Power Reactor Status Report for December 30, 2012
UNEVALUATED INFORMATION PROVIDED BY THE FACILITY
On this page:
Region 1
| Unit | Power | Down | Reason or Comment | Change in report (*) | Number of Scrams (#) |
|---|---|---|---|---|---|
| Beaver Valley 1 | 100 | ||||
| Beaver Valley 2 | 100 | ||||
| Calvert Cliffs 1 | 100 | ||||
| Calvert Cliffs 2 | 100 | ||||
| FitzPatrick | 100 | ||||
| Ginna | 100 | ||||
| Hope Creek 1 | 100 | ||||
| Indian Point 2 | 100 | 138 KV FEEDER (LINE 33332) OOS | |||
| Indian Point 3 | 100 | 138 KV FEEDER (LINE 33332LM) OOS | |||
| Limerick 1 | 100 | ||||
| Limerick 2 | 100 | ||||
| Millstone 2 | 100 | ||||
| Millstone 3 | 100 | ||||
| Nine Mile Point 1 | 100 | ||||
| Nine Mile Point 2 | 100 | ||||
| Oyster Creek | 100 | ||||
| Peach Bottom 2 | 100 | ||||
| Peach Bottom 3 | 100 | ||||
| Pilgrim 1 | 100 | ||||
| Salem 1 | 100 | ||||
| Salem 2 | 100 | ||||
| Seabrook 1 | 100 | ||||
| Susquehanna 1 | 99 | LIMITED BY GENERATOR CAPABILITY CURVE | * | ||
| Susquehanna 2 | 44 | INCREASING POWER | * | ||
| Three Mile Island 1 | 100 | ||||
| Vermont Yankee | 100 |
Region 2
| Unit | Power | Down | Reason or Comment | Change in report (*) | Number of Scrams (#) |
|---|---|---|---|---|---|
| Browns Ferry 1 | 100 | 161 KV (1 OF 2) LINES OOS | |||
| Browns Ferry 2 | 100 | 161 KV (1 OF 2) LINES OOS | |||
| Browns Ferry 3 | 100 | 161 KV (1 OF 2) LINES OOS | |||
| Brunswick 1 | 100 | ||||
| Brunswick 2 | 97 | TWO CONTROL RODS INSERTED FOR FUEL LEAK SUPPRESSION COASTDOWN TO REFUELING OUTAGE | * | ||
| Catawba 1 | 75 | HOLDING FOR FUEL CONDITIONING | * | ||
| Catawba 2 | 100 | * | |||
| Crystal River 3 | 0 | 09/25/2009 | DEFUELED - CONT. TENSIONING ON HOLD | ||
| Farley 1 | 100 | ||||
| Farley 2 | 100 | ||||
| Harris 1 | 100 | ||||
| Hatch 1 | 100 | ||||
| Hatch 2 | 100 | ||||
| McGuire 1 | 100 | ||||
| McGuire 2 | 100 | ||||
| North Anna 1 | 100 | ||||
| North Anna 2 | 100 | ||||
| Oconee 1 | 100 | ||||
| Oconee 2 | 100 | ||||
| Oconee 3 | 100 | ||||
| Robinson 2 | 100 | ||||
| Saint Lucie 1 | 100 | ||||
| Saint Lucie 2 | 100 | ||||
| Sequoyah 1 | 100 | ||||
| Sequoyah 2 | 0 | 10/14/2012 | REFUELING OUTAGE | ||
| Summer | 100 | ||||
| Surry 1 | 100 | ||||
| Surry 2 | 100 | ||||
| Turkey Point 3 | 99 | REDUCED POWER DUE TO EXTENDED POWER UPRATE OUTAGE ISSUES | |||
| Turkey Point 4 | 0 | 11/04/2012 | DEFUELED - REFUELING OUTAGE | ||
| Vogtle 1 | 100 | ||||
| Vogtle 2 | 100 | ||||
| Watts Bar 1 | 100 |
Region 3
| Unit | Power | Down | Reason or Comment | Change in report (*) | Number of Scrams (#) |
|---|---|---|---|---|---|
| Braidwood 1 | 100 | ||||
| Braidwood 2 | 100 | ||||
| Byron 1 | 100 | ||||
| Byron 2 | 100 | ||||
| Clinton | 97 | 100% ELECTRICAL CAPABILITY | |||
| D.C. Cook 1 | 100 | ||||
| D.C. Cook 2 | 100 | ||||
| Davis-Besse | 100 | ||||
| Dresden 2 | 100 | ||||
| Dresden 3 | 100 | ||||
| Duane Arnold | 100 | ||||
| Fermi 2 | 0 | 11/07/2012 | FORCED OUTAGE - SEE EN #48487 | ||
| Kewaunee | 100 | ||||
| La Salle 1 | 100 | ||||
| La Salle 2 | 97 | COASTDOWN TO REFUELING OUTAGE | |||
| Monticello | 100 | ||||
| Palisades | 100 | ||||
| Perry 1 | 90 | INCREASING POWER TO 100% | * | ||
| Point Beach 1 | 100 | ||||
| Point Beach 2 | 100 | ||||
| Prairie Island 1 | 0 | 10/22/2012 | REFUELING OUTAGE | ||
| Prairie Island 2 | 100 | ||||
| Quad Cities 1 | 100 | ||||
| Quad Cities 2 | 100 |
Region 4
| Unit | Power | Down | Reason or Comment | Change in report (*) | Number of Scrams (#) |
|---|---|---|---|---|---|
| Arkansas Nuclear 1 | 100 | ||||
| Arkansas Nuclear 2 | 100 | ||||
| Callaway | 100 | ||||
| Columbia Generating Station | 100 | ||||
| Comanche Peak 1 | 100 | ||||
| Comanche Peak 2 | 100 | ||||
| Cooper | 100 | ||||
| Diablo Canyon 1 | 100 | ||||
| Diablo Canyon 2 | 100 | ||||
| Fort Calhoun | 0 | 04/09/2011 | DEFUELED - REFUELING OUTAGE | ||
| Grand Gulf 1 | 0 | 12/29/2012 | FORCED OUTAGE - AUTOMATIC SCRAM. SEE EN #48637 | * | |
| Palo Verde 1 | 100 | ||||
| Palo Verde 2 | 100 | ||||
| Palo Verde 3 | 100 | ||||
| River Bend 1 | 100 | ||||
| San Onofre 2 | 0 | 01/09/2012 | REFUELING OUTAGE | ||
| San Onofre 3 | 0 | 01/31/2012 | DEFUELED - FORCED OUTAGE - S/G REPAIR | ||
| South Texas 1 | 100 | ||||
| South Texas 2 | 100 | ||||
| Waterford 3 | 0 | 10/17/2012 | REFUELING OUTAGE | ||
| Wolf Creek 1 | 100 |