Power Reactor Status Report for March 09, 2024

UNEVALUATED INFORMATION PROVIDED BY THE FACILITY

On this page:

Region 1

Unit Power Down Reason or Comment Change in Report (*) Scrams (#)
Beaver Valley 1 100
Beaver Valley 2 100
Calvert Cliffs 1 100
Calvert Cliffs 2 100
FitzPatrick 100
Ginna 100
Hope Creek 1 92 Coastdown To Refueling Outage *
Limerick 1 97 Coastdown To Refueling Outage
Limerick 2 100
Millstone 2 100
Millstone 3 100
Nine Mile Point 1 100
Nine Mile Point 2 0 2024-03-03 Refueling Outage
Peach Bottom 2 100
Peach Bottom 3 100
Salem 1 100
Salem 2 100
Seabrook 1 100 One Down Power Contingency to 1100 Mwe
Susquehanna 1 94 Coastdown To Refueling Outage *
Susquehanna 2 100

Region 2

Unit Power Down Reason or Comment Change in Report (*) Scrams (#)
Browns Ferry 1 70 Reduced Power For Maintenance *
Browns Ferry 2 100
Browns Ferry 3 0 2024-02-17 Refueling Outage
Brunswick 1 0 2024-02-12 Refueling Outage
Brunswick 2 100
Catawba 1 100
Catawba 2 100
Farley 1 100
Farley 2 100
Harris 1 100
Hatch 1 0 2024-02-04 Refueling Outage
Hatch 2 100
McGuire 1 100
McGuire 2 100
North Anna 1 0 2024-03-03 Refueling Outage
North Anna 2 100
Oconee 1 100
Oconee 2 100
Oconee 3 100
Robinson 2 100
Saint Lucie 1 0 2024-03-09 Refueling Outage *
Saint Lucie 2 100
Sequoyah 1 95 Coastdown To Refueling Outage
Sequoyah 2 100
Summer 100
Surry 1 100
Surry 2 100
Turkey Point 3 100
Turkey Point 4 100
Vogtle 1 100
Vogtle 2 100
Vogtle 3 100
Vogtle 4 0 2024-03-06 Planned Maintenance Outage
Watts Bar 1 100
Watts Bar 2 100 *

Region 3

Unit Power Down Reason or Comment Change in Report (*) Scrams (#)
Braidwood 1 100
Braidwood 2 100
Byron 1 100
Byron 2 100
Clinton 100 *
D.C. Cook 1 100
D.C. Cook 2 100
Davis-Besse 0 2024-03-03 Refueling Outage
Dresden 2 100
Dresden 3 87 Reduced Power For Rod Pattern Adjustment *
Fermi 2 100
LaSalle 1 12 Plant Startup *
LaSalle 2 100
Monticello 100
Perry 1 100
Point Beach 1 100
Point Beach 2 100
Prairie Island 1 100
Prairie Island 2 48 Holding power *
Quad Cities 1 100
Quad Cities 2 92 Coastdown To Refueling Outage *

Region 4

Unit Power Down Reason or Comment Change in Report (*) Scrams (#)
Arkansas Nuclear 1 100
Arkansas Nuclear 2 100
Callaway 100
Columbia Generating Station 100
Comanche Peak 1 100
Comanche Peak 2 100
Cooper 100
Diablo Canyon 1 100
Diablo Canyon 2 100
Grand Gulf 1 0 2024-03-02 Refueling Outage
Palo Verde 1 100
Palo Verde 2 100
Palo Verde 3 100
River Bend Station 1 100
South Texas 1 100
South Texas 2 100
Waterford 3 100
Wolf Creek 1 100

* - Power Reactor Status Report change within past 24 hours
# - Number of reactor scrams or trips within past 24 hours

Notes:
  • Reactor status data collected between 4 a.m. and 8 a.m. each day.
  • All times are based on eastern time.