Power Reactor Status Report for October 3, 2008
UNEVALUATED INFORMATION PROVIDED BY THE FACILITY
On this page:
Region 1
| Unit | Power | Down | Reason or Comment | Change in report (*) | Number of Scrams (#) |
|---|---|---|---|---|---|
| Beaver Valley 1 | 100 | ||||
| Beaver Valley 2 | 100 | ||||
| Calvert Cliffs 1 | 100 | ||||
| Calvert Cliffs 2 | 100 | ||||
| FitzPatrick | 0 | 09/14/2008 | REFUELING OUTAGE | ||
| Ginna | 100 | ||||
| Hope Creek 1 | 100 | ||||
| Indian Point 2 | 100 | ||||
| Indian Point 3 | 100 | ||||
| Limerick 1 | 100 | ||||
| Limerick 2 | 100 | ||||
| Millstone 2 | 100 | ||||
| Millstone 3 | 100 | ||||
| Nine Mile Point 1 | 100 | ||||
| Nine Mile Point 2 | 100 | ||||
| Oyster Creek | 98 | HOLDING POWER DUE TO CONTROL VALVE LIMITATION FOR TURBINE | |||
| Peach Bottom 2 | 0 | 09/14/2008 | REFUELING OUTAGE | ||
| Peach Bottom 3 | 100 | ||||
| Pilgrim 1 | 100 | LOCAL ISO MAY REQUEST STATION TO REDUCE POWER TO 500MW ELECTRICAL NET AS A CONTINGENCY DUE TO WORK ON GRID | |||
| Salem 1 | 100 | ||||
| Salem 2 | 100 | ||||
| Seabrook 1 | 100 | * | |||
| Susquehanna 1 | 94 | 100% ELECTRICAL CAPABILITY | |||
| Susquehanna 2 | 100 | ||||
| Three Mile Island 1 | 100 | ||||
| Vermont Yankee | 99 |
Region 2
| Unit | Power | Down | Reason or Comment | Change in report (*) | Number of Scrams (#) |
|---|---|---|---|---|---|
| Browns Ferry 1 | 100 | ONE COOLING TOWER TRANSFORMER OOS - 161KV TRINITY LINE OOS FOR APPROXIMATELY 36 HOURS | |||
| Browns Ferry 2 | 100 | ONE COOLING TOWER TRANSFORMER OOS - 161KV TRINITY LINE OOS FOR APPROXIMATELY 36 HOURS | |||
| Browns Ferry 3 | 100 | ONE COOLING TOWER TRANSFORMER OOS - 161KV TRINITY LINE OOS FOR APPROXIMATELY 36 HOURS | |||
| Brunswick 1 | 100 | ||||
| Brunswick 2 | 100 | ||||
| Catawba 1 | 100 | ||||
| Catawba 2 | 100 | ||||
| Crystal River 3 | 100 | ||||
| Farley 1 | 100 | ||||
| Farley 2 | 98 | COASTDOWN TO REFUELING OUTAGE | * | ||
| Harris 1 | 100 | ||||
| Hatch 1 | 100 | ||||
| Hatch 2 | 100 | ||||
| McGuire 1 | 0 | 09/20/2008 | REFUELING OUTAGE - DEFUELED | * | |
| McGuire 2 | 100 | ||||
| North Anna 1 | 100 | ||||
| North Anna 2 | 0 | 09/13/2008 | REFUELING OUTAGE - CORE RELOAD COMPLETED | ||
| Oconee 1 | 100 | ||||
| Oconee 2 | 100 | ||||
| Oconee 3 | 100 | ||||
| Robinson 2 | 0 | 09/25/2008 | REFUELING OUTAGE | ||
| Saint Lucie 1 | 100 | ||||
| Saint Lucie 2 | 100 | ||||
| Sequoyah 1 | 100 | ||||
| Sequoyah 2 | 100 | ||||
| Summer | 100 | ||||
| Surry 1 | 100 | ||||
| Surry 2 | 100 | ||||
| Turkey Point 3 | 100 | ||||
| Turkey Point 4 | 100 | ||||
| Vogtle 1 | 100 | ||||
| Vogtle 2 | 0 | 09/14/2008 | DEFUELED | ||
| Watts Bar 1 | 100 |
Region 3
| Unit | Power | Down | Reason or Comment | Change in report (*) | Number of Scrams (#) |
|---|---|---|---|---|---|
| Braidwood 1 | 100 | ||||
| Braidwood 2 | 100 | ||||
| Byron 1 | 100 | ||||
| Byron 2 | 100 | * | |||
| Clinton | 96 | 100% ELECTRICAL CAPABILITY | * | ||
| D.C. Cook 1 | 0 | 09/20/2008 | SEE EN #44507. | ||
| D.C. Cook 2 | 100 | ||||
| Davis-Besse | 100 | ||||
| Dresden 2 | 98 | 100% ELECTRICAL CAPABILITY | * | ||
| Dresden 3 | 93 | COASTDOWN TO REFUELING OUTAGE | |||
| Duane Arnold | 98 | 100% ELECTRICAL CAPABILITY | |||
| Fermi 2 | 100 | ||||
| Kewaunee | 100 | ||||
| La Salle 1 | 23 | INCREASING POWER | * | ||
| La Salle 2 | 100 | ||||
| Monticello | 100 | ||||
| Palisades | 100 | ||||
| Perry 1 | 100 | ||||
| Point Beach 1 | 100 | ||||
| Point Beach 2 | 100 | ||||
| Prairie Island 1 | 100 | ||||
| Prairie Island 2 | 0 | 09/19/2008 | DEFUELED | ||
| Quad Cities 1 | 98 | 100% ELECTRICAL CAPABILITY | |||
| Quad Cities 2 | 97 | 100% ELECTRICAL CAPABILITY | * |
Region 4
| Unit | Power | Down | Reason or Comment | Change in report (*) | Number of Scrams (#) |
|---|---|---|---|---|---|
| Arkansas Nuclear 1 | 100 | ||||
| Arkansas Nuclear 2 | 100 | ||||
| Callaway | 100 | ||||
| Columbia Generating Station | 100 | ||||
| Comanche Peak 1 | 0 | 09/27/2008 | REFUELING OUTAGE - FUEL MOVEMENT IN PROGRESS | ||
| Comanche Peak 2 | 100 | ||||
| Cooper | 100 | ||||
| Diablo Canyon 1 | 100 | ||||
| Diablo Canyon 2 | 100 | ||||
| Fort Calhoun | 100 | ||||
| Grand Gulf 1 | 0 | 09/21/2008 | REFUELING OUTAGE - FUEL MOVEMENT IN PROGRESS | ||
| Palo Verde 1 | 100 | ||||
| Palo Verde 2 | 100 | ||||
| Palo Verde 3 | 100 | * | |||
| River Bend 1 | 100 | ||||
| San Onofre 2 | 99 | ||||
| San Onofre 3 | 75 | REDUCED POWER DUE TO LP EXTRACTION STEAM VALVE BELLOWS LEAK AND CONDENSER TUBE LEAK. MAINTENANCE ONGOING. | * | ||
| South Texas 1 | 100 | ||||
| South Texas 2 | 87 | COASTDOWN TO REFUELING OUTAGE | |||
| Waterford 3 | 100 | ||||
| Wolf Creek 1 | 100 |
Page Last Reviewed/Updated Tuesday, August 25, 2026