The U.S. Nuclear Regulatory Commission is in the process of rescinding or revising guidance and policies posted on this webpage in accordance with Executive Order 14151 Ending Radical and Wasteful Government DEI Programs and Preferencing, and Executive Order 14168 Defending Women From Gender Ideology Extremism and Restoring Biological Truth to the Federal Government. In the interim, any previously issued diversity, equity, inclusion, or gender-related guidance on this webpage should be considered rescinded that is inconsistent with these Executive Orders.

Morning Report for April 12, 2006

Headquarters Daily Report

To top of page

REGION I

Management Change at Oyster Creek Generating Station

Licensee/Facility:

AMERGEN ENERGY CO., LLC
Oyster Creek
FORKED RIVER, New Jersey
Dockets: 05000219
[1] GE-2
License No:
Notification:

MR Number: 1-2006-0005
Date: 04/12/2006

E-MAIL from Licensee

Discussion:

On April 12, Exelon Nuclear announced that Tim Rausch has been named Site Vice President at the Oyster Creek Generating Station. Mr. Rausch most recently served as the Mid-Atlantic Corporate Engineering Director for Exelon. Mr. Rausch previously served as the Plant General Manager at First Energy's Perry Nuclear Power Station. He has held Senior Reactor Operator licenses at the Perry and Oyster Creek plants.

Mr. Rausch will be replacing Bud Swenson, who will be moving to a vice president role at Exelon Power in Kennett Square, focusing on merger integration and market mitigation strategies.

Accession Numbers:

Accession No Accession Date
ML061020568 04/12/2006

Contacts:

Name Office Abbrev Phone No E-Mail
ROSEBROOK, ANDREW A R1 (610) 337-5199 AAR@nrc.gov

Page Last Reviewed/Updated Thursday, March 25, 2021