The U.S. Nuclear Regulatory Commission is in the process of rescinding or revising guidance and policies posted on this webpage in accordance with Executive Order 14151 Ending Radical and Wasteful Government DEI Programs and Preferencing, and Executive Order 14168 Defending Women From Gender Ideology Extremism and Restoring Biological Truth to the Federal Government. In the interim, any previously issued diversity, equity, inclusion, or gender-related guidance on this webpage should be considered rescinded that is inconsistent with these Executive Orders.

Morning Report for November 22, 1999

                       Headquarters Daily Report

                         NOVEMBER 22, 1999

***************************************************************************
                    REPORT             NEGATIVE            NO INPUT
                    ATTACHED           INPUT RECEIVED      RECEIVED

HEADQUARTERS                           X
REGION I                               X
REGION II                              X
REGION III          X
REGION IV                              X
PRIORITY ATTENTION REQUIRED  MORNING REPORT - REGION III  NOV. 22, 1999

Licensee/Facility:                     Notification:

Commonwealth Edison Co.                MR Number: 3-99-0094
La Salle 1                             Date: 11/22/99
Marseilles,Illinois                    SRI via LAN
Dockets: 50-373
BWR/GE-5

Subject: LASALLE UNIT 1 RESTART FROM PLANNED REFUELING OUTAGE

Discussion:

On November 22, 1999, at 7:07 a.m. (CST), LaSalle County Station
operations personnel synchronized the Unit 1 main turbine generator to
the grid completing Refueling Outage 8 (RFO-8). Major activities, in
addition to refueling the reactor, completed during this 29-day outage
included: 1) Noble Metals Chemical Addition; 2) Modification of Jet Pumps
9 and 10 to Replace the Inlet Mixers; 3) 1A and 1B Reactor Recirculation
Pump Seal Replacements; 4) 1B Reactor Recirculation Pump Suction Valve
Overhaul; and 5) Condenser Chemical Cleaning and Eddy Current Testing.

Regional Action:

Resident inspectors observed portions of plant outage and restart
activities, and will continue to monitor power ascension.

Contact:  Melvyn Leach               (630)829-9705