Power Reactor Status Report for April 12, 2012
UNEVALUATED INFORMATION PROVIDED BY THE FACILITY
On this page:
Region 1
| Unit | Power | Down | Reason or Comment | Change in report (*) | Number of Scrams (#) |
|---|---|---|---|---|---|
| Beaver Valley 1 | 0 | 04/08/2012 | REFUELING OUTAGE | ||
| Beaver Valley 2 | 100 | ||||
| Calvert Cliffs 1 | 95 | HOLDING POWER FOR FUEL SOAK | * | ||
| Calvert Cliffs 2 | 100 | ||||
| FitzPatrick | 100 | ||||
| Ginna | 100 | ||||
| Hope Creek 1 | 95 | COASTDOWN TO REFUELING OUTAGE | |||
| Indian Point 2 | 100 | ||||
| Indian Point 3 | 11 | INCREASING POWER | * | ||
| Limerick 1 | 100 | HIGH VOLTAGE ALERT | |||
| Limerick 2 | 100 | HIGH VOLTAGE ALERT | |||
| Millstone 2 | 100 | ||||
| Millstone 3 | 100 | ||||
| Nine Mile Point 1 | 100 | ||||
| Nine Mile Point 2 | 0 | 04/08/2012 | REFUELING OUTAGE | * | |
| Oyster Creek | 100 | ||||
| Peach Bottom 2 | 100 | * | |||
| Peach Bottom 3 | 100 | * | |||
| Pilgrim 1 | 100 | ||||
| Salem 1 | 100 | ||||
| Salem 2 | 100 | ||||
| Seabrook 1 | 85 | HOLDING POWER BASED ON GENERATOR STATOR COOLING DELTA T LIMIT | |||
| Susquehanna 1 | 0 | 03/31/2012 | REFUELING OUTAGE HIGH SYSTEM VOLTAGE ACTION | * | |
| Susquehanna 2 | 100 | HIGH SYSTEM VOLTAGE ACTION | |||
| Three Mile Island 1 | 100 | HIGH SYSTEM VOLTAGE ACTION | |||
| Vermont Yankee | 86 | INCREASING POWER | * |
Region 2
| Unit | Power | Down | Reason or Comment | Change in report (*) | Number of Scrams (#) |
|---|---|---|---|---|---|
| Browns Ferry 1 | 100 | ||||
| Browns Ferry 2 | 100 | ||||
| Browns Ferry 3 | 0 | 04/07/2012 | REFUELING OUTAGE | ||
| Brunswick 1 | 0 | 02/23/2012 | REFUELING OUTAGE | ||
| Brunswick 2 | 100 | ||||
| Catawba 1 | 0 | 04/04/2012 | FORCED OUTAGE. SEE EN #47805 | ||
| Catawba 2 | 0 | 03/10/2012 | REFUELING OUTAGE | ||
| Crystal River 3 | 0 | 09/25/2009 | DEFUELED - CONTAINMENT TENSIONING ON HOLD | ||
| Farley 1 | 0 | 04/01/2012 | REFUELING OUTAGE | * | |
| Farley 2 | 100 | ||||
| Harris 1 | 95 | COASTDOWN TO REFUELING OUTAGE | * | ||
| Hatch 1 | 100 | ||||
| Hatch 2 | 100 | ||||
| McGuire 1 | 100 | ||||
| McGuire 2 | 100 | ||||
| North Anna 1 | 0 | 03/10/2012 | DEFUELED | ||
| North Anna 2 | 100 | ||||
| Oconee 1 | 100 | ||||
| Oconee 2 | 100 | ||||
| Oconee 3 | 79 | COASTDOWN TO REFUELING OUTAGE | * | ||
| Robinson 2 | 100 | ||||
| Saint Lucie 1 | 0 | 04/07/2012 | SHUTDOWN FOR WATERBOX REPAIR | ||
| Saint Lucie 2 | 100 | ||||
