete Preplacement Insp." (12 page(s), 1/25/1974)
- ML20127C069 - Rev 2 to Site Insp & Test Procedure W-SITP-7, "Insp of Concrete Placing,Curing,Finishing & Repair." (8 page(s), 5/7/1976)
- ML20127B678 - Discusses control & distribution of facility tracking sys document. (3 page(s), 5/17/1984)
- ML20127C165 - Rev 3 to Nuclear Project Operating Procedure POP-N-702, "Personnel Training,Qualification & Certification." (7 page(s), 10/5/1976)
- ML20127C168 - Rev 0 to Const Work Procedure W-WP-4, "Handling,Storage, Installation & Mod of Rebar." (7 page(s), 9/30/1975)
- ML20127C433 - Rev 2 to Nuclear Project Operating Procedure POP-N-300, "Control of Engineering Documents." (14 page(s), 12/20/1976)
- ML20127C421 - Rev 0 to Nuclear Project Operating Procedure POP-N-300, "Control of Engineering Documents." (13 page(s), 10/15/1975)