| Sequoyah 1 | 100 | ||||
| Sequoyah 2 | 100 | ||||
| Summer | 100 | ||||
| Surry 1 | 100 | ||||
| Surry 2 | 100 | ||||
| Turkey Point 3 | 0 | 02/26/2012 | DEFUELED | ||
| Turkey Point 4 | 100 | ||||
| Vogtle 1 | 100 | ||||
| Vogtle 2 | 100 | ||||
| Watts Bar 1 | 100 |
Region 3
| Unit | Power | Down | Reason or Comment | Change in report (*) | Number of Scrams (#) |
|---|---|---|---|---|---|
| Braidwood 1 | 94 | COASTDOWN TO REFUELING OUTAGE | * | ||
| Braidwood 2 | 100 | ||||
| Byron 1 | 99 | FEED WATER FLOW INVESTIGATION - POWER LIMITED TO 99.2% | * | ||
| Byron 2 | 100 | FEED WATER FLOW INVESTIGATION - POWER LIMITED TO 99.9% | |||
| Clinton | 97 | 100% ELECTRICAL CAPABILITY | |||
| D.C. Cook 1 | 100 | HIGH VOLTAGE ACTION | * | ||
| D.C. Cook 2 | 0 | 03/21/2012 | DEFUELED HIGH VOLTAGE ACTION | * | |
| Davis-Besse | 100 | ||||
| Dresden 2 | 100 | ||||
| Dresden 3 | 100 | ||||
| Duane Arnold | 100 | ||||
| Fermi 2 | 0 | 03/25/2012 | REFUELING OUTAGE - BOTH 345KV LINES OOS FOR PM | ||
| Kewaunee | 0 | 04/05/2012 | REFUELING OUTAGE | ||
| La Salle 1 | 100 | ||||
| La Salle 2 | 100 | ||||
| Monticello | 100 | ||||
| Palisades | 0 | 04/08/2012 | REFUELING OUTAGE | ||
| Perry 1 | 100 | ||||
| Point Beach 1 | 100 | ||||
| Point Beach 2 | 100 | ||||
| Prairie Island 1 | 100 | ||||
| Prairie Island 2 | 0 | 02/21/2012 | DEFUELED | ||
| Quad Cities 1 | 100 | ||||
| Quad Cities 2 | 0 | 03/19/2012 | REFUELING OUTAGE |
Region 4
| Unit | Power | Down | Reason or Comment | Change in report (*) | Number of Scrams (#) |
|---|---|---|---|---|---|
| Arkansas Nuclear 1 | 100 | ||||
| Arkansas Nuclear 2 | 100 | ||||
| Callaway | 98 | TURBINE CONTROL OSCILLATIONS | |||
| Columbia Generating Station | 100 | ||||
| Comanche Peak 1 | 100 | ||||
| Comanche Peak 2 | 99 | 100% TURBINE LOAD | |||
| Cooper | 100 | ||||
| Diablo Canyon 1 | 100 | ||||
| Diablo Canyon 2 | 100 | ||||
| Fort Calhoun | 0 | 04/09/2011 | REFUELING OUTAGE | ||
| Grand Gulf 1 | 0 | 02/19/2012 | REFUELING OUTAGE | ||
| Palo Verde 1 | 80 | REDUCED POWER FOR FEEDWATER HEATER REPAIR | |||
| Palo Verde 2 | 100 | ||||
| Palo Verde 3 | 0 | 03/16/2012 | REFUELING OUTAGE | * | |
| River Bend 1 | 100 | ||||
| San Onofre 2 | 0 | 01/09/2012 | REFUELING OUTAGE | ||
| San Onofre 3 | 0 | 01/31/2012 | FORCED OUTAGE - S/G REPAIR | ||
| South Texas 1 | 100 | ||||
| South Texas 2 | 0 | 11/28/2011 | HEATUP IN PROGRESS | ||
| Waterford 3 | 100 | ||||
| Wolf Creek 1 | 100 